SH 70 @ Quitaque River
0105-04-047 · let Jun 2, 2026 · Motley, Childress · Bridge Replacement
$3,403,214Low bid: SKYLINE BRIDGE LLC+2.2% vs estimate $3,331,357
$275,246Left on the table8.1% gap to the second bid
9BiddersSpread 76% low to high
64Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SKYLINE BRIDGE LLC | $3,403,214 | 2.2% | $275,246 | 6+$156,932 | 3-$314,140 | |
| 2 | TUCAN CONTRACTING, LLC | $3,678,460 | +8.1% | 10.4% | $254,208 | 6+$384,977 | 2-$291,163 |
| 3 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $3,932,668 | +15.6% | 18.1% | $27,494 | 4+$243,216 | 2-$258,463 |
| 4 | ALTUS CONSTRUCTION LLC | $3,960,162 | +16.4% | 18.9% | $84,761 | 2+$242,165 | 3-$136,345 |
| 5 | COPPELL CONSTRUCTION CO., INC. | $4,044,923 | +18.9% | 21.4% | $509,055 | 7+$347,901 | 2-$116,188 |
| 6 | GILVIN-TERRILL, LTD. | $4,553,977 | +33.8% | 36.7% | $315,694 | ||
| 7 | EARTH BUILDERS, L.P. | $4,869,671 | +43.1% | 46.2% | $505,300 | ||
| 8 | J. LEE MILLIGAN, INC. | $5,374,971 | +57.9% | 61.3% | $630,928 | ||
| 9 | L A FULLER & SONS CONSTRUCTION, LTD. | $6,005,898 | +76.5% | 80.3% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
SKYLINE BRIDGE LLC vs TUCAN CONTRACTING, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 442-7007 STR STEEL (MISC NON-BRIDGE) | 4,270 LB | $8.00 | $44.28 | $11.11 | $154,916 |
| 422-7001 REINF CONC SLAB | 18,005 SF | $24.00 | $32.40 | $24.45 | $151,242 |
| 416-7006 DRILL SHAFT (36 IN) | 873 LF | $270.00 | $378.00 | $280.58 | $94,284 |
| 450-7024 RAIL (TY SSTR) | 1,060 LF | $98.00 | $162.00 | $69.92 | $67,840 |
| 100-7002 PREPARING ROW | 30 STA | $2,750.00 | $1,080.00 | $6,072.92 | -$50,100 |
| 420-7059 CL C CONC(PILE ENCASEMENT) | 174 LF | $685.00 | $432.00 | $435.92 | -$44,022 |
| 425-7003 PRESTR CONC GIRDER (TX40) | 3,482.5 LF | $230.00 | $220.48 | $213.86 | -$33,153 |
| 416-7002 DRILL SHAFT (18 IN) | 120 LF | $250.00 | $513.00 | $161.72 | $31,560 |
| 500-7001 MOBILIZATION | 1 LS | $300,000.00 | $270,000.00 | $523,850.32 | -$30,000 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $60,000.00 | $86,400.00 | $136,676.66 | $26,400 |
| 420-7022 CL C CONC (CAP) | 64.4 CY | $2,000.00 | $1,620.00 | $1,543.38 | -$24,472 |
| 552-7003 WIRE FENCE (TY C) | 1,665 LF | $21.00 | $8.64 | $12.12 | -$20,579 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 800 LF | $100.00 | $124.20 | $52.29 | $19,360 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 525 CY | $185.00 | $216.00 | $190.61 | $16,275 |
| 420-7038 CL C CONC (COLUMN) | 33.1 CY | $2,350.00 | $1,944.00 | $1,548.37 | -$13,439 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 800 LF | $38.00 | $21.60 | $12.08 | -$13,120 |
| 247-7090 FL BS (CMP IN PLC)(TY A GR 1-2) (10") | 1,100 SY | $55.00 | $43.20 | $18.50 | -$12,980 |
| 540-7002 MTL W-BEAM GD FEN (STEEL POST) | 1,550 LF | $31.50 | $39.64 | $30.74 | $12,617 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 86 CY | $600.00 | $702.00 | $616.83 | $8,772 |
| 105-7030 RMV (10") TRT/UNTRT BASE & ASPH PAV | 1,100 SY | $12.00 | $19.42 | $5.99 | $8,162 |
Positive: the low bidder was cheaper on that item. These 20 items account for $349,562 of the $275,246 gap.
SKYLINE BRIDGE LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7090 FL BS (CMP IN PLC)(TY A GR 1-2) (10") | 1,100 SY | $55.00 | $18.50 | 2.97x | $40,154 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 800 LF | $100.00 | $52.29 | 1.91x | $38,169 |
| 316-7012 ASPH (CRS-2P) | 880 GAL | $30.00 | $4.37 | 6.86x | $22,553 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 800 LF | $38.00 | $12.08 | 3.14x | $20,733 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 800 LF | $30.00 | $7.54 | 3.98x | $17,972 |
| 354-7053 PLANE ASPH CONC PAV(4") | 646 SY | $30.00 | $3.14 | 9.55x | $17,351 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $2,400.00 | $11,585.04 | 0.21x | -$137,776 |
| 100-7002 PREPARING ROW | 30 STA | $2,750.00 | $6,072.92 | 0.45x | -$99,688 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $60,000.00 | $136,676.66 | 0.44x | -$76,677 |
TUCAN CONTRACTING, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 442-7007 STR STEEL (MISC NON-BRIDGE) | 4,270 LB | $44.28 | $11.11 | 3.99x | $141,630 |
| 450-7024 RAIL (TY SSTR) | 1,060 LF | $162.00 | $69.92 | 2.32x | $97,602 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 800 LF | $124.20 | $52.29 | 2.38x | $57,529 |
| 416-7002 DRILL SHAFT (18 IN) | 120 LF | $513.00 | $161.72 | 3.17x | $42,154 |
| 247-7090 FL BS (CMP IN PLC)(TY A GR 1-2) (10") | 1,100 SY | $43.20 | $18.50 | 2.34x | $27,174 |
| 354-7053 PLANE ASPH CONC PAV(4") | 646 SY | $32.38 | $3.14 | 10.31x | $18,889 |
| 100-7002 PREPARING ROW | 30 STA | $1,080.00 | $6,072.92 | 0.18x | -$149,788 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $2,160.00 | $11,585.04 | 0.19x | -$141,376 |
HODGES AND SON CONSTRUCTION COMPANY, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 420-7059 CL C CONC(PILE ENCASEMENT) | 174 LF | $965.00 | $435.92 | 2.21x | $92,061 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 800 LF | $145.00 | $52.29 | 2.77x | $74,169 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 800 LF | $65.00 | $12.08 | 5.38x | $42,333 |
| 247-7090 FL BS (CMP IN PLC)(TY A GR 1-2) (10") | 1,100 SY | $50.00 | $18.50 | 2.70x | $34,654 |
| 100-7002 PREPARING ROW | 30 STA | $1,500.00 | $6,072.92 | 0.25x | -$137,188 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $3,500.00 | $11,585.04 | 0.30x | -$121,276 |
ALTUS CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 30 STA | $13,068.63 | $6,072.92 | 2.15x | $209,871 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 800 LF | $52.45 | $12.08 | 4.34x | $32,293 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 525 CY | $31.66 | $190.61 | 0.17x | -$83,449 |
| 316-7124 AGGR (TY-L, GR-4)(SAC-A) | 16 CY | $116.94 | $1,900.00 | 0.06x | -$28,529 |
| 442-7007 STR STEEL (MISC NON-BRIDGE) | 4,270 LB | $5.41 | $11.11 | 0.49x | -$24,366 |
COPPELL CONSTRUCTION CO., INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 525 CY | $366.00 | $190.61 | 1.92x | $92,079 |
| 450-7024 RAIL (TY SSTR) | 1,060 LF | $135.00 | $69.92 | 1.93x | $68,982 |
| 403-7001 TEMPORARY SPL SHORING | 1,215 SF | $75.00 | $25.56 | 2.93x | $60,069 |
| 552-7003 WIRE FENCE (TY C) | 1,665 LF | $35.00 | $12.12 | 2.89x | $38,098 |
| 422-7013 APPROACH SLAB | 58 CY | $1,300.00 | $738.51 | 1.76x | $32,567 |
| 316-7012 ASPH (CRS-2P) | 880 GAL | $40.00 | $4.37 | 9.15x | $31,353 |
| 247-7090 FL BS (CMP IN PLC)(TY A GR 1-2) (10") | 1,100 SY | $41.00 | $18.50 | 2.22x | $24,754 |
| 100-7002 PREPARING ROW | 30 STA | $3,000.00 | $6,072.92 | 0.49x | -$92,188 |
| 316-7124 AGGR (TY-L, GR-4)(SAC-A) | 16 CY | $400.00 | $1,900.00 | 0.21x | -$24,000 |