US 87: 0143-01-068; OV
0143-01-068 · let Jul 1, 2026 · Bexar, San Antonio · Overlay
$2,314,232Low bid: TEXAS MATERIALS GROUP, INC.-10.0% vs estimate $2,571,223
$163,428Left on the table7.1% gap to the second bid
8BiddersSpread 54% low to high
66Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TEXAS MATERIALS GROUP, INC. | $2,314,232 | -10.0% | $163,428 | 0 | 4-$560,923 | |
| 2 | CLARK CONSTRUCTION OF TEXAS, INC. | $2,477,660 | +7.1% | -3.6% | $181,015 | 0 | 5-$629,095 |
| 3 | HUNTER INDUSTRIES, LTD. | $2,658,674 | +14.9% | 3.4% | $50,489 | 0 | 3-$390,809 |
| 4 | BOBCAT SERVICES, INC. | $2,709,164 | +17.1% | 5.4% | $16,476 | 0 | 2-$338,846 |
| 5 | DEAN WORD COMPANY, LTD. | $2,725,640 | +17.8% | 6.0% | $167,753 | 0 | 2-$415,990 |
| 6 | ALLEN KELLER COMPANY | $2,893,393 | +25.0% | 12.5% | $48,759 | ||
| 7 | H. L. ZUMWALT CONSTRUCTION, INC. | $2,942,152 | +27.1% | 14.4% | $613,932 | ||
| 8 | LONE STAR PAVING COMPANY | $3,556,084 | +53.7% | 38.3% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
TEXAS MATERIALS GROUP, INC. vs CLARK CONSTRUCTION OF TEXAS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 344-7031 SP MIXES SP-C SAC-B PG76-22 | 14,591 TON | $88.00 | $97.38 | $97.84 | $136,864 |
| 3006-7001 UNDERSEAL COURSE | 25,376 GAL | $3.60 | $5.60 | $3.65 | $50,752 |
| 354-7030 PLANE ASPH CONC PAV(0" TO 0.5") | 126,878 SY | $0.5000 | $0.2000 | $0.5109 | -$38,063 |
| 500-7001 MOBILIZATION | 1 LS | $57,700.00 | $32,000.00 | $523,850.32 | -$25,700 |
| 3007-7001 BONDING COURSE | 3,241 GAL | $0.0100 | $4.55 | $3.32 | $14,714 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 9,986 EA | $1.50 | $0.5300 | $1.03 | -$9,686 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $3,150.00 | $1,840.25 | $11,585.04 | -$9,168 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 550 LF | $24.75 | $40.00 | $25.60 | $8,388 |
| 341-7046 D-GR HMA TY-D PG64-22 (LEVEL-UP) | 973 TON | $109.25 | $116.99 | $152.47 | $7,531 |
| 505-7001 TMA (STATIONARY) | 105 DAY | $25.00 | $90.00 | $217.57 | $6,825 |
| 666-7352 PAVEMENT SLER 24" | 2,102 LF | $0.5000 | $3.50 | $1.84 | $6,306 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 174 DAY | $25.00 | $58.00 | $87.82 | $5,742 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 116 SY | $54.00 | $93.93 | $49.06 | $4,632 |
| 112-7003 SUBGR WIDEN (OC) | 116 SY | $66.00 | $105.34 | $22.87 | $4,563 |
| 354-7051 PLANE ASPH CONC PAV(2") | 126,878 SY | $1.50 | $1.47 | $1.86 | -$3,806 |
| 351-7004 FLEXIBLE PAVEMENT STRUCTURE REPAIR(5") | 2,679 SY | $43.75 | $42.41 | $35.89 | -$3,590 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 3,294 EA | $1.50 | $0.5300 | $0.5715 | -$3,195 |
| 666-7354 PAVEMENT SLER (WORD) | 49 EA | $20.00 | $85.00 | $35.94 | $3,185 |
| 662-7017 WK ZN PAV MRK NON-REMOV (W)24"(SLD) | 2,102 LF | $2.00 | $3.50 | $3.95 | $3,153 |
| 666-7353 PAVEMENT SLER (ARROW) | 54 EA | $20.00 | $75.00 | $30.62 | $2,970 |
Positive: the low bidder was cheaper on that item. These 20 items account for $162,415 of the $163,428 gap.
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $57,700.00 | $523,850.32 | 0.11x | -$466,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $3,150.00 | $11,585.04 | 0.27x | -$59,045 |
| 505-7001 TMA (STATIONARY) | 105 DAY | $25.00 | $217.57 | 0.11x | -$20,220 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $1,500.00 | $9,253.78 | 0.16x | -$15,508 |
CLARK CONSTRUCTION OF TEXAS, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $32,000.00 | $523,850.32 | 0.06x | -$491,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $1,840.25 | $11,585.04 | 0.16x | -$68,214 |
| 354-7030 PLANE ASPH CONC PAV(0" TO 0.5") | 126,878 SY | $0.2000 | $0.5109 | 0.39x | -$39,446 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $1,158.68 | $9,253.78 | 0.13x | -$16,190 |
| 505-7001 TMA (STATIONARY) | 105 DAY | $90.00 | $217.57 | 0.41x | -$13,395 |