US 90 (FM 2830-FM 770 NORTH) OVERLAY
0028-04-084 · let Jul 2, 2026 · Liberty, Beaumont · Overlay
$1,939,953Low bid: TEXAS MATERIALS GROUP, INC.-8.0% vs estimate $2,109,577
$29,174Left on the table1.5% gap to the second bid
3BiddersSpread 3% low to high
39Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TEXAS MATERIALS GROUP, INC. | $1,939,953 | -8.0% | $29,174 | 0 | 4-$522,921 | |
| 2 | DURWOOD GREENE CONSTRUCTION CO. | $1,969,127 | +1.5% | -6.7% | $21,076 | 3+$64,282 | 3-$680,552 |
| 3 | HAYDEN PAVING, INC. | $1,990,204 | +2.6% | -5.7% | 1+$21,420 | 4-$629,048 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
TEXAS MATERIALS GROUP, INC. vs DURWOOD GREENE CONSTRUCTION CO., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 361-7046 FULL-DEPTH REPAIR CPJR (VAR DEPTH) | 180 CY | $1,481.25 | $640.00 | $1,415.64 | -$151,425 |
| 344-7030 SP MIXES SP-C SAC-A PG76-22 | 4,451 TON | $150.25 | $177.00 | $138.38 | $119,064 |
| 530-7022 INTRSCT, DRVWAYS, & TURNOUT (ACP) | 1,200 SY | $20.25 | $75.00 | $42.62 | $65,700 |
| 500-7001 MOBILIZATION | 1 LS | $147,000.00 | $85,000.00 | $523,850.32 | -$62,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $883.75 | $10,000.00 | $11,585.04 | $45,581 |
| 100-7002 PREPARING ROW | 19 STA | $2,614.00 | $700.00 | $6,072.92 | -$36,366 |
| 351-7009 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") | 600 SY | $91.00 | $110.00 | $77.78 | $11,400 |
| 354-7080 PLAN ASPH CONC PAV (3.5") | 2,029 SY | $4.75 | $10.00 | $3.74 | $10,652 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 60 DAY | $130.75 | $300.00 | $87.82 | $10,155 |
| 505-7001 TMA (STATIONARY) | 120 DAY | $330.00 | $250.00 | $217.57 | -$9,600 |
| 354-7095 PLANE ASPH PAV (0" TO 3.5") | 5,289 SY | $9.75 | $8.00 | $10.35 | -$9,256 |
| 644-7001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) | 62 EA | $621.50 | $750.00 | $696.14 | $7,967 |
| 341-7043 D-GR HMA TY-D PG64-22 | 3,338 TON | $130.00 | $132.00 | $133.94 | $6,676 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 9.25 CY | $835.75 | $1,500.00 | $616.83 | $6,144 |
| 505-7003 TMA (MOBILE OPERATION) | 10 DAY | $760.00 | $300.00 | $229.60 | -$4,600 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 575 LF | $27.25 | $35.00 | $25.60 | $4,456 |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) | 16,600 LF | $0.7500 | $0.5000 | $0.2040 | -$4,150 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 4 EA | $3,081.25 | $3,950.00 | $3,190.07 | $3,475 |
| 672-7004 REFL PAV MRKR TY II-A-A | 700 EA | $4.25 | $8.50 | $3.97 | $2,975 |
| 668-7089 PREFAB PM TY C (W)(24")(SLD) | 300 LF | $13.50 | $22.00 | $13.72 | $2,550 |
Positive: the low bidder was cheaper on that item. These 20 items account for $19,400 of the $29,174 gap.
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $147,000.00 | $523,850.32 | 0.28x | -$376,850 |
| 100-7002 PREPARING ROW | 19 STA | $2,614.00 | $6,072.92 | 0.43x | -$65,720 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $883.75 | $11,585.04 | 0.08x | -$53,506 |
| 530-7022 INTRSCT, DRVWAYS, & TURNOUT (ACP) | 1,200 SY | $20.25 | $42.62 | 0.48x | -$26,845 |
DURWOOD GREENE CONSTRUCTION CO.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 530-7022 INTRSCT, DRVWAYS, & TURNOUT (ACP) | 1,200 SY | $75.00 | $42.62 | 1.76x | $38,855 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 60 DAY | $300.00 | $87.82 | 3.42x | $12,731 |
| 354-7080 PLAN ASPH CONC PAV (3.5") | 2,029 SY | $10.00 | $3.74 | 2.67x | $12,695 |
| 500-7001 MOBILIZATION | 1 LS | $85,000.00 | $523,850.32 | 0.16x | -$438,850 |
| 361-7046 FULL-DEPTH REPAIR CPJR (VAR DEPTH) | 180 CY | $640.00 | $1,415.64 | 0.45x | -$139,616 |
| 100-7002 PREPARING ROW | 19 STA | $700.00 | $6,072.92 | 0.12x | -$102,086 |
HAYDEN PAVING, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 134-7004 BACKFILL (TY A OR B) | 82.77 STA | $470.00 | $211.21 | 2.23x | $21,420 |
| 500-7001 MOBILIZATION | 1 LS | $75,000.00 | $523,850.32 | 0.14x | -$448,850 |
| 100-7002 PREPARING ROW | 19 STA | $1,300.00 | $6,072.92 | 0.21x | -$90,686 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $2,200.00 | $11,585.04 | 0.19x | -$46,925 |
| 354-7095 PLANE ASPH PAV (0" TO 3.5") | 5,289 SY | $2.30 | $10.35 | 0.22x | -$42,587 |