US 57:0276-07-035; OV
0276-07-035 · let Aug 5, 2026 · Frio, San Antonio · Overlay
$7,430,847Low bid: CLARK CONSTRUCTION OF TEXAS, INC.-14.2% vs estimate $8,663,166
$90,323Left on the table1.2% gap to the second bid
6BiddersSpread 30% low to high
73Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | CLARK CONSTRUCTION OF TEXAS, INC. | $7,430,847 | -14.2% | $90,323 | 0 | 5-$1,115,966 | |
| 2 | HUNTER INDUSTRIES, LTD. | $7,521,170 | +1.2% | -13.2% | $1,011,140 | 0 | 2-$175,141 |
| 3 | ANDERSON COLUMBIA CO., INC. | $8,532,310 | +14.8% | -1.5% | $457,390 | 1+$69,676 | 1-$118,106 |
| 4 | LONE STAR PAVING COMPANY | $8,989,700 | +21.0% | 3.8% | $3,347 | 0 | 3-$612,937 |
| 5 | TEXAS MATERIALS GROUP, INC. | $8,993,047 | +21.0% | 3.8% | $687,378 | 0 | 2-$319,150 |
| 6 | CK NEWBERRY, LLC | $9,680,425 | +30.3% | 11.7% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
CLARK CONSTRUCTION OF TEXAS, INC. vs HUNTER INDUSTRIES, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 347-7002 TOM-C PG76-22 SAC-B | 17,580 TON | $130.12 | $103.18 | $130.62 | -$473,605 |
| 341-7056 D-GR HMA TY-D PG76-22 | 28,281 TON | $104.56 | $91.36 | $123.11 | -$373,309 |
| 3006-7001 UNDERSEAL COURSE | 76,155 GAL | $0.0100 | $4.54 | $3.65 | $344,982 |
| 500-7001 MOBILIZATION | 1 LS | $211,000.00 | $534,678.02 | $523,850.32 | $323,678 |
| 3007-7001 BONDING COURSE | 61,109 GAL | $0.0100 | $3.14 | $3.32 | $191,271 |
| 510-7002 ONE-WAY TRAF CONT (PILOT CAR) | 2,060 HR | $1.00 | $93.50 | $98.78 | $190,550 |
| 341-7059 D-GR HMA TY-D PG76-22 (LEVEL-UP) | 4,017 TON | $129.35 | $90.58 | $115.04 | -$155,739 |
| 354-7030 PLANE ASPH CONC PAV(0" TO 0.5") | 213,355 SY | $0.2600 | $0.5500 | $0.5109 | $61,873 |
| 351-7004 FLEXIBLE PAVEMENT STRUCTURE REPAIR(5") | 16,951 SY | $36.36 | $33.51 | $35.89 | -$48,310 |
| 480-7001 CLEAN EXIST CULVERTS | 25 EA | $500.00 | $2,300.00 | $1,712.97 | $45,000 |
| 510-7001 ONE-WAY TRAF CONT (FLAGGER CONT) | 510 HR | $1.00 | $77.00 | $46.94 | $38,760 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 412 DAY | $86.00 | $27.06 | $87.82 | -$24,283 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 38,671 EA | $0.5800 | $1.19 | $1.03 | $23,589 |
| 354-7082 PLANE ASPH CONC PAV (2.5") | 26,860 SY | $2.25 | $1.43 | $2.67 | -$22,025 |
| 530-7010 DRIVEWAYS (ACP) | 2,055 SY | $32.34 | $22.20 | $54.96 | -$20,838 |
| 662-7113 WK ZN PAV MRK SHT TERM (TAB)TY Y | 28,455 EA | $0.5800 | $1.19 | $1.11 | $17,358 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $2,165.00 | $3,290.52 | $11,585.04 | $14,632 |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) | 116,390 LF | $0.1600 | $0.0700 | $0.2040 | -$10,475 |
| 164-7015 DRILL SEED (TEMP_WARM_COOL) | 3,113 SY | $4.00 | $0.7000 | $0.1885 | -$10,273 |
| 164-7009 DRILL SEED (PERM_RURAL_SAND) | 3,113 SY | $4.00 | $0.8000 | $0.1844 | -$9,962 |
Positive: the low bidder was cheaper on that item. These 20 items account for $102,873 of the $90,323 gap.
CLARK CONSTRUCTION OF TEXAS, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $211,000.00 | $523,850.32 | 0.40x | -$312,850 |
| 3006-7001 UNDERSEAL COURSE | 76,155 GAL | $0.0100 | $3.65 | 0.00x | -$276,884 |
| 3007-7001 BONDING COURSE | 61,109 GAL | $0.0100 | $3.32 | 0.00x | -$202,344 |
| 510-7002 ONE-WAY TRAF CONT (PILOT CAR) | 2,060 HR | $1.00 | $98.78 | 0.01x | -$201,426 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $2,165.00 | $11,585.04 | 0.19x | -$122,461 |