Bid Tab X-ray: 6511-07-001

Nov 18, 2026 · Leon Sign up free
Set your company to personalize scores

FY27 - Leon HMA - 11

6511-07-001 · let Nov 18, 2026 · Leon, Bryan · Material Maintenance Project

$283,600Low bid: BIG CREEK CONSTRUCTION, LTD.-15.3% vs estimate $335,000
$4,400Left on the table1.6% gap to the second bid
3BiddersSpread 15% low to high
4Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1BIG CREEK CONSTRUCTION, LTD. $283,600-15.3% $4,400 0 0
2KNIFE RIVER CORPORATION - SOUTH $288,000+1.6%-14.0% $37,935 0 0
3TEXAS MATERIALS GROUP, INC. $325,935+14.9%-2.7% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.

Where the job was won

BIG CREEK CONSTRUCTION, LTD. vs KNIFE RIVER CORPORATION - SOUTH, biggest item swings
ItemQtyLow2ndMarket2nd minus low
8011-7055 D-GR HMA TY D PG 64-22 (PICKUP)2,000 TON $75.00$76.00$89.12 $2,000
8011-7091 D-GR HMA TY F PG 64-22 (PICKUP)500 TON $75.10$78.00$87.59 $1,450
8011-7092 D-GR HMA TY F PG 64-22 (DEL) SITE 1500 TON $96.10$98.00$101.37 $950
8011-7056 D-GR HMA TY D PG 64-22 (DEL) SITE 1500 TON $96.00$96.00$99.54 $0

Positive: the low bidder was cheaper on that item. These 4 items account for $4,400 of the $4,400 gap.