FY 2027 HOTMIX COLD-LAID-MATERIAL ONLY
6506-95-001 · let Nov 17, 2026 · Bell, Waco · Material Maintenance Project
$467,875Low bid: LONE STAR PAVING COMPANY-3.5% vs estimate $484,930
$27,375Left on the table5.9% gap to the second bid
3BiddersSpread 38% low to high
9Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | LONE STAR PAVING COMPANY | $467,875 | -3.5% | $27,375 | 0 | 0 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $495,250 | +5.9% | 2.1% | $151,313 | 0 | 0 |
| 3 | KNIFE RIVER CORPORATION - SOUTH | $646,563 | +38.2% | 33.3% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
LONE STAR PAVING COMPANY vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8013-7017 HMCL ACP TYPE D (DEL)(SITE 1) | 1,000 TON | $88.50 | $102.00 | $93.03 | $13,500 |
| 8013-7019 HMCL ACP TYPE D (DEL)(SITE 3) | 1,000 TON | $100.25 | $112.00 | $86.52 | $11,750 |
| 8013-7002 HMCL ACP TYPE B (DEL)(SITE 1) | 500 TON | $88.25 | $95.00 | $93.51 | $3,375 |
| 8013-7018 HMCL ACP TYPE D (DEL)(SITE 2) | 250 TON | $94.75 | $106.00 | $92.98 | $2,813 |
| 8013-7007 HMCL ACP TYPE B (DEL)(SITE 6) | 1,000 TON | $106.75 | $104.00 | $93.60 | -$2,750 |
| 8013-7020 HMCL ACP TYPE D (DEL)(SITE 4) | 250 TON | $108.25 | $106.00 | $101.29 | -$563 |
| 8013-7024 HMCL ACP TYPE D (DEL)(SITE 8) | 250 TON | $103.75 | $102.00 | $116.69 | -$438 |
| 8013-7023 HMCL ACP TYPE D (DEL)(SITE 7) | 250 TON | $106.75 | $106.00 | $104.72 | -$188 |
| 8013-7006 HMCL ACP TYPE B (DEL)(SITE 5) | 250 TON | $99.50 | $99.00 | $89.30 | -$125 |
Positive: the low bidder was cheaper on that item. These 9 items account for $27,375 of the $27,375 gap.