SH 7 F:SH 75 T:HOUSTON CO LINE -2
0335-01-040 · let Aug 8, 2025 · Leon, Bryan · Super-2 Highway
$21,287,953Low bid: BIG CREEK CONSTRUCTION, LTD.-11.9% vs estimate $24,159,203
$2,126,429Left on the table10.0% gap to the second bid
4BiddersSpread 39% low to high
103Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $21,287,953 | -11.9% | $2,126,429 | 1+$1,476,150 | 2-$3,324,461 | |
| 2 | KNIFE RIVER CORPORATION - SOUTH | $23,414,382 | +10.0% | -3.1% | $2,058,513 | 2+$771,332 | 3-$3,209,146 |
| 3 | A. L. HELMCAMP, INC. | $25,472,895 | +19.7% | 5.4% | $4,053,709 | 2+$2,003,548 | 1-$2,916,310 |
| 4 | VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC | $29,526,604 | +38.7% | 22.2% | 6+$5,641,364 | 1-$2,908,780 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs KNIFE RIVER CORPORATION - SOUTH, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 344-7020 SP MIXES SP-C SAC-A PG70-22 | 63,560 TON | $110.00 | $141.00 | $137.95 | $1,970,360 |
| 500-7001 MOBILIZATION | 1 LS | $2,000,000.00 | $699,861.00 | $523,850.32 | -$1,300,139 |
| 505-7002 TMA (MOBILE OPERATION) | 560 HR | $80.00 | $1,000.00 | $64.00 | $515,200 |
| 344-7009 SP MIXES SP-C PG64-22 | 16,433 TON | $95.00 | $122.00 | $131.13 | $443,691 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 30 MO | $3,000.00 | $13,700.00 | $11,585.04 | $321,000 |
| 100-7002 PREPARING ROW | 753 STA | $2,000.00 | $2,400.00 | $6,072.92 | $301,200 |
| 530-7010 DRIVEWAYS (ACP) | 4,939 SY | $55.00 | $105.00 | $54.96 | $246,950 |
| 275-7004 CEMENT TRT (EXIST MATL)(10") | 120,339 SY | $3.00 | $1.00 | $3.71 | -$240,678 |
| 423-7016 RETAINING WALL (CAST-IN-PLACE) | 4,839 SF | $130.00 | $81.00 | $115.72 | -$237,111 |
| 247-7044 FL BS (CMP IN PLC)(TY A GR 1-2) (6") | 120,339 SY | $14.00 | $12.50 | $12.30 | -$180,509 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 14,374 CY | $15.00 | $5.00 | $13.19 | -$143,740 |
| 466-7101 HEADWALL (CH - PW - 0) (DIA= 24 IN) | 7 EA | $7,000.00 | $21,100.00 | $8,593.16 | $98,700 |
| 354-7051 PLANE ASPH CONC PAV(2") | 362,382 SY | $1.50 | $1.75 | $1.86 | $90,596 |
| 110-7001 EXCAV (ROADWAY) | 71,957 CY | $15.00 | $16.00 | $11.68 | $71,957 |
| 467-7307 SET (TY II) (18 IN) (RCP) (6: 1) (C) | 138 EA | $900.00 | $1,410.00 | $1,382.82 | $70,380 |
| 403-7001 TEMPORARY SPL SHORING | 2,180 SF | $34.00 | $63.00 | $25.56 | $63,220 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 113,161 SY | $1.00 | $0.5000 | $1.43 | -$56,581 |
| 480-7001 CLEAN EXIST CULVERTS | 7 EA | $2,000.00 | $8,330.00 | $1,712.97 | $44,310 |
| 496-7004 REMOV STR (SET) | 183 EA | $300.00 | $540.00 | $514.07 | $43,920 |
| 466-7178 WINGWALL (PW - 1) (HW=8 FT) | 2 EA | $60,000.00 | $42,600.00 | $42,198.45 | -$34,800 |
Positive: the low bidder was cheaper on that item. These 20 items account for $2,087,927 of the $2,126,429 gap.
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 1KNIFE RIVER CORPORATION - SOUTH: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7002 TMA (MOBILE OPERATION) | 560 HR | $1,000.00 | $64.00 | 15.63x | $524,162 |
| 530-7010 DRIVEWAYS (ACP) | 4,939 SY | $105.00 | $54.96 | 1.91x | $247,170 |
| 100-7002 PREPARING ROW | 753 STA | $2,400.00 | $6,072.92 | 0.40x | -$2,765,710 |
| 275-7004 CEMENT TRT (EXIST MATL)(10") | 120,339 SY | $1.00 | $3.71 | 0.27x | -$325,685 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 14,374 CY | $5.00 | $13.19 | 0.38x | -$117,750 |
A. L. HELMCAMP, INC.: unbalanced items
Placed 3VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,975,355.81 | $523,850.32 | 5.68x | $2,451,505 |
| 247-7044 FL BS (CMP IN PLC)(TY A GR 1-2) (6") | 120,339 SY | $22.93 | $12.30 | 1.86x | $1,279,733 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 30 MO | $48,060.88 | $11,585.04 | 4.15x | $1,094,275 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 14,374 CY | $44.06 | $13.19 | 3.34x | $443,698 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 113,161 SY | $3.16 | $1.43 | 2.21x | $195,848 |
| 168-7001 VEGETATIVE WATERING | 1,132 TGL | $164.18 | $8.43 | 19.47x | $176,305 |
| 100-7002 PREPARING ROW | 753 STA | $2,210.00 | $6,072.92 | 0.36x | -$2,908,780 |