FM 636 at Willow Creek
0574-02-022 · let Sep 5, 2025 · Navarro, Dallas · Bridge Replacement
$9,649,382Low bid: INDUS ROAD & BRIDGE, INC.-8.0% vs estimate $10,486,887
$244,741Left on the table2.5% gap to the second bid
8BiddersSpread 29% low to high
353Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | INDUS ROAD & BRIDGE, INC. | $9,649,382 | -8.0% | $244,741 | 7+$1,253,090 | 2-$145,820 | |
| 2 | SKYLINE BRIDGE LLC | $9,894,124 | +2.5% | -5.7% | $80,100 | 9+$753,409 | 5-$696,166 |
| 3 | HIGHWAY 19 CONSTRUCTION LLC | $9,974,224 | +3.4% | -4.9% | $1,201,691 | 8+$930,130 | 2-$317,153 |
| 4 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $11,175,915 | +15.8% | 6.6% | $636,245 | 9+$1,380,824 | 3-$462,287 |
| 5 | A. L. HELMCAMP, INC. | $11,812,159 | +22.4% | 12.6% | $120,002 | 13+$3,013,906 | 2-$391,768 |
| 6 | TALBERT COMPANIES LLC | $11,932,161 | +23.7% | 13.8% | $64,225 | ||
| 7 | GREY SKY CONSTRUCTION LLC | $11,996,385 | +24.3% | 14.4% | $493,993 | ||
| 8 | HARPER BROTHERS CONSTRUCTION LLC | $12,490,379 | +29.4% | 19.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
INDUS ROAD & BRIDGE, INC. vs SKYLINE BRIDGE LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 28 STA | $14,000.00 | $2,000.00 | $6,072.92 | -$336,000 |
| 132-7010 EMBANK (FNL)(DC)(TY C2) | 801 CY | $327.00 | $40.00 | $22.38 | -$229,887 |
| 416-7004 DRILL SHAFT (24 IN) | 2,235 LF | $184.00 | $275.00 | $234.98 | $203,385 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 35 MO | $7,700.00 | $2,000.00 | $11,585.04 | -$199,500 |
| 423-7001 RETAINING WALL (MSE) | 3,537 SF | $70.00 | $125.00 | $74.07 | $194,535 |
| 403-7001 TEMPORARY SPL SHORING | 8,106 SF | $33.00 | $12.50 | $25.56 | -$166,173 |
| 500-7001 MOBILIZATION | 1 LS | $961,038.96 | $800,000.00 | $523,850.32 | -$161,039 |
| 512-7029 PORT CTB (MOVE)(F-SHAPE)(TY 1) | 2,250 LF | $8.00 | $50.00 | $9.04 | $94,500 |
| 275-7007 CEMENT TRT (EXIST MATL & NEW BASE)(8") | 5,433 SY | $5.50 | $22.00 | $2.34 | $89,645 |
| 432-7047 RIPRAP (STONE PROTECTION)(30 IN) | 5,929 CY | $127.00 | $141.00 | $160.54 | $83,006 |
| 247-7125 FL BS (CMP IN PLC)(TY D GR 1-2) (12") | 7,651 SY | $36.00 | $45.00 | $29.90 | $68,859 |
| 432-7048 RIPRAP (STONE PROTECTION)(36 IN) | 2,761 CY | $127.00 | $150.00 | $174.48 | $63,503 |
| 422-7002 REINF CONC SLAB (HPC) | 16,770 SF | $31.00 | $28.00 | $26.91 | -$50,310 |
| 506-7020 CONSTRUCTION EXITS (INSTALL) (TY 1) | 1,956 SY | $40.00 | $15.00 | $30.47 | -$48,900 |
| 425-7016 PRESTR CONC SLAB BEAM (4SB12) | 1,726.02 LF | $214.00 | $240.00 | $259.02 | $44,877 |
| 450-7009 RAIL (TY T223)(HPC) | 850 LF | $125.00 | $175.00 | $152.11 | $42,500 |
| 275-7006 CEMENT TRT (EXIST MATL & NEW BASE)(6") | 2,218 SY | $5.00 | $24.00 | $2.25 | $42,142 |
| 247-7102 FL BS (CMP IN PLC)(TY D GR 1-2) (10") | 2,102 SY | $35.00 | $55.00 | $25.28 | $42,040 |
| 260-7007 LIME TRT (EXIST MATL)(8") | 2,102 SY | $10.00 | $30.00 | $4.35 | $42,040 |
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 4,560 LF | $40.00 | $49.00 | $40.65 | $41,040 |
Positive: the low bidder was cheaper on that item. These 20 items account for -$139,738 of the $244,741 gap.
INDUS ROAD & BRIDGE, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $961,038.96 | $523,850.32 | 1.83x | $437,189 |
| 132-7010 EMBANK (FNL)(DC)(TY C2) | 801 CY | $327.00 | $22.38 | 14.61x | $244,002 |
| 100-7002 PREPARING ROW | 28 STA | $14,000.00 | $6,072.92 | 2.31x | $221,958 |
| 316-7012 ASPH (CRS-2P) | 4,642 GAL | $30.00 | $4.37 | 6.86x | $118,967 |
| 316-7071 ASPH (AC-15P, AC-20-5TR OR AC-20XP) | 3,826 GAL | $28.00 | $3.42 | 8.19x | $94,042 |
| 316-7211 AGGR (TY-PB, GR-4)(SAC-B) | 65 CY | $1,490.00 | $133.09 | 11.20x | $88,199 |
| 316-7171 AGGR (TY-B, GR-3)(SAC-B) | 48 CY | $1,200.00 | $184.71 | 6.50x | $48,734 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $40,000.00 | $136,676.66 | 0.29x | -$96,677 |
| 168-7001 VEGETATIVE WATERING | 6,610.9 TGL | $1.00 | $8.43 | 0.12x | -$49,143 |
SKYLINE BRIDGE LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7012 ASPH (CRS-2P) | 4,642 GAL | $29.50 | $4.37 | 6.75x | $116,646 |
| 275-7007 CEMENT TRT (EXIST MATL & NEW BASE)(8") | 5,433 SY | $22.00 | $2.34 | 9.42x | $106,832 |
| 316-7071 ASPH (AC-15P, AC-20-5TR OR AC-20XP) | 3,826 GAL | $30.00 | $3.42 | 8.77x | $101,694 |
| 316-7211 AGGR (TY-PB, GR-4)(SAC-B) | 65 CY | $1,600.00 | $133.09 | 12.02x | $95,349 |
| 512-7029 PORT CTB (MOVE)(F-SHAPE)(TY 1) | 2,250 LF | $50.00 | $9.04 | 5.53x | $92,161 |
| 344-7011 SP MIXES SP-C SAC-B PG64-22 | 339 TON | $325.00 | $130.31 | 2.49x | $65,999 |
| 247-7102 FL BS (CMP IN PLC)(TY D GR 1-2) (10") | 2,102 SY | $55.00 | $25.28 | 2.18x | $62,471 |
| 316-7171 AGGR (TY-B, GR-3)(SAC-B) | 48 CY | $1,400.00 | $184.71 | 7.58x | $58,334 |
| 260-7007 LIME TRT (EXIST MATL)(8") | 2,102 SY | $30.00 | $4.35 | 6.90x | $53,924 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 35 MO | $2,000.00 | $11,585.04 | 0.17x | -$335,476 |
| 100-7002 PREPARING ROW | 28 STA | $2,000.00 | $6,072.92 | 0.33x | -$114,042 |
| 403-7001 TEMPORARY SPL SHORING | 8,106 SF | $12.50 | $25.56 | 0.49x | -$105,869 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $50,000.00 | $136,676.66 | 0.37x | -$86,677 |
| 168-7001 VEGETATIVE WATERING | 6,610.9 TGL | $0.2500 | $8.43 | 0.03x | -$54,102 |
HIGHWAY 19 CONSTRUCTION LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 403-7001 TEMPORARY SPL SHORING | 8,106 SF | $55.00 | $25.56 | 2.15x | $238,636 |
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 4,560 LF | $75.00 | $40.65 | 1.85x | $156,647 |
| 508-7001 CONSTRUCTING DETOURS | 1,565 SY | $180.00 | $83.58 | 2.15x | $150,890 |
| 316-7012 ASPH (CRS-2P) | 4,642 GAL | $27.00 | $4.37 | 6.18x | $105,041 |
| 316-7071 ASPH (AC-15P, AC-20-5TR OR AC-20XP) | 3,826 GAL | $25.00 | $3.42 | 7.31x | $82,564 |
| 316-7211 AGGR (TY-PB, GR-4)(SAC-B) | 65 CY | $1,325.00 | $133.09 | 9.96x | $77,474 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 3 EA | $50,000.00 | $28,021.15 | 1.78x | $65,937 |
| 512-7053 PORT CTB (REMOVE)(F-SHAPE)(TY 1) | 4,560 LF | $25.00 | $13.39 | 1.87x | $52,943 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 35 MO | $5,000.00 | $11,585.04 | 0.43x | -$230,476 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $50,000.00 | $136,676.66 | 0.37x | -$86,677 |
HODGES AND SON CONSTRUCTION COMPANY, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,015,000.00 | $523,850.32 | 1.94x | $491,150 |
| 247-7125 FL BS (CMP IN PLC)(TY D GR 1-2) (12") | 7,651 SY | $60.00 | $29.90 | 2.01x | $230,291 |
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 4,560 LF | $80.00 | $40.65 | 1.97x | $179,447 |
| 251-7051 REWORK BS MTL (TY C)(8")(ORD COMP) | 5,433 SY | $25.00 | $2.89 | 8.65x | $120,129 |
| 512-7053 PORT CTB (REMOVE)(F-SHAPE)(TY 1) | 4,560 LF | $35.00 | $13.39 | 2.61x | $98,543 |
| 247-7102 FL BS (CMP IN PLC)(TY D GR 1-2) (10") | 2,102 SY | $60.00 | $25.28 | 2.37x | $72,981 |
| 275-7007 CEMENT TRT (EXIST MATL & NEW BASE)(8") | 5,433 SY | $15.00 | $2.34 | 6.42x | $68,801 |
| 316-7171 AGGR (TY-B, GR-3)(SAC-B) | 48 CY | $1,500.00 | $184.71 | 8.12x | $63,134 |
| 316-7211 AGGR (TY-PB, GR-4)(SAC-B) | 65 CY | $1,000.00 | $133.09 | 7.51x | $56,349 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 35 MO | $2,500.00 | $11,585.04 | 0.22x | -$317,976 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $50,000.00 | $136,676.66 | 0.37x | -$86,677 |
| 506-7020 CONSTRUCTION EXITS (INSTALL) (TY 1) | 1,956 SY | $1.00 | $30.47 | 0.03x | -$57,634 |
A. L. HELMCAMP, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,100,000.00 | $523,850.32 | 2.10x | $576,150 |
| 403-7001 TEMPORARY SPL SHORING | 8,106 SF | $75.00 | $25.56 | 2.93x | $400,756 |
| 422-7002 REINF CONC SLAB (HPC) | 16,770 SF | $48.00 | $26.91 | 1.78x | $353,698 |
| 420-7013 CL C CONC (ABUT)(HPC) | 115.2 CY | $4,000.00 | $1,329.26 | 3.01x | $307,670 |
| 420-7023 CL C CONC (CAP)(HPC) | 101.7 CY | $4,200.00 | $1,420.15 | 2.96x | $282,710 |
| 423-7001 RETAINING WALL (MSE) | 3,537 SF | $150.00 | $74.07 | 2.03x | $268,558 |
| 132-7008 EMBANK (FNL)(DC)(TY C1) | 13,045 CY | $35.00 | $17.39 | 2.01x | $229,726 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 3 EA | $95,000.00 | $28,021.15 | 3.39x | $200,937 |
| 420-7039 CL C CONC (COLUMN)(HPC) | 57.6 CY | $3,200.00 | $1,492.16 | 2.14x | $98,372 |
| 275-7007 CEMENT TRT (EXIST MATL & NEW BASE)(8") | 5,433 SY | $18.00 | $2.34 | 7.70x | $85,100 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 35 MO | $5,050.00 | $11,585.04 | 0.44x | -$228,726 |
| 100-7002 PREPARING ROW | 28 STA | $250.00 | $6,072.92 | 0.04x | -$163,042 |