Material Maintenance Project
CCSJ 6512-83-001 · lets Dec 15, 2026 · Kimble, San Angelo · US0377
$153,230Engineer's estimate
Items at market: $123,533 (-19.4%)
$153,766Most likely low bid$140,076 to $166,163 (middle half)
2.4Expected bidders5 plan holders, 4 regular bidders
87/100Strong fit: bid itMarket only. Set your company for a personal score
Where the low bid should land
$153,766
Estimate $153,230
$130,108 (1 in 10 go lower)$185,044 (1 in 10 go higher)
From 13 comparable let jobs (district + work type, estimates of $61,292 to $383,075, last 3 years). 46% of them went under the estimate; the typical low bid was 0.3% vs estimate.
Bid / no-bid score
- Competition25 / 25Jobs like this draw about 2.4 bidders.
- Margin14 / 20Low bids land at 100% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Sep 2026 | 6508-22-001Tom Green · 3 bidders | $390,154+4.7% |
| Sep 2026 | 6508-40-001Tom Green · 2 bidders | $341,356-8.6% |
| Sep 2026 | 6504-85-001Reagan · 3 bidders | $285,600+32.2% |
| Sep 2026 | 6504-86-001Tom Green · 3 bidders | $90,000+3.3% |
| Jun 2026 | 6503-69-001Tom Green · 3 bidders | $83,550-15.0% |
| Nov 2025 | 6493-28-001Runnels · 1 bidders | $111,000-15.4% |
| Nov 2025 | 6493-29-001Concho · 1 bidders | $116,000+0.3% |
| Nov 2025 | 6493-30-001Runnels · 3 bidders | $211,194-5.3% |
The field: plan holders and how they bid
Last 3 years in Texas| Plan holder | Bids | Wins | In San Angelo | Avg bid vs est. | Avg win vs est. | Their typical bid here |
|---|---|---|---|---|---|---|
| ALLIES LAND CLEARING SharpestBidders | 35 | 12 | 1 of 3 | -20.5% | -31.3% | $121,879 |
| TOUCHSTONE RESOURCES, LLCBidders | 413 | 170 | 7 of 18 | 11.0% | 0.5% | $170,132 |
| TRADERS INN LLCBidders | 6 | 0 | 13.9% | $174,508 | ||
| MARTIN MARIETTA MATERIALS, INC.Bidders | 243 | 64 | 2 of 8 | 15.3% | 1.3% | $176,668 |
| OASIS LAWN & LANDSCAPE, INCBidders | 0 | 0 |
"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.
Items that decide this job
8 of 8 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 8010-7021 FL BS(TY A GR 1-2)(DEL)(ST1)31 low bids · prices swing 5x | 600 TON | $39.77 | $16.74 – $76.33 | $23,864 | 19.3% |
| 8010-7022 FL BS(TY A GR 1-2)(DEL)(ST2)20 low bids | 500 TON | $42.69 | $28.50 – $59.57 | $21,344 | 17.3% |
| 8010-7025 FL BS(TY A GR 1-2)(DEL)(ST5)7 low bids | 500 TON | $35.76 | $22.68 – $59.17 | $17,878 | 14.5% |
| 8010-7028 FL BS(TY A GR 1-2)(DEL)(ST8)5 low bids | 300 TON | $49.37 | $28.91 – $71.67 | $14,811 | 12.0% |
| 8010-7027 FL BS(TY A GR 1-2)(DEL)(ST7)8 low bids · prices swing 4x | 300 TON | $48.92 | $20.00 – $70.00 | $14,676 | 11.9% |
| 8010-7026 FL BS(TY A GR 1-2)(DEL)(ST6)7 low bids | 300 TON | $36.21 | $22.00 – $54.84 | $10,863 | 8.8% |
| 8010-7023 FL BS(TY A GR 1-2)(DEL)(ST3)19 low bids | 300 TON | $35.12 | $24.00 – $53.75 | $10,536 | 8.5% |
| 8010-7024 FL BS(TY A GR 1-2)(DEL)(ST4)15 low bids | 300 TON | $31.87 | $21.75 – $57.00 | $9,561 | 7.7% |