Black Base-FY 27
6508-40-001 · let Sep 8, 2026 · Tom Green, San Angelo · Material Maintenance Project
$341,356Low bid: VULCAN CONSTRUCTION MATERIALS, LLC-8.6% vs estimate $373,411
$50,320Left on the table14.7% gap to the second bid
2BiddersSpread 15% low to high
14Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | VULCAN CONSTRUCTION MATERIALS, LLC | $341,356 | -8.6% | $50,320 | 0 | 0 | |
| 2 | MARTIN MARIETTA MATERIALS, INC. | $391,676 | +14.7% | 4.9% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
VULCAN CONSTRUCTION MATERIALS, LLC vs MARTIN MARIETTA MATERIALS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8001-7023 LRA (TY I GR A) (DEL) (ST1) | 300 TON | $124.40 | $139.20 | $128.57 | $4,440 |
| 8001-7026 LRA (TY I GR A) (DEL) (ST4) | 200 TON | $106.08 | $127.32 | $114.29 | $4,248 |
| 8001-7030 LRA (TY I GR A) (DEL) (ST8) | 200 TON | $101.04 | $121.34 | $99.33 | $4,060 |
| 8001-7031 LRA (TY I GR A) (DEL) (ST9) | 200 TON | $96.51 | $116.24 | $94.93 | $3,946 |
| 8001-7028 LRA (TY I GR A) (DEL) (ST6) | 200 TON | $111.42 | $129.90 | $109.42 | $3,696 |
| 8001-7032 LRA (TY I GR A) (DEL) (ST10) | 200 TON | $124.40 | $142.56 | $122.30 | $3,632 |
| 8001-7025 LRA (TY I GR A) (DEL) (ST3) | 200 TON | $113.35 | $131.41 | $125.09 | $3,612 |
| 8001-7024 LRA (TY I GR A) (DEL) (ST2) | 200 TON | $117.33 | $135.36 | $129.21 | $3,606 |
| 8001-7034 LRA (TY I GR A) (DEL) (ST12) | 200 TON | $127.70 | $144.87 | $125.53 | $3,434 |
| 8001-7029 LRA (TY I GR A) (DEL) (ST7) | 200 TON | $115.36 | $132.38 | $113.25 | $3,404 |
| 8001-7035 LRA (TY I GR A) (DEL) (ST13) | 200 TON | $123.08 | $139.20 | $121.01 | $3,224 |
| 8001-7027 LRA (TY I GR A) (DEL) (ST5) | 200 TON | $119.27 | $135.36 | $117.05 | $3,218 |
| 8001-7036 LRA (TY I GR A) (DEL) (ST14) | 200 TON | $133.64 | $148.56 | $131.33 | $2,984 |
| 8001-7033 LRA (TY I GR A) (DEL) (ST11) | 200 TON | $131.00 | $145.08 | $128.75 | $2,816 |
Positive: the low bidder was cheaper on that item. These 14 items account for $50,320 of the $50,320 gap.