AGGREGATE-TY B GR 4
6493-30-001 · let Nov 19, 2025 · Runnels, San Angelo · Material Maintenance Project
$211,194Low bid: MARTIN MARIETTA MATERIALS, INC.-5.3% vs estimate $223,000
$25,206Left on the table11.9% gap to the second bid
3BiddersSpread 22% low to high
14Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | MARTIN MARIETTA MATERIALS, INC. | $211,194 | -5.3% | $25,206 | 0 | 0 | |
| 2 | TOUCHSTONE RESOURCES, LLC | $236,400 | +11.9% | 6.0% | $21,734 | 0 | 0 |
| 3 | J. H. STRAIN & SONS, INC. | $258,134 | +22.2% | 15.8% | 1+$10,644 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
MARTIN MARIETTA MATERIALS, INC. vs TOUCHSTONE RESOURCES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8000-7112 AGGR (TY B GR 4) (DEL) (ST14) | 200 TON | $55.60 | $85.00 | $55.60 | $5,880 |
| 8000-7111 AGGR (TY B GR 4) (DEL) (ST13) | 200 TON | $60.94 | $85.00 | $60.94 | $4,812 |
| 8000-7104 AGGR (TY B GR 4) (DEL) (ST6) | 200 TON | $74.58 | $90.00 | $81.72 | $3,084 |
| 8000-7107 AGGR (TY B GR 4) (DEL) (ST9) | 200 TON | $70.42 | $85.00 | $81.33 | $2,916 |
| 8000-7103 AGGR (TY B GR 4) (DEL) (ST5) | 200 TON | $66.85 | $80.00 | $78.65 | $2,630 |
| 8000-7100 AGGR (TY B GR 4) (DEL) (ST2) | 200 TON | $77.83 | $87.00 | $72.44 | $1,834 |
| 8000-7106 AGGR (TY B GR 4) (DEL) (ST8) | 200 TON | $73.97 | $80.00 | $81.23 | $1,206 |
| 8000-7101 AGGR (TY B GR 4) (DEL) (ST3) | 200 TON | $79.73 | $85.00 | $78.78 | $1,054 |
| 8000-7102 AGGR (TY B GR 4) (DEL) (ST4) | 200 TON | $74.79 | $80.00 | $75.77 | $1,042 |
| 8000-7110 AGGR (TY B GR 4) (DEL) (ST12) | 200 TON | $85.62 | $90.00 | $85.62 | $876 |
| 8000-7108 AGGR (TY B GR 4) (DEL) (ST10) | 200 TON | $88.66 | $85.00 | $88.66 | -$732 |
| 8000-7109 AGGR (TY B GR 4) (DEL) (ST11) | 200 TON | $87.33 | $90.00 | $87.33 | $534 |
| 8000-7099 AGGR (TY B GR 4) (DEL) (ST1) | 200 TON | $79.54 | $80.00 | $67.96 | $92 |
| 8000-7105 AGGR (TY B GR 4) (DEL) (ST7) | 200 TON | $80.11 | $80.00 | $77.59 | -$22 |
Positive: the low bidder was cheaper on that item. These 14 items account for $25,206 of the $25,206 gap.
J. H. STRAIN & SONS, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 8000-7112 AGGR (TY B GR 4) (DEL) (ST14) | 200 TON | $108.82 | $55.60 | 1.96x | $10,644 |