Bid Day Forecast: 6512-22-001

Orange · Dec 3, 2026 Sign up free
Set your company to personalize scores

Material Maintenance Project - Sealed

CCSJ 6512-22-001 · lets Dec 3, 2026 · Orange, Beaumont · FM0105

$729,900Engineer's estimate Items at market: $557,195 (-23.7%)
$705,924Most likely low bid$623,535 to $775,151 (middle half)
1.8Expected bidders2 plan holders, 1 regular bidders
80/100Strong fit: bid itMarket only. Set your company for a personal score

Where the low bid should land

$582,348 (1 in 10 go lower)$807,793 (1 in 10 go higher)

From 13 comparable let jobs (district + work type, estimates of $291,960 to $1,824,750, last 3 years). 69% of them went under the estimate; the typical low bid was -3.3% vs estimate.

Bid / no-bid score

  • Competition25 / 25Jobs like this draw about 1.8 bidders.
  • Margin11 / 20Low bids land at 97% of the estimate.

Set your company to add your experience, win rate and size fit.

Comparable jobs

May 2026 6502-75-001Jefferson · 4 bidders $287,250-14.6%
May 2026 6501-83-001Hardin · 1 bidders $1,185,775-2.0%
Dec 2025 6495-27-001Jefferson · 2 bidders $856,500+6.2%
Dec 2025 6495-28-001Orange · 1 bidders $919,700+18.6%
Dec 2025 6495-32-001Liberty · 2 bidders $458,000-20.1%
Sep 2025 6491-43-001Liberty · 1 bidders $405,500+8.7%
Sep 2025 6491-12-001Jefferson · 2 bidders $672,636-7.9%
Sep 2025 6491-04-001Newton · 1 bidders $866,030-2.4%

The field: plan holders and how they bid

Last 3 years in Texas
Plan holderBidsWinsIn BeaumontAvg bid vs est.Avg win vs est.Their typical bid here
TOUCHSTONE RESOURCES, LLC SharpestBidders 4131706 of 8 11.0%0.5% $810,411
FLAGGSTONE DEVELOPMENT GROUP LLCBidders 00

"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.

Items that decide this job

9 of 9 items priced from low bids
ItemQtyMarket priceRange of low bidsAt marketShare
8011-7148 D-GR HMA TY D PG 70-22 (DEL) SITE 34 low bids 1,000 TON$165.00$165.00 – $165.00 $165,00029.6%
8011-7147 D-GR HMA TY D PG 70-22 (DEL) SITE 27 low bids 1,000 TON$142.41$113.00 – $170.00 $142,41225.6%
8011-7146 D-GR HMA TY D PG 70-22 (DEL) SITE 135 low bids 1,000 TON$117.96$92.00 – $200.00 $117,95621.2%
8011-7055 D-GR HMA TY D PG 64-22 (PICKUP)150 low bids 500 TON$89.12$59.00 – $147.00 $44,5628.0%
8011-7004 D-GR HMA TY B PG 64-22 (DEL) SITE 323 low bids 500 TON$75.45$69.00 – $106.11 $37,7236.8%
8011-7145 D-GR HMA TY D PG 70-22 (PICKUP)35 low bids 200 TON$111.44$78.50 – $142.00 $22,2884.0%
8011-7127 D-GR HMA TY C PG 70-22 (PICKUP)13 low bids 100 TON$120.24$87.00 – $137.00 $12,0242.2%
8011-7037 D-GR HMA TY C PG 64-22 (PICKUP)45 low bids 100 TON$82.72$58.00 – $150.00 $8,2721.5%
8011-7001 D-GR HMA TY B PG 64-22 (PICKUP)56 low bids 100 TON$69.58$54.00 – $132.00 $6,9581.2%