Routine Maintenance Project - Sealed
CCSJ 6509-62-001 · lets Dec 10, 2026 · Val Verde, Laredo · US0090
$680,095Engineer's estimate
Items at market: $908,256 (+33.5%)
$712,801Most likely low bid$619,475 to $809,313 (middle half)
2.5Expected bidders3 plan holders, 3 regular bidders
93/100Strong fit: bid itMarket only. Set your company for a personal score
Where the low bid should land
$712,801
Estimate $680,095
$562,915 (1 in 10 go lower)$914,975 (1 in 10 go higher)
From 17 comparable let jobs (district + work type, estimates of $272,038 to $1,700,238, last 3 years). 41% of them went under the estimate; the typical low bid was 4.8% vs estimate.
Bid / no-bid score
- Competition25 / 25Jobs like this draw about 2.5 bidders.
- Margin17 / 20Low bids land at 105% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Nov 2026 | 6509-66-001Dimmit · 4 bidders | $428,848-8.9% |
| Sep 2026 | 6506-24-001La Salle · 4 bidders | $1,244,224-1.9% |
| Jun 2026 | 6499-01-001Webb · 3 bidders | $623,184+4.3% |
| Jun 2026 | 6500-57-001Maverick · 3 bidders | $460,615+4.8% |
| Jun 2026 | 6499-00-001Webb · 1 bidders | $885,125+12.1% |
| May 2026 | 6498-99-001La Salle · 1 bidders | $632,346+19.0% |
| Nov 2025 | 6492-47-001Kinney · 2 bidders | $241,954-18.1% |
| Nov 2025 | 6492-75-001Duval · 2 bidders | $569,033+19.0% |
The field: plan holders and how they bid
Last 3 years in Texas| Plan holder | Bids | Wins | In Laredo | Avg bid vs est. | Avg win vs est. | Their typical bid here |
|---|---|---|---|---|---|---|
| ROSS SA ENTERPRISE LLC SharpestBidders | 98 | 40 | 0 of 1 | -19.4% | -24.5% | $548,180 |
| T&L CLEANING SERVICES LLCBidders | 105 | 29 | 4.7% | -18.0% | $712,342 | |
| LUCANIA CONTRACTORS LLCBidders | 46 | 12 | 2 of 9 | 12.8% | -6.9% | $767,393 |
"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.
Items that decide this job
57 of 63 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 500-7004 MOBILIZATION (CALLOUT 2)19 low bids · prices swing 1,100,000,000x | 15 EA | $18,951.60 | $0.0010 – $1,100,000.00 | $284,274 | 31.3% |
| 770-7037 REPLACE GUARDRAIL END TREATMENT SYSTEM29 low bids · prices swing 8x | 60 EA | $3,116.90 | $1,300.00 – $10,000.00 | $187,014 | 20.6% |
| 500-7005 MOBILIZATION (CALLOUT 3)11 low bids · prices swing 75,000,000x | 15 EA | $10,868.78 | $0.0010 – $75,000.00 | $163,032 | 17.9% |
| 770-7001 REPLACE RAIL ELEMENT (W-BEAM)100 low bids · prices swing 1,150x | 2,200 LF | $22.03 | $0.1000 – $115.00 | $48,461 | 5.3% |
| 505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x | 120 DAY | $217.57 | $0.0010 – $16,487.00 | $26,109 | 2.9% |
| 540-7031 MTL BM GD FEN TRANS (31"-28")(25')20 low bids · prices swing 1,400x | 40 EA | $636.27 | $1.00 – $1,400.00 | $25,451 | 2.8% |
| 500-7006 MOBILIZATION (CALLOUT 4)8 low bids · prices swing 100x | 15 EA | $1,388.64 | $100.00 – $10,000.00 | $20,830 | 2.3% |
| 770-7015 REPL SINGLE GDRAIL TERM IMPACT HEAD82 low bids · prices swing 8,000x | 15 EA | $975.38 | $1.00 – $8,000.00 | $14,631 | 1.6% |
| 770-7006 REPLACE TIMBER POST W/O CONC FND99 low bids · prices swing 750x | 150 EA | $89.82 | $1.00 – $750.00 | $13,473 | 1.5% |
| 540-7015 DOWNSTREAM ANCHOR TERMINAL SECTION366 low bids · prices swing 6,000x | 10 EA | $1,297.32 | $1.00 – $6,000.00 | $12,973 | 1.4% |
| 451-7044 RETROFIT RAIL (TY PR11)3 low bids | 60 LF | $192.34 | $167.79 – $250.00 | $11,540 | 1.3% |
| 770-7016 REPLACE SINGLE GDRAIL TERMINAL RAIL83 low bids · prices swing 175x | 350 LF | $31.82 | $1.00 – $175.00 | $11,136 | 1.2% |
| 770-7026 REPLACE DOWNSTREAM ANCHOR TERMINAL62 low bids · prices swing 2,500x | 15 EA | $534.87 | $1.00 – $2,500.00 | $8,023 | 0.9% |
| 770-7018 REPLACE BLOCKOUT93 low bids · prices swing 25,000x | 150 EA | $44.95 | $0.1000 – $2,500.00 | $6,743 | 0.7% |
| 540-7001 MTL W-BEAM GD FEN (TIM POST)511 low bids · prices swing 4,623x | 250 LF | $25.60 | $0.0500 – $231.17 | $6,401 | 0.7% |