Routine Maintenance Project - Sealed
CCSJ 6504-73-001 · lets Dec 10, 2026 · Smith, Tyler · IH0020
$311,575Engineer's estimate
Items at market: $278,315 (-10.7%)
$286,752Most likely low bid$249,096 to $317,952 (middle half)
4.9Expected bidders4 plan holders, 3 regular bidders
56/100Worth a lookMarket only. Set your company for a personal score
Where the low bid should land
$286,752
Estimate $311,575
$232,342 (1 in 10 go lower)$375,835 (1 in 10 go higher)
From 74 comparable let jobs (district, estimates of $124,630 to $778,938, last 3 years). 74% of them went under the estimate; the typical low bid was -8.0% vs estimate.
Bid / no-bid score
- Competition17 / 25Jobs like this draw about 4.9 bidders.
- Margin8 / 20Low bids land at 92% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Nov 2026 | 6504-49-001Smith · 1 bidders | $635,290+11.6% |
| Nov 2026 | 6504-71-001Wood · 1 bidders | $905,160+24.0% |
| Oct 2026 | 6505-28-001Anderson · 7 bidders | $505,217-4.1% |
| Sep 2026 | 6498-39-001Henderson · 9 bidders | $115,322-20.7% |
| Sep 2026 | 6506-98-001Smith · 9 bidders | $203,752-21.7% |
| Aug 2026 | 6498-38-001Anderson · 5 bidders | $223,693-22.4% |
| Aug 2026 | 6501-29-001Gregg · 13 bidders | $133,105-48.3% |
| Aug 2026 | 6501-71-001Smith · 11 bidders | $167,226-18.1% |
The field: plan holders and how they bid
Last 3 years in Texas| Plan holder | Bids | Wins | In Tyler | Avg bid vs est. | Avg win vs est. | Their typical bid here |
|---|---|---|---|---|---|---|
| STRIPING TECHNOLOGY, L.P. SharpestBidders | 97 | 22 | 8 of 20 | -4.0% | -21.9% | $298,957 |
| TEXAS TRAFFIC CONTROL SYSTEMS, INC.Bidders | 10 | 4 | 3 of 6 | -3.4% | -4.1% | $300,858 |
| WG ENGINEERING & CONSTRUCTION, LLCBidders | 90 | 13 | 0 of 6 | 9.2% | 10.1% | $340,324 |
| CALDERA SPECIALTIES LLCInformational Proposals | 0 | 0 |
"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.
Items that decide this job
23 of 23 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 690-7126 REPLACE LUMINAIRE POLE12 low bids · prices swing 10x | 20 EA | $2,395.50 | $600.00 – $6,000.00 | $47,910 | 17.2% |
| 690-7244 REPLACE LUMINAIRES5 low bids · prices swing 5x | 150 EA | $252.93 | $165.00 – $882.00 | $37,940 | 13.6% |
| 690-7151 REPLACE CONDUCTOR8 low bids · prices swing 4x | 10,000 LF | $2.71 | $1.40 – $6.00 | $27,115 | 9.7% |
| 505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x | 100 DAY | $217.57 | $0.0010 – $16,487.00 | $21,757 | 7.8% |
| 690-7019 REPLACE OF ELECTRICAL SERVICE19 low bids · prices swing 11x | 5 EA | $4,286.17 | $1,000.00 – $11,000.00 | $21,431 | 7.7% |
| 690-7197 REPLACE TRANSFORMER BASE10 low bids · prices swing 7x | 20 EA | $806.00 | $250.00 – $1,742.00 | $16,120 | 5.8% |
| 690-7195 INSTALL FOUNDATION9 low bids · prices swing 47x | 5 EA | $3,069.15 | $300.00 – $14,150.00 | $15,346 | 5.5% |
| 500-7002 MOBILIZATION (CALLOUT)748 low bids · prices swing 535,000,000x | 24 EA | $600.85 | $0.0010 – $535,000.00 | $14,420 | 5.2% |
| 690-7161 ROAD BORE5 low bids · prices swing 4x | 750 LF | $19.00 | $10.00 – $35.00 | $14,250 | 5.1% |
| 690-7183 REPLACE LUMINAIRE ARMS6 low bids · prices swing 200x | 10 EA | $1,055.14 | $10.00 – $2,000.00 | $10,551 | 3.8% |
| 690-7218 REPLACE FUSE17 low bids · prices swing 5x | 200 EA | $47.51 | $25.00 – $125.00 | $9,501 | 3.4% |
| 690-7192 REPLACE STEEL SERVICE POLE10 low bids · prices swing 10x | 5 EA | $1,353.81 | $500.00 – $5,000.00 | $6,769 | 2.4% |
| 690-7245 REPLACE PHOTOCELL8 low bids · prices swing 9x | 80 EA | $77.97 | $25.00 – $214.30 | $6,237 | 2.2% |
| 690-7194 INSTALL GROUND BOX W/APRON12 low bids · prices swing 3x | 5 EA | $1,218.21 | $600.00 – $1,800.00 | $6,091 | 2.2% |
| 690-7220 REPLACE BREAKAWAY FUSE HOLDER14 low bids · prices swing 4x | 40 EA | $149.36 | $75.00 – $333.95 | $5,975 | 2.1% |