FY27 Cleaning and Sealing Bridge Joints
6501-71-001 · let Aug 11, 2026 · Smith, Tyler · Bridge Preventative Maintenance - Sealed
$167,226Low bid: INFRATEX CONSTRUCTION LLC-18.1% vs estimate $204,170
$12,374Left on the table7.4% gap to the second bid
11BiddersSpread 163% low to high
9Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | INFRATEX CONSTRUCTION LLC | $167,226 | -18.1% | $12,374 | 0 | 3-$16,030 | |
| 2 | JACKSON EXCAVATION, LLC | $179,600 | +7.4% | -12.0% | $22,786 | 0 | 1-$8,303 |
| 3 | MACIAS SPECIALTY CONTRACTING LLC | $202,386 | +21.0% | -0.9% | $1,458 | 1+$26,996 | 0 |
| 4 | RED BARON BUILDING COMPANY MUNICIPAL PROJECTS DIVISION LLC | $203,843 | +21.9% | -0.2% | $6,798 | 0 | 1-$2,693 |
| 5 | SCOUT 5 CONSTRUCTION LLC | $210,641 | +26.0% | 3.2% | $3,391 | 1+$46,996 | 3-$16,030 |
| 6 | 12TWELVE ROAD AND BRIDGE LLC | $214,032 | +28.0% | 4.8% | $33,168 | ||
| 7 | GARRET SHIELDS INFRASTRUCTURE | $247,200 | +47.8% | 21.1% | $18,230 | ||
| 8 | SCR CIVIL CONSTRUCTION, LLC | $265,430 | +58.7% | 30.0% | $9,350 | ||
| 9 | REAR CONTRACTORS LLC | $274,780 | +64.3% | 34.6% | $15,204 | ||
| 10 | STRUCTURAL INTEGRITY GROUP LLC | $289,984 | +73.4% | 42.0% | $149,778 | ||
| 11 | CROSS PLUS CONSTRUCTION, LLC | $439,762 | +163.0% | 115.4% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
INFRATEX CONSTRUCTION LLC vs JACKSON EXCAVATION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 438-7007 CLEANING AND SEALING EXIST JOINTS (CL7) | 1,352 LF | $35.00 | $50.00 | $38.57 | $20,280 |
| 438-7004 CLEANING AND SEALING EXIST JOINTS (CL3) | 1,212 LF | $30.00 | $20.00 | $19.19 | -$12,120 |
| 785-7002 BRIDGE JOINT REPAIR (HEADER) | 372 LF | $140.00 | $120.00 | $199.12 | -$7,440 |
| 438-7008 CLEANING EXISTING JOINTS | 1,071 LF | $15.00 | $20.00 | $16.75 | $5,355 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 40 DAY | $0.0100 | $100.00 | $117.34 | $4,000 |
| 438-7014 CLEAN AND SEAL EXIST JTS (STRIP SEAL) | 200 LF | $52.00 | $60.00 | $57.79 | $1,600 |
| 505-7001 TMA (STATIONARY) | 40 DAY | $0.0100 | $10.00 | $217.57 | $400 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 30 DAY | $0.0100 | $10.00 | $87.82 | $300 |
| 500-7002 MOBILIZATION (CALLOUT) | 5 EA | $1,000.00 | $1,000.00 | $600.85 | $0 |
Positive: the low bidder was cheaper on that item. These 9 items account for $12,374 of the $12,374 gap.
INFRATEX CONSTRUCTION LLC: unbalanced items
Placed 1JACKSON EXCAVATION, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 40 DAY | $10.00 | $217.57 | 0.05x | -$8,303 |
MACIAS SPECIALTY CONTRACTING LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 5 EA | $6,000.00 | $600.85 | 9.99x | $26,996 |
RED BARON BUILDING COMPANY MUNICIPAL PROJECTS DIVISION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 40 DAY | $50.00 | $117.34 | 0.43x | -$2,693 |
SCOUT 5 CONSTRUCTION LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 5 EA | $10,000.00 | $600.85 | 16.64x | $46,996 |
| 505-7001 TMA (STATIONARY) | 40 DAY | $0.0100 | $217.57 | 0.00x | -$8,702 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 40 DAY | $0.0100 | $117.34 | 0.00x | -$4,693 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 30 DAY | $0.0100 | $87.82 | 0.00x | -$2,634 |