FY27 BPM JOINTS IH-20
6501-29-001 · let Aug 11, 2026 · Gregg, Tyler · Bridge Preventative Maintenance - Sealed
$133,105Low bid: 12TWELVE ROAD AND BRIDGE LLC-48.3% vs estimate $257,618
$74,026Left on the table55.6% gap to the second bid
13BiddersSpread 620% low to high
9Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | 12TWELVE ROAD AND BRIDGE LLC | $133,105 | -48.3% | $74,026 | 0 | 6-$590,510 | |
| 2 | SCOUT 5 CONSTRUCTION LLC | $207,131 | +55.6% | -19.6% | $1,883 | 0 | 5-$573,926 |
| 3 | STRUCTURAL INTEGRITY GROUP LLC | $209,014 | +57.0% | -18.9% | $2,331 | 1+$38,541 | 5-$558,532 |
| 4 | JACKSON EXCAVATION, LLC | $211,345 | +58.8% | -18.0% | $1,687 | 0 | 4-$574,709 |
| 5 | MACIAS SPECIALTY CONTRACTING LLC | $213,032 | +60.0% | -17.3% | $6,440 | 0 | 2-$521,020 |
| 6 | ROAD DOCTORS LLC | $219,472 | +64.9% | -14.8% | $15,700 | ||
| 7 | REAR CONTRACTORS LLC | $235,172 | +76.7% | -8.7% | $11,162 | ||
| 8 | GHB EQUIPMENT COMPANY, L.L.C. | $246,334 | +85.1% | -4.4% | $7,033 | ||
| 9 | RED BARON BUILDING COMPANY MUNICIPAL PROJECTS DIVISION LLC | $253,367 | +90.4% | -1.7% | $1,277 | ||
| 10 | SCR CIVIL CONSTRUCTION, LLC | $254,644 | +91.3% | -1.2% | $19,738 | ||
| 11 | O. TREVINO CONSTRUCTION, LLC | $274,382 | +106.1% | 6.5% | $98 | ||
| 12 | GARRET SHIELDS INFRASTRUCTURE | $274,480 | +106.2% | 6.5% | $683,989 | ||
| 13 | CROSS PLUS CONSTRUCTION, LLC | $958,469 | +620.1% | 272.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
12TWELVE ROAD AND BRIDGE LLC vs SCOUT 5 CONSTRUCTION LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 438-7008 CLEANING EXISTING JOINTS | 6,184 LF | $9.00 | $22.00 | $16.75 | $80,392 |
| 785-7002 BRIDGE JOINT REPAIR (HEADER) | 160 LF | $300.00 | $140.00 | $199.12 | -$25,600 |
| 500-7001 MOBILIZATION | 1 LS | $1,000.00 | $12,000.00 | $523,850.32 | $11,000 |
| 429-7002 CONC STR REPAIR (EPOXY MORTAR) | 55 SF | $50.00 | $200.00 | $151.82 | $8,250 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 180 DAY | $0.1000 | $0.0100 | $87.82 | -$16 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 30 DAY | $0.0010 | $0.0100 | $117.34 | $0 |
| 438-7004 CLEANING AND SEALING EXIST JOINTS (CL3) | 856 LF | $30.00 | $30.00 | $19.19 | $0 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $0.0100 | $0.0100 | $11,585.04 | $0 |
| 505-7001 TMA (STATIONARY) | 90 DAY | $0.0100 | $0.0100 | $217.57 | $0 |
Positive: the low bidder was cheaper on that item. These 9 items account for $74,026 of the $74,026 gap.
12TWELVE ROAD AND BRIDGE LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,000.00 | $523,850.32 | 0.00x | -$522,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $0.0100 | $11,585.04 | 0.00x | -$23,170 |
| 505-7001 TMA (STATIONARY) | 90 DAY | $0.0100 | $217.57 | 0.00x | -$19,581 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 180 DAY | $0.1000 | $87.82 | 0.00x | -$15,789 |
| 429-7002 CONC STR REPAIR (EPOXY MORTAR) | 55 SF | $50.00 | $151.82 | 0.33x | -$5,600 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 30 DAY | $0.0010 | $117.34 | 0.00x | -$3,520 |
SCOUT 5 CONSTRUCTION LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $12,000.00 | $523,850.32 | 0.02x | -$511,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $0.0100 | $11,585.04 | 0.00x | -$23,170 |
| 505-7001 TMA (STATIONARY) | 90 DAY | $0.0100 | $217.57 | 0.00x | -$19,581 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 180 DAY | $0.0100 | $87.82 | 0.00x | -$15,805 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 30 DAY | $0.0100 | $117.34 | 0.00x | -$3,520 |
STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 785-7002 BRIDGE JOINT REPAIR (HEADER) | 160 LF | $440.00 | $199.12 | 2.21x | $38,541 |
| 500-7001 MOBILIZATION | 1 LS | $19,500.00 | $523,850.32 | 0.04x | -$504,350 |
| 505-7001 TMA (STATIONARY) | 90 DAY | $1.00 | $217.57 | 0.00x | -$19,491 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 180 DAY | $1.00 | $87.82 | 0.01x | -$15,627 |
| 438-7004 CLEANING AND SEALING EXIST JOINTS (CL3) | 856 LF | $1.00 | $19.19 | 0.05x | -$15,573 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 30 DAY | $1.00 | $117.34 | 0.01x | -$3,490 |
JACKSON EXCAVATION, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,000.00 | $523,850.32 | 0.00x | -$522,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $2,000.00 | $11,585.04 | 0.17x | -$19,170 |
| 505-7001 TMA (STATIONARY) | 90 DAY | $10.00 | $217.57 | 0.05x | -$18,681 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 180 DAY | $10.00 | $87.82 | 0.11x | -$14,007 |