Traffic Control Devices
CCSJ 0923-00-085 · lets Dec 1, 2026 · Eastland, Brownwood · Various
$1,889,401Engineer's estimate
Items at market: $2,587,100 (+36.9%)
$1,611,697Most likely low bid$1,401,687 to $1,789,778 (middle half)
5.4Expected bidders3 plan holders, 3 regular bidders
42/100Weak fitMarket only. Set your company for a personal score
Where the low bid should land
$1,611,697
Estimate $1,889,401
$1,261,770 (1 in 10 go lower)$2,125,705 (1 in 10 go higher)
From 46 comparable let jobs (district, estimates of $755,760 to $4,723,502, last 3 years). 83% of them went under the estimate; the typical low bid was -14.7% vs estimate.
Bid / no-bid score
- Competition15 / 25Jobs like this draw about 5.4 bidders.
- Margin4 / 20Low bids land at 85% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Nov 2026 | 0923-06-068Brown · 6 bidders | $1,561,729-10.3% |
| Nov 2026 | 0054-05-027Coleman · 4 bidders | $2,929,127+19.6% |
| Nov 2026 | 6494-86-001Brown · 5 bidders | $561,742-40.2% |
| Oct 2026 | 6503-72-001Lampasas · 9 bidders | $719,494-20.2% |
| Oct 2026 | 6496-56-001Brown · 7 bidders | $3,276,697-25.8% |
| Oct 2026 | 6499-74-001Comanche · 11 bidders | $727,661-25.8% |
| Sep 2026 | 6500-62-001Comanche · 3 bidders | $777,883-21.0% |
| Aug 2026 | 6505-22-001Eastland · 9 bidders | $2,982,235-7.3% |
The field: plan holders and how they bid
Last 3 years in Texas| Plan holder | Bids | Wins | In Brownwood | Avg bid vs est. | Avg win vs est. | Their typical bid here |
|---|---|---|---|---|---|---|
| CENTERLINE TECHNOLOGIES, LLC SharpestBidders | 98 | 26 | 0 of 7 | -14.5% | -23.4% | $1,615,118 |
| TRP INFRASTRUCTURE SERVICES, LLCBidders | 272 | 78 | 2 of 9 | -9.4% | -24.1% | $1,711,923 |
| STRIPE-A-ZONE, LLCBidders | 188 | 51 | 1 of 9 | -8.9% | -22.7% | $1,721,746 |
"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.
Items that decide this job
48 of 54 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 666-7519 REFL PAV MRK TY I (W)6"(SLD)(125MIL)5 low bids | 1,082,733 LF | $0.6060 | $0.5500 – $1.00 | $656,154 | 25.4% |
| 666-7523 REFL PAV MRK TY I (Y)6"(SLD)(125MIL)5 low bids | 1,038,354 LF | $0.6108 | $0.5500 – $1.00 | $634,236 | 24.5% |
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 1 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $523,850 | 20.2% |
| 666-7522 REFL PAV MRK TY I (Y)6"(BRK)(125MIL)4 low bids | 156,179 LF | $0.6313 | $0.5500 – $1.00 | $98,589 | 3.8% |
| 672-7004 REFL PAV MRKR TY II-A-A1023 low bids · prices swing 23,500x | 22,286 EA | $3.97 | $0.0400 – $940.00 | $88,554 | 3.4% |
| 533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE)260 low bids · prices swing 250x | 367,424 LF | $0.2394 | $0.0800 – $20.00 | $87,962 | 3.4% |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR)352 low bids · prices swing 380x | 356,841 LF | $0.2040 | $0.0500 – $19.00 | $72,795 | 2.8% |
| 668-7089 PREFAB PM TY C (W)(24")(SLD)330 low bids · prices swing 172x | 4,630 LF | $13.72 | $1.27 – $218.00 | $63,541 | 2.5% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x | 5 MO | $11,585.04 | $0.0010 – $273,686.48 | $57,925 | 2.2% |
| 316-7032 ASPH (RC-250)14 low bids · prices swing 6x | 44.5 TON | $1,089.28 | $877.50 – $5,000.00 | $48,473 | 1.9% |
| 316-7175 AGGR (TY-B, GR-5)(SAC-B)22 low bids · prices swing 54x | 429.3 CY | $88.19 | $35.00 – $1,900.00 | $37,862 | 1.5% |
| 505-7003 TMA (MOBILE OPERATION)1256 low bids · prices swing 3,000,000x | 164 DAY | $229.60 | $0.0010 – $3,000.00 | $37,654 | 1.5% |
| 668-7127 PREFAB PM TY C (Y)(24")(SLD)57 low bids | 2,892 LF | $11.82 | $9.00 – $25.00 | $34,192 | 1.3% |
| 677-7002 ELIM EXT PM & MRKS (6")426 low bids · prices swing 6,000x | 96,932 LF | $0.2755 | $0.0100 – $60.00 | $26,707 | 1.0% |
| 666-7347 PAVEMENT SLER 6"401 low bids · prices swing 20,000x | 138,571 LF | $0.1841 | $0.0010 – $20.00 | $25,515 | 1.0% |