Bridge Replacement
CCSJ 0918-47-460 · lets Dec 1, 2026 · Dallas, Dallas · W PLEASANT RUN RD, WESTMORELAND · Bridge Replacement
$8,607,909Engineer's estimate
Items at market: $7,701,637 (-10.5%)
$7,788,106Most likely low bid$7,141,351 to $8,564,552 (middle half)
5.3Expected bidders17 plan holders, 16 regular bidders
49/100Weak fitMarket only. Set your company for a personal score
Where the low bid should land
$7,788,106
Estimate $8,607,909
$6,380,349 (1 in 10 go lower)$9,327,839 (1 in 10 go higher)
From 101 comparable let jobs (district, estimates of $3,443,163 to $21,519,772, last 3 years). 76% of them went under the estimate; the typical low bid was -9.5% vs estimate.
Bid / no-bid score
- Competition15 / 25Jobs like this draw about 5.3 bidders.
- Margin7 / 20Low bids land at 90% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Oct 2026 | 0092-03-064Ellis · 8 bidders | $3,761,164-17.0% |
| Oct 2026 | 0092-05-058Ellis · 1 bidders | $13,621,550-25.9% |
| Oct 2026 | 0387-01-016Collin · 8 bidders | $4,906,593-17.4% |
| Sep 2026 | 0918-00-440Dallas · 8 bidders | $4,190,000-5.9% |
| Aug 2026 | 1012-03-027Collin · 7 bidders | $18,829,388+2.7% |
| Aug 2026 | 0092-06-111Navarro · 6 bidders | $5,407,398-18.7% |
| Aug 2026 | 0173-04-059Kaufman · 7 bidders | $6,242,701-13.3% |
| Jul 2026 | 2977-01-011Collin · 6 bidders | $11,064,754-10.8% |
The field: plan holders and how they bid
Last 3 years in Texas| Plan holder | Bids | Wins | In Dallas | Avg bid vs est. | Avg win vs est. | Their typical bid here |
|---|---|---|---|---|---|---|
| TUCAN CONTRACTING, LLC SharpestBidders | 35 | 5 | 2 of 7 | 0.1% | -15.8% | $8,616,152 |
| THK CONSTRUCTION LLCBidders | 98 | 30 | 0 of 1 | 2.7% | -13.7% | $8,844,264 |
| TEXAS STEEL INDUSTRIAL PLACING, LLCBidders | 68 | 5 | 0 of 5 | 3.1% | -10.3% | $8,877,511 |
| GRANITE CONSTRUCTION COMPANYBidders | 31 | 5 | 3 of 15 | 3.2% | -18.0% | $8,883,824 |
| R CONSTRUCTION CIVIL, LLCBidders | 58 | 10 | 0 of 4 | 3.2% | -6.3% | $8,887,392 |
| PRATER DIRT WORK LLCInformational Proposals | 19 | 1 | 4.9% | -12.9% | $9,025,808 | |
| ALTUS CONSTRUCTION LLCBidders | 62 | 9 | 3 of 16 | 5.4% | -9.9% | $9,076,952 |
| INDUS ROAD & BRIDGE, INC.Bidders | 39 | 9 | 5 of 17 | 5.8% | -11.8% | $9,110,511 |
| COPPELL CONSTRUCTION CO., INC.Bidders | 52 | 6 | 0 of 1 | 9.1% | -6.8% | $9,394,868 |
| YOKO EXCAVATING, LLCBidders | 18 | 4 | 0 of 1 | 9.3% | -6.6% | $9,407,001 |
| EAST TEXAS BRIDGE, INC.Bidders | 126 | 13 | 0 of 1 | 11.8% | 3.6% | $9,623,304 |
| RAGLE CONSTRUCTION, INC.Bidders | 251 | 38 | 7 of 44 | 13.0% | -5.0% | $9,726,482 |
| IBCTX, LLCBidders | 47 | 6 | 4 of 31 | 13.3% | -8.4% | $9,751,908 |
| URBAN INFRACONSTRUCTION LLCBidders | 20 | 2 | 1 of 5 | 13.5% | -4.7% | $9,766,771 |
| ED BELL CONSTRUCTION COMPANYBidders | 122 | 7 | 1 of 78 | 14.6% | -2.8% | $9,863,398 |
| Lumin8 Transportation Technologies, LLCBidders | 18 | 1 | 0 of 6 | 26.7% | -7.5% | $10,910,396 |
| MCMAHON CONTRACTING AND CONSTRUCTION, LLCBidders | 2 | 0 | 0 of 1 | 35.5% | $11,666,575 |
"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.
Items that decide this job
191 of 195 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 425-7002 PRESTR CONC GIRDER (TX34)26 low bids | 3,102.8 LF | $210.34 | $105.00 – $300.00 | $652,649 | 8.5% |
| 425-7019 PRESTR CONC SLAB BEAM (5SB15)47 low bids | 2,493 LF | $261.75 | $155.00 – $429.05 | $652,532 | 8.5% |
| 422-7002 REINF CONC SLAB (HPC)58 low bids · prices swing 12x | 23,491 SF | $26.91 | $19.00 – $220.00 | $632,117 | 8.2% |
| 422-7008 REINF CONC SLAB (SLAB BEAM)(HPC)7 low bids | 14,140 SF | $28.14 | $19.00 – $42.25 | $397,904 | 5.2% |
| 416-7006 DRILL SHAFT (36 IN)175 low bids · prices swing 9x | 1,256 LF | $280.58 | $135.00 – $1,200.00 | $352,408 | 4.6% |
| 416-7004 DRILL SHAFT (24 IN)125 low bids · prices swing 5x | 1,431 LF | $234.98 | $100.00 – $524.19 | $336,251 | 4.4% |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN)119 low bids · prices swing 11x | 1,585 CY | $190.61 | $45.00 – $500.00 | $302,121 | 3.9% |
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 0.55 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $288,118 | 3.7% |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH)86 low bids · prices swing 113x | 2 EA | $136,676.66 | $10,000.00 – $1,125,000.00 | $273,353 | 3.5% |
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 0.45 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $235,733 | 3.1% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x | 20 MO | $11,585.04 | $0.0010 – $273,686.48 | $231,701 | 3.0% |
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN)171 low bids · prices swing 57x | 967 CY | $179.97 | $35.00 – $2,000.00 | $174,031 | 2.3% |
| 422-7014 APPROACH SLAB (HPC)54 low bids · prices swing 2,500x | 195.1 CY | $731.91 | $1.00 – $2,500.00 | $142,796 | 1.9% |
| 422-7014 APPROACH SLAB (HPC)54 low bids · prices swing 2,500x | 189.2 CY | $731.91 | $1.00 – $2,500.00 | $138,478 | 1.8% |
| 420-7039 CL C CONC (COLUMN)(HPC)51 low bids · prices swing 10x | 91.7 CY | $1,492.16 | $940.00 – $9,500.00 | $136,831 | 1.8% |