Bid Tab X-ray: 1012-03-027

Aug 6, 2026 · Collin Sign up free
Set your company to personalize scores

FM 981 from SH 78 to FM 1562

1012-03-027 · let Aug 6, 2026 · Collin, Dallas · Rehabilitation of Existing Road

$18,829,388Low bid: D. L. LENNON INCORPORATED - CONTRACTOR+2.7% vs estimate $18,327,262
$521,532Left on the table2.8% gap to the second bid
7BiddersSpread 30% low to high
300Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1D. L. LENNON INCORPORATED - CONTRACTOR $18,829,3882.7% $521,532 1+$102,167 2-$3,919,890
2A. K. GILLIS & SONS, LLC $19,350,920+2.8%5.6% $629,156 1+$475,954 2-$3,840,206
3OVERLAND CORPORATION $19,980,076+6.1%9.0% $2,571,735 5+$2,017,555 4-$3,959,892
4JAGOE-PUBLIC COMPANY $22,551,810+19.8%23.1% $188,279 5+$4,443,600 3-$3,997,979
5AUSTIN BRIDGE & ROAD SERVICES, LP $22,740,089+20.8%24.1% $25,030 3+$3,124,214 1-$868,980
6STERLING DELAWARE HOLDING COMPANY $22,765,120+20.9%24.2% $1,659,121
7ED BELL CONSTRUCTION COMPANY $24,424,241+29.7%33.3%

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

D. L. LENNON INCORPORATED - CONTRACTOR vs A. K. GILLIS & SONS, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
500-7001 MOBILIZATION1 LS $470,525.00$999,804.60$523,850.32 $529,280
344-7011 SP MIXES SP-C SAC-B PG64-2218,812 TON $139.00$124.70$130.31 -$269,012
432-7031 RIPRAP (STONE COMMON)(DRY)(12 IN)3,735 CY $155.50$223.20$152.41 $252,860
247-7209 FL BS (RDWY DEL) (TY D GR 1-2)23,252 TON $47.00$57.00$51.99 $232,520
530-7010 DRIVEWAYS (ACP)12,406 SY $67.00$80.42$54.96 $166,489
354-7054 PLANE ASPH CONC PAV(5")129,487 SY $4.25$3.35$4.56 -$116,538
533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR)96,873 LF $1.15$0.1500$0.2040 -$96,873
316-7244 AGGR (TY-B OR L, GR-3)(SAC-B)1,131 CY $98.40$160.88$157.65 $70,665
100-7002 PREPARING ROW533.33 STA $352.43$484.43$6,072.92 $70,400
251-7055 REWORK BS MTL (TY C)(12")(ORD COMP)136,225 SY $3.00$2.50$2.69 -$68,113
508-7005 CONSTRUCTING DETOURS (TY3)349 SY $272.00$100.00$41.46 -$60,028
533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE)48,952 LF $1.15$0.1500$0.2394 -$48,952
508-7003 CONSTRUCTING DETOURS (TY1)491 SY $184.00$100.00$101.74 -$41,244
105-7012 RMV (12"-16") TRT/UNTRT BASE & ASPH PAV9,683 SY $19.00$14.82$8.45 -$40,475
275-7006 CEMENT TRT (EXIST MATL & NEW BASE)(6")144,576 SY $2.75$2.50$2.25 -$36,144
506-7020 CONSTRUCTION EXITS (INSTALL) (TY 1)1,632 SY $37.00$15.00$30.47 -$35,904
503-7002 PORTABLE CHANGEABLE MESSAGE SIGN4 EA $18,000.00$10,000.00$9,253.78 -$32,000
403-7001 TEMPORARY SPL SHORING953 SF $50.00$18.00$25.56 -$30,496
351-7011 FLEXIBLE PAVEMENT STRUCTURE REPAIR(12")284 SY $110.84$214.74$98.88 $29,508
400-7006 CUT & RESTORING PAV451 SY $36.50$100.00$171.81 $28,639

Positive: the low bidder was cheaper on that item. These 20 items account for $504,580 of the $521,532 gap.

D. L. LENNON INCORPORATED - CONTRACTOR: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
105-7012 RMV (12"-16") TRT/UNTRT BASE & ASPH PAV9,683 SY $19.00$8.452.25x$102,167
100-7002 PREPARING ROW533.33 STA $352.43$6,072.920.06x-$3,050,910
168-7001 VEGETATIVE WATERING103,159 TGL $0.0100$8.430.00x-$868,980

A. K. GILLIS & SONS, LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $999,804.60$523,850.321.91x$475,954
100-7002 PREPARING ROW533.33 STA $484.43$6,072.920.08x-$2,980,510
168-7001 VEGETATIVE WATERING103,159 TGL $0.1000$8.430.01x-$859,696

OVERLAND CORPORATION: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $1,998,000.00$523,850.323.81x$1,474,150
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING18 MO $22,260.00$11,585.041.92x$192,149
164-7010 DRILL SEED (PERM_RURAL_CLAY)346,694 SY $0.6100$0.21112.89x$138,296
105-7012 RMV (12"-16") TRT/UNTRT BASE & ASPH PAV9,683 SY $20.00$8.452.37x$111,850
505-7001 TMA (STATIONARY)358 DAY $500.00$217.572.30x$101,109
100-7002 PREPARING ROW533.33 STA $2,500.00$6,072.920.41x-$1,905,546
168-7001 VEGETATIVE WATERING103,159 TGL $0.0200$8.430.00x-$867,949
247-7209 FL BS (RDWY DEL) (TY D GR 1-2)23,252 TON $14.68$51.990.28x-$867,458
354-7054 PLANE ASPH CONC PAV(5")129,487 SY $2.10$4.560.46x-$318,939

JAGOE-PUBLIC COMPANY: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $2,500,000.00$523,850.324.77x$1,976,150
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING18 MO $61,500.00$11,585.045.31x$898,469
110-7001 EXCAV (ROADWAY)27,095 CY $35.00$11.683.00x$631,796
432-7031 RIPRAP (STONE COMMON)(DRY)(12 IN)3,735 CY $300.00$152.411.97x$551,245
132-7006 EMBANK (FNL)(DC)(TY C)15,557 CY $38.00$13.192.88x$385,940
100-7002 PREPARING ROW533.33 STA $500.00$6,072.920.08x-$2,972,206
168-7001 VEGETATIVE WATERING103,159 TGL $0.1000$8.430.01x-$859,696
310-7013 PRIME COAT(MC-30 OR AE-P)51,390 GAL $1.50$4.730.32x-$166,077

AUSTIN BRIDGE & ROAD SERVICES, LP: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $2,610,000.00$523,850.324.98x$2,086,150
275-7006 CEMENT TRT (EXIST MATL & NEW BASE)(6")144,576 SY $5.87$2.252.61x$524,074
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING18 MO $40,140.10$11,585.043.46x$513,991
168-7001 VEGETATIVE WATERING103,159 TGL $0.0100$8.430.00x-$868,980