Safety Improvement Projects
CCSJ 0002-02-065 · lets Dec 1, 2026 · El Paso, El Paso · FM 258, PEBBLE HILLS BLVD, SH 20, SHADOW MTN, US 62 · Hazard Elimination & Safety
$1,370,184Engineer's estimate
Items at market: $1,874,279 (+36.8%)
$1,301,554Most likely low bid$1,155,151 to $1,465,059 (middle half)
2.9Expected bidders8 plan holders, 7 regular bidders
78/100Strong fit: bid itMarket only. Set your company for a personal score
Where the low bid should land
$1,301,554
Estimate $1,370,184
$1,074,041 (1 in 10 go lower)$1,809,222 (1 in 10 go higher)
From 74 comparable let jobs (district, estimates of $548,073 to $3,425,459, last 3 years). 64% of them went under the estimate; the typical low bid was -5.0% vs estimate.
Bid / no-bid score
- Competition25 / 25Jobs like this draw about 2.9 bidders.
- Margin10 / 20Low bids land at 95% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Oct 2026 | 6507-39-001El Paso · 6 bidders | $845,627+4.4% |
| Sep 2026 | 6504-81-001El Paso · 3 bidders | $1,548,900-4.7% |
| Aug 2026 | 6498-87-001El Paso · 3 bidders | $531,000-4.3% |
| Aug 2026 | 6500-72-001Culberson · 3 bidders | $1,106,900+10.8% |
| Aug 2026 | 6505-39-001El Paso · 3 bidders | $715,750-8.9% |
| Aug 2026 | 6504-80-001El Paso · 6 bidders | $1,772,400-27.1% |
| Jul 2026 | 6498-87-001El Paso · 3 bidders | $478,000-14.4% |
| Jun 2026 | 6498-86-001El Paso · 1 bidders | $1,195,900+32.4% |
The field: plan holders and how they bid
Last 3 years in Texas| Plan holder | Bids | Wins | In El Paso | Avg bid vs est. | Avg win vs est. | Their typical bid here |
|---|---|---|---|---|---|---|
| WINDING ROAD CONSTRUCTION, INC. SharpestBidders | 37 | 7 | 1 of 2 | -0.4% | -10.1% | $1,364,126 |
| GHB EQUIPMENT COMPANY, L.L.C.Bidders | 34 | 3 | 1.2% | -19.6% | $1,386,005 | |
| TRI STATE ELECTRIC, LTD.Bidders | 15 | 10 | 10 of 15 | 1.4% | -0.2% | $1,389,930 |
| DIGG COMMERCIAL, LLCBidders | 187 | 42 | 6 of 12 | 6.8% | -5.7% | $1,463,003 |
| MARTINEZ BROS. CONTRACTORS, LLCBidders | 10 | 1 | 1 of 10 | 12.9% | -8.0% | $1,546,386 |
| RAGLE CONSTRUCTION, INC.Bidders | 251 | 38 | 2 of 3 | 13.0% | -5.0% | $1,548,235 |
| Horizone Construction I, LtdBidders | 10 | 3 | 3 of 10 | 17.3% | 28.1% | $1,607,115 |
| LESNA CONSTRUCTION, INC.Bidders | 2 | 0 | 0 of 2 | 24.4% | $1,704,582 |
"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.
Items that decide this job
224 of 229 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 1 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $523,850 | 27.9% |
| 531-7001 CONC SIDEWALKS (4")222 low bids · prices swing 57x | 2,757 SY | $70.57 | $21.64 – $1,237.00 | $194,549 | 10.4% |
| 530-7006 DRIVEWAYS (CONC)295 low bids · prices swing 134x | 1,385 SY | $109.20 | $29.89 – $4,000.00 | $151,239 | 8.1% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x | 8 MO | $11,585.04 | $0.0010 – $273,686.48 | $92,680 | 4.9% |
| 100-7002 PREPARING ROW593 low bids · prices swing 86,117,000x | 8 STA | $6,072.92 | $0.0100 – $861,170.00 | $48,583 | 2.6% |
| 530-7010 DRIVEWAYS (ACP)299 low bids · prices swing 84x | 863 SY | $54.96 | $8.88 – $750.00 | $47,427 | 2.5% |
| 686-7041 INS TRF SIG PL AM(S)1 ARM(40')35 low bids | 2 EA | $15,342.99 | $9,999.00 – $25,500.00 | $30,686 | 1.6% |
| 531-7010 CURB RAMPS (TY 7)148 low bids · prices swing 11x | 10 EA | $2,829.94 | $727.51 – $7,750.00 | $28,299 | 1.5% |
| 104-7011 REMOV CONC (DRIVEWAYS)327 low bids · prices swing 78x | 1,385 SY | $19.70 | $2.75 – $214.00 | $27,288 | 1.5% |
| 687-7001 PED POLE ASSEMBLY212 low bids · prices swing 39x | 9 EA | $2,930.76 | $383.00 – $15,000.00 | $26,377 | 1.4% |
| 682-7042 BACKPLATE W/REF BRDR(3 SEC)(VENT)ALUM138 low bids · prices swing 6x | 101 EA | $201.17 | $115.00 – $720.80 | $20,319 | 1.1% |
| 505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x | 91 DAY | $217.57 | $0.0010 – $16,487.00 | $19,799 | 1.1% |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL)834 low bids · prices swing 16,640x | 4,684 LF | $3.92 | $0.0100 – $166.40 | $18,342 | 1.0% |
| 450-7063 RAIL (HANDRAIL)(TY F)41 low bids · prices swing 4x | 102 LF | $152.24 | $100.00 – $351.00 | $15,529 | 0.8% |
| 687-7001 PED POLE ASSEMBLY212 low bids · prices swing 39x | 5 EA | $2,930.76 | $383.00 – $15,000.00 | $14,654 | 0.8% |