| 10 | 202(A)2200 |
UNCLASSIFIED EXCAVATION | 260 | CY |
$20.00 |
$14.41 |
$20.70 |
$18.70 |
$37.51 |
$21.40 |
$19.25 |
| 20 | 202(D)2500 |
UNCLASSIFIED BORROW | 109 | CY |
$30.00 |
$32.99 |
$31.40 |
$47.30 |
$65.29 |
$37.45 |
$29.25 |
| 30 | 205(A)6200 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$20,000.00 |
$10,832.04 |
$17,745.00 |
$6,000.00 |
$3,950.00 |
$16,050.00 |
$4,100.00 |
| 40 | 221(B)2300 |
TEMPORARY SILT FENCE | 3,368 | LF |
$4.00 |
$3.00 |
$3.85 |
$2.75 |
$3.30 |
$2.94 |
$3.00 |
| 50 | 230(A)7200 |
SOLID SLAB SODDING | 2,331 | SY |
$6.00 |
$5.40 |
$4.95 |
$5.40 |
$7.79 |
$7.43 |
$7.25 |
| 60 | 303(A)1200 |
AGGREGATE BASE TYPE A | 5 | CY |
$150.00 |
$258.32 |
$137.50 |
$280.00 |
$370.00 |
$117.70 |
$130.00 |
| 70 | 310(B)5300 |
SUBGRADE, METHOD B | 2,680 | SY |
$5.00 |
$5.07 |
$2.20 |
$4.25 |
$5.70 |
$5.35 |
$2.25 |
| 80 | 407(B)7300 |
TACK COAT | 364 | GAL |
$5.50 |
$8.30 |
$4.40 |
$3.00 |
$3.30 |
$3.21 |
$3.75 |
| 90 | 408 8100 |
PRIME COAT | 1,130 | GAL |
$6.50 |
$6.39 |
$6.60 |
$5.00 |
$5.40 |
$5.35 |
$5.90 |
| 100 | 411(B)1330 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 185 | TON |
$175.00 |
$201.29 |
$221.50 |
$264.50 |
$307.00 |
$246.10 |
$225.00 |
| 110 | 411(C)1430 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 220 | TON |
$185.00 |
$226.76 |
$328.50 |
$264.50 |
$275.72 |
$246.10 |
$275.00 |
| 120 | 414(A)5200 |
P.C.CONCRETE PAVEMENT(PLACEMENT) | 1,804 | SY |
$40.00 |
$23.76 |
$29.70 |
$25.00 |
$24.00 |
$19.26 |
$27.75 |
| 130 | 414(G)5800 |
P.C. CONCRETE FOR PAVEMENT | 451 | CY |
$250.00 |
$269.55 |
$242.00 |
$333.00 |
$330.00 |
$321.00 |
$225.00 |
| 140 | 509(A)0200 |
CLASS AA CONCRETE | 14 | CY |
$1,000.00 |
$719.74 |
$661.00 |
$660.00 |
$660.00 |
$642.00 |
$640.00 |
| 150 | 619(B)6360 |
REMOVAL OF CONCRETE PAVEMENT | 1,803 | SY |
$15.00 |
$11.03 |
$11.80 |
$16.50 |
$12.69 |
$20.33 |
$11.00 |
| 160 | 619(B)6364 |
REMOVAL OF ASPHALT PAVEMENT | 3,577 | SY |
$9.00 |
$10.10 |
$14.40 |
$17.50 |
$15.00 |
$8.56 |
$11.25 |
| 170 | 619(B)6396 |
REMOVAL OF GUARDRAIL | 1,057 | LF |
$7.00 |
$10.42 |
$9.55 |
$9.50 |
$5.00 |
$9.29 |
$4.50 |
| 180 | 623 1100 |
(PL)GUARDRAIL CURBING | 4 | EA |
$1,700.00 |
$1,278.67 |
$1,936.00 |
$1,665.00 |
$1,250.00 |
$2,140.00 |
$1,800.00 |
| 190 | 623(A)1200 |
BEAM GUARDRAIL W-BEAM SINGLE | 1,188 | LF |
$30.00 |
$35.17 |
$32.30 |
$32.25 |
$31.66 |
$31.37 |
$25.00 |
| 200 | 623(F)1764 |
GUARDRAIL TRAIL END TURNDOWN (31") | 2 | EA |
$1,800.00 |
$1,799.36 |
$1,652.00 |
$1,650.00 |
$1,800.00 |
$1,605.00 |
$770.00 |
| 210 | 623(G)1820 |
GUARDRAIL END TREATMENT (31") | 2 | EA |
$4,000.00 |
$4,678.32 |
$4,296.00 |
$4,290.00 |
$4,400.00 |
$4,173.00 |
$3,100.00 |
| 220 | 623(I)2050 |
GUARDRAIL BRIDGE CONN-THRIE BEAM (31") | 4 | EA |
$3,500.00 |
$4,558.36 |
$4,186.00 |
$4,180.00 |
$4,300.00 |
$4,066.00 |
$3,100.00 |
| 230 | 501(B)1300 |
SUBSTRUCTURE EXCAVATION COMMON | 20 | CY |
$40.00 |
$14.05 |
$111.00 |
$54.00 |
$212.00 |
$42.80 |
$75.00 |
| 240 | 501(G)1800 |
CLSM BACKFILL | 432.8 | CY |
$225.00 |
$217.47 |
$243.00 |
$225.00 |
$295.00 |
$340.85 |
$230.00 |
| 250 | 504(A)5200 |
APPROACH SLAB | 729.8 | SY |
$300.00 |
$289.52 |
$327.00 |
$310.00 |
$325.70 |
$323.47 |
$425.00 |
| 260 | 504(B)5300 |
SAW-CUT GROOVING | 1,621.9 | SY |
$6.00 |
$6.24 |
$5.75 |
$5.20 |
$6.40 |
$5.56 |
$5.50 |
| 270 | 504(E)5520 |
42" F-SHAPED PARAPET | 352 | LF |
$160.00 |
$152.27 |
$173.00 |
$135.00 |
$174.00 |
$153.94 |
$150.00 |
| 280 | 506(A)7200 |
STRUCTURAL STEEL | 318,120 | LB |
$3.75 |
$2.39 |
$2.55 |
$2.65 |
$2.87 |
$3.52 |
$3.26 |
| 290 | 507(A)8210 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 12 | EA |
$1,750.00 |
$2,135.13 |
$2,921.00 |
$1,960.00 |
$2,220.00 |
$2,472.38 |
$2,500.00 |
| 300 | 507(B)8310 |
WEATHERING STL EXP. BEARING ASSEMBLY | 12 | EA |
$1,750.00 |
$2,135.13 |
$2,921.00 |
$1,960.00 |
$2,450.00 |
$2,472.38 |
$2,500.00 |
| 310 | 509(A)0210 |
CLASS AA CONCRETE | 229.2 | CY |
$930.00 |
$1,093.49 |
$946.50 |
$1,096.00 |
$1,001.00 |
$912.59 |
$1,300.00 |
| 320 | 509(B)0320 |
CLASS A CONCRETE | 1 | CY |
$2,000.00 |
$1,881.08 |
$4,933.00 |
$1,955.00 |
$2,400.00 |
$1,287.09 |
$1,200.00 |
| 330 | 509(D)0510 |
CLASS C CONCRETE | 12 | CY |
$1,000.00 |
$539.58 |
$688.50 |
$785.00 |
$566.00 |
$1,274.32 |
$650.00 |
| 340 | 511 2100 |
MECHANICAL SPLICES | 12 | EA |
$100.00 |
$207.58 |
$265.50 |
$172.80 |
$264.00 |
$117.60 |
$200.00 |
| 350 | 511(B)2310 |
EPOXY COATED REINFORCING STEEL | 52,130 | LB |
$1.90 |
$1.59 |
$2.60 |
$1.73 |
$1.62 |
$1.80 |
$2.00 |
| 360 | 513(A)4200 |
CLASS A BRIDGE DECK REPAIR | 10 | SY |
$350.00 |
$431.79 |
$563.50 |
$335.00 |
$245.00 |
$233.26 |
$550.00 |
| 370 | 513(B)4300 |
CLASS B BRIDGE DECK REPAIR | 40 | SY |
$350.00 |
$391.80 |
$550.00 |
$450.00 |
$418.00 |
$410.88 |
$460.00 |
| 380 | 515(A)7200 |
WATER REPELLENT (VISUALLY INSPECTED) | 2,080 | SY |
$6.25 |
$12.60 |
$6.05 |
$5.50 |
$6.10 |
$9.73 |
$5.75 |
| 390 | 517 9110 |
ELASTOMERIC COATING | 724 | SF |
$26.00 |
$23.99 |
$22.00 |
$20.00 |
$22.00 |
$29.96 |
$25.00 |
| 400 | 518(B)0310 |
EXPANSION JOINT SYSTEM | 86 | LF |
$200.00 |
$107.96 |
$99.10 |
$99.00 |
$125.00 |
$186.18 |
$125.00 |
| 410 | 520(A)1200 |
PREPARATION OF CRACKS, ABOVE WATER | 12 | LF |
$50.00 |
$47.98 |
$44.10 |
$40.00 |
$44.00 |
$58.85 |
$50.00 |
| 420 | 520(C)1400 |
EPOXY RESIN, ABOVE WATER | 1 | GAL |
$200.00 |
$149.95 |
$137.50 |
$125.00 |
$140.00 |
$149.80 |
$150.00 |
| 430 | 521(A)2200 |
PNEUMATICALLY PLACED MORTAR | 27.2 | SY |
$950.00 |
$839.70 |
$771.00 |
$770.00 |
$920.00 |
$891.31 |
$800.00 |
| 440 | 523(A)3200 |
SEALER CRACK PREPARATION | 199 | LF |
$5.00 |
$7.20 |
$6.60 |
$6.00 |
$6.70 |
$1,064.65 |
$6.50 |
| 450 | 523(B)3300 |
SEALER RESIN | 2.2 | GAL |
$100.00 |
$221.92 |
$204.00 |
$185.00 |
$205.00 |
$207.15 |
$200.00 |
| 460 | 535 7100 |
CORROSION INHIBITOR(SURFACE APPLIED) | 34 | SY |
$50.00 |
$47.98 |
$44.10 |
$44.00 |
$49.00 |
$54.57 |
$45.00 |
| 470 | 619(B)6304 |
REMOVAL OF BRIDGE ITEMS | 1 | LSUM |
$175,000.00 |
$161,432.75 |
$137,880.00 |
$183,000.00 |
$131,000.00 |
$61,503.60 |
$145,000.00 |
| 480 | 413(D)4510 |
RUMBLE STRIP METHOD PCC-CYC | 2,164 | LF |
$1.00 |
$2.10 |
$1.95 |
$1.83 |
$1.95 |
$1.87 |
$5.25 |
| 490 | 857(A)9200 |
CONSTRUCTION TRAFFIC STR.(PAINT)(4" WIDE) | 11,380 | LF |
$0.5000 |
$0.6000 |
$0.5500 |
$0.5500 |
$0.5400 |
$0.5300 |
$0.3000 |
| 500 | 857(F)9700 |
PAVEMENT MRKNG.REMOVAL(TRAF.STRP) | 15,842 | LF |
$0.6800 |
$0.6400 |
$0.5800 |
$0.5800 |
$0.5900 |
$0.5600 |
$0.1500 |
| 510 | 871(B)2300 |
CONST.ZONE IMPACT ATTEN. | 220 | SD |
$20.00 |
$13.20 |
$12.10 |
$12.10 |
$12.20 |
$11.77 |
$5.25 |
| 520 | 871(C)2410 |
RELOCATION OF IMPACT ATTENUATOR | 4 | EA |
$1,000.00 |
$599.79 |
$551.00 |
$550.00 |
$542.00 |
$535.00 |
$25.75 |
| 530 | 877(B)4300 |
DELIVER PORTABLE LONGITUDINAL BARRIER | 3,730 | LF |
$30.00 |
$14.99 |
$13.80 |
$15.00 |
$14.50 |
$13.37 |
$25.00 |
| 540 | 877(C)4400 |
RELOCATION OF PORT. LONGITUDINAL BARRIER | 7,298 | LF |
$5.00 |
$2.40 |
$2.20 |
$3.00 |
$3.50 |
$2.14 |
$4.00 |
| 550 | 880(A)6220 |
ARROW DISPLAY(TYPE C) | 80 | SD |
$10.00 |
$53.98 |
$49.60 |
$49.50 |
$50.00 |
$48.15 |
$51.25 |
| 560 | 880(B)6300 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 5,040 | SD |
$0.5000 |
$0.7200 |
$0.6600 |
$0.6600 |
$0.6400 |
$0.6400 |
$0.6500 |
| 570 | 880(B)6310 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 6,320 | SD |
$0.7500 |
$0.0200 |
$0.0300 |
$0.0200 |
$0.0400 |
$0.0200 |
$1.05 |
| 580 | 880(B)6320 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 6,040 | SD |
$1.00 |
$2.70 |
$2.50 |
$4.50 |
$2.43 |
$2.40 |
$2.10 |
| 590 | 880(C)6410 |
CONSTRUCTION BARRICADES(TYPE III) | 1,560 | SD |
$1.50 |
$0.6000 |
$0.5500 |
$0.5500 |
$0.5600 |
$0.5300 |
$1.05 |
| 600 | 880(E)6600 |
WARNING LIGHTS(TYPE A) | 7,360 | SD |
$0.7500 |
$2.04 |
$1.85 |
$3.00 |
$1.95 |
$1.81 |
$0.3500 |
| 610 | 880(F)6700 |
DRUMS | 9,400 | SD |
$0.7500 |
$0.0200 |
$0.0500 |
$0.0200 |
$0.0400 |
$0.0200 |
$0.7500 |
| 620 | 880(G)6800 |
TUBE CHANNELIZERS | 2,660 | SD |
$0.7000 |
$0.7200 |
$0.6600 |
$0.6000 |
$0.6700 |
$0.6400 |
$1.00 |
| 630 | 880(L)7310 |
(SP) TRAFFIC SURVEILLANCE, OHP (NON-BID) | 720 | HOUR |
$77.00 |
$77.00 |
$77.00 |
$77.00 |
$77.00 |
$77.00 |
$77.00 |
| 640 | 882(A)8210 |
PORT.CHANGEABLE MESSAGE SIGN | 388 | SD |
$21.00 |
$12.00 |
$11.00 |
$11.00 |
$12.00 |
$10.70 |
$36.00 |
| 650 | 619(B)6432 |
REMOVAL OF CABLE BARRIER | 1,658 | LF |
$20.00 |
$19.25 |
$17.70 |
$17.65 |
$18.00 |
$17.17 |
$17.25 |
| 660 | 628 7100 |
INSTALLATION OF CABLE BARRIER SYSTEM | 1,658 | LF |
$30.00 |
$23.93 |
$22.00 |
$22.00 |
$22.00 |
$21.34 |
$21.50 |
| 670 | 628(C)7400 |
END ANCHORS | 4 | EA |
$8,700.00 |
$13,795.04 |
$12,670.00 |
$12,650.00 |
$12,800.00 |
$12,305.00 |
$12,300.00 |
| 680 | 628(E)7600 |
CABLE BARRIER TENSION METER | 1 | EA |
$7,000.00 |
$4,318.45 |
$3,966.00 |
$3,960.00 |
$4,200.00 |
$3,852.00 |
$3,850.00 |
| 690 | 805(D)3528 |
(PL)REMOVE & RESET EXISTING SIGNS | 2 | EA |
$500.00 |
$719.74 |
$661.00 |
$660.00 |
$690.00 |
$642.00 |
$255.00 |
| 700 | 853 5170 |
GUARDRAIL DELINEATORS(TYPE 1, CODE 1) | 28 | EA |
$25.00 |
$19.07 |
$17.50 |
$17.50 |
$18.00 |
$17.01 |
$25.75 |
| 710 | 856(A)8207 |
(SP) TRAFFIC STRIPE(PLURAL-COMPONENT)(6" WIDE) | 14,752 | LF |
$1.50 |
$1.08 |
$0.9900 |
$0.9900 |
$0.9900 |
$0.9600 |
$1.05 |
| 720 | 642(B)3300 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$10,000.00 |
$12,892.73 |
$24,355.00 |
$10,000.00 |
$7,900.00 |
$14,980.00 |
$20,000.00 |
| 730 | 641 2100 |
MOBILIZATION | 1 | LSUM |
$175,000.00 |
$176,257.01 |
$126,837.03 |
$160,900.00 |
$165,500.00 |
$142,161.21 |
$180,050.00 |