Bid tab 260043

Let Feb 19, 2026 · Division 8 · Washington Sign up free

‹ Feb 2026 results

Resurface (Asphalt)

Let date
Thursday, February 19, 2026
Contract
260043 · job page
J/P numbers
36171(04)
District
Division 8
County
Washington
Highway
US-60
Limits
US-60: FROM US-75, EXTEND EAST IN THE CITY OF BARTLESVILLE.
Classification
Resurface (Asphalt)
Project number
SSR-018N(095)SR
Working days
90

Bidders 5

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$1,545,728
1 APAC-CENTRAL, INC. Low bidder $1,142,500 -26.1%
2 BECCO CONTRACTORS, INC. $1,237,000 -20.0% +8.3%
3 SHERWOOD CONSTRUCTION CO., INC. $1,354,432 -12.4% +18.5%
4 Paragon Contractors, LLC $1,373,358 -11.2% +20.2%
5 Tri Star Construction, LLC $1,695,000 +9.7% +48.4%

Bid tab: unit prices 39 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 APAC-CENTRAL, I…#2 BECCO CONTRACTO…#3 SHERWOOD CONSTR…#4 Paragon Contrac…#5 Tri Star Constr…
10202(A)2200 UNCLASSIFIED EXCAVATION232CY $22.50 $20.00 $10.00 $37.43 $31.19 $50.00
20202(D)2500 UNCLASSIFIED BORROW200CY $50.00 $20.00 $5.00 $48.13 $44.35 $100.00
30221(B)2300 TEMPORARY SILT FENCE1,000LF $3.70 $6.95 $1.00 $8.07 $3.27 $2.00
40229 6100 DITCH LINER PROTECTION22LF $21.00 $75.00 $80.00 $80.22 $38.02 $71.00
45407(A)7200 FOG SEAL1,027GAL $5.00 $7.00 $2.00 $3.34 $5.77 $2.00
50407(B)7300 TACK COAT35GAL $12.50 $7.00 $5.00 $7.75 $21.61 $8.00
60411(C)1420 SUPERPAVE, TYPE S4(PG 70-28 OK)6,899TON $115.00 $103.50 $105.00 $119.36 $120.70 $153.00
70411(C)1430 SUPERPAVE, TYPE S4(PG 64-22 OK)105TON $200.00 $103.50 $100.00 $167.42 $161.92 $180.00
80411(H)1900 SUPERPAVE, TYPE S3(PATCH)(PG64-22OK)300TON $426.50 $103.50 $80.00 $205.01 $183.90 $200.00
90412 3100 COLD MILLING PAVEMENT61,587SY $3.00 $2.35 $2.50 $2.60 $2.42 $3.00
100501(A)1200 STRUCTURAL EXCAVATION UNCLASSIFIED21CY $40.00 $98.00 $100.00 $53.48 $110.92 $115.00
110509(A)0200 CLASS AA CONCRETE51CY $1,200.00 $794.25 $1,400.00 $1,053.56 $898.96 $1,500.00
120509(C)0400 CLASS A CONCRETE, SMALL STRUCTURES6CY $1,500.00 $500.00 $1,400.00 $1,497.44 $565.92 $1,300.00
130509(D)0500 CLASS C CONCRETE5CY $600.00 $1,023.00 $600.00 $727.33 $1,157.87 $800.00
135511(A)2200 REINFORCING STEEL9,069LB $4.15 $1.25 $2.00 $1.49 $1.41 $2.50
140619(B)6396 REMOVAL OF GUARDRAIL600LF $6.15 $3.00 $3.00 $3.21 $3.68 $3.00
150619(B)6400 REMOVAL OF CURB44LF $14.00 $31.05 $10.00 $13.20 $47.71 $61.00
160623(A)1200 BEAM GUARDRAIL W-BEAM SINGLE525LF $30.00 $23.00 $25.00 $24.60 $22.56 $23.00
170623(G)1820 GUARDRAIL END TREATMENT (31")8EA $3,320.00 $3,075.00 $3,100.00 $3,289.03 $2,671.14 $3,075.00
180853 5115 DELINEATORS(TYPE 2, CODE 1)22EA $28.00 $40.00 $40.00 $42.78 $1.13 $40.00
200857(A)9200 CONSTRUCTION TRAFFIC STR.(PAINT)(4" WIDE)77,107LF $0.1800 $0.0200 $0.0200 $0.0200 $0.0600 $0.0200
210857(F)9700 PAVEMENT MRKNG.REMOVAL(TRAF.STRP)77,107LF $0.2500 $0.0200 $0.0200 $0.0200 $0.0200 $0.0200
220857(F)9710 PAVEMENT MARKING REMOVAL(ARROWS)8EA $50.00 $50.00 $50.00 $53.48 $16.98 $50.00
230857(F)9720 PAVEMENT MARKING REMOVAL(WORDS)4EA $50.00 $75.00 $75.00 $80.22 $16.98 $75.00
240876(A)3210 (PL)TRUCK MOUNTED ATTENUATOR180SD $40.00 $5.00 $5.00 $5.35 $22.64 $5.00
250880(B)6300 CONSTRUCTION SIGNS 0 TO 6.25 SF1,710SD $0.2500 $1.00 $1.00 $1.07 $0.2800 $1.00
260880(B)6310 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF1,350SD $1.00 $0.2500 $0.3000 $0.2700 $0.2800 $0.2500
270880(B)6320 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF1,890SD $2.45 $0.2500 $0.3000 $0.2700 $0.2800 $0.2500
280880(C)6410 CONSTRUCTION BARRICADES(TYPE III)360SD $0.6000 $0.2500 $0.3000 $0.2700 $0.8500 $0.2500
290880(E)6607 WARNING LIGHTS(TYPE B)2,520SD $0.5000 $0.7500 $0.7500 $0.8000 $0.3400 $0.7500
310880(E)6616 WARNING LIGHTS(TYPE D)7,470SD $1.06 $0.2500 $0.2500 $0.2700 $0.3400 $0.2500
320880(F)6700 DRUMS720SD $0.5000 $1.00 $1.00 $1.07 $0.3400 $1.00
330880(G)6805 CHANNELIZER CONES6,750SD $0.2500 $2.00 $2.00 $2.14 $0.3400 $2.00
340856(A)8207 (SP) TRAFFIC STRIPE(PLURAL-COMPONENT)(6" WIDE)77,107LF $0.7500 $0.5400 $0.5500 $0.5800 $0.8000 $0.5400
350856(A)8219 (SP) TRAFFIC STRIPE(PLURAL-COMPONENT)(24" WIDE)212LF $21.00 $10.00 $10.00 $10.70 $16.98 $10.00
360856(B)8307 (SP) TRAFFIC STRIPE(PLURAL-COMP)(ARROWS)8EA $300.00 $155.00 $200.00 $165.78 $254.66 $155.00
370856(B)8315 (SP) TRAFFIC STRIPE(PLURAL-COMP)(WORDS)4EA $402.00 $200.00 $300.00 $213.92 $565.92 $200.00
380642(A)3200 CONSTRUCTION STAKING LEVEL I1LSUM $23,850.00 $1,351.52 $3,964.87 $2,666.52 $4,997.23 $8,500.00
390641 2110 MOBILIZATION1LSUM $85,823.00 $41,974.27 $95,000.00 $57,564.33 $92,188.57 $103,299.94