Bridge Repair
- Let date
- Thursday, October 16, 2025
- Contract
- 250297 · job page
- J/P numbers
- 38157(04)
- District
- Division 7
- County
- Caddo, Custer
- Highway
- COUNTY ROADS
- Limits
- COUNTY ROADS: AT MULTIPLE LOCATIONS IN DISTRICT V AND DISTRICT VII.
- Classification
- Bridge Repair
- Project number
- BRO-208F(138)CB
- Working days
- 60
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $551,520 | ||
| 1 | K & R BUILDERS, INC. Low bidder | $265,942 | -51.8% | |
| 2 | Wyatt Contracting | $401,960 | -27.1% | +51.1% |
| 3 | Built Right Construction, LLC | $419,840 | -23.9% | +57.9% |
| 4 | Haskell Lemon Group, LLC | $453,659 | -17.7% | +70.6% |
| 5 | LOGOS CONSTRUCTION CO., LLC | $697,721 | +26.5% | +162.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 K & R BUILDERS,… | #2 Wyatt Contracti… | #3 Built Right Con… | #4 Haskell Lemon G… | #5 LOGOS CONSTRUCT… |
|---|---|---|---|---|---|---|---|---|---|---|
| 10 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $8,000.00 | $15,000.00 | $15,000.00 | $20,000.00 | $13,975.00 | $7,448.00 |
| 20 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 10 | CY | $50.00 | $60.00 | $50.00 | $30.00 | $11.00 | $186.00 |
| 30 | 202(D)2510 | UNCLASSIFIED BORROW | 400 | CY | $225.00 | $39.75 | $90.00 | $30.00 | $16.50 | $329.00 |
| 40 | 506(A)7200 | STRUCTURAL STEEL | 55 | LB | $12.00 | $27.75 | $12.00 | $100.00 | $107.50 | $60.00 |
| 50 | 509(B)0320 | CLASS A CONCRETE | 5 | CY | $2,500.00 | $990.00 | $2,200.00 | $2,000.00 | $4,567.00 | $2,155.00 |
| 60 | 511(A)2210 | REINFORCING STEEL | 400 | LB | $5.00 | $3.63 | $5.00 | $3.00 | $18.50 | $6.00 |
| 70 | 601(A)1110 | TYPE I PLAIN RIPRAP | 650 | TON | $175.00 | $85.00 | $100.00 | $150.00 | $137.00 | $222.00 |
| 80 | 619(B)6304 | REMOVAL OF BRIDGE ITEMS | 1 | LSUM | $10,000.00 | $15,000.00 | $5,000.00 | $15,000.00 | $9,500.00 | $7,448.00 |
| 90 | 202(D)2510 | UNCLASSIFIED BORROW | 150 | CY | $250.00 | $43.50 | $100.00 | $30.00 | $16.50 | $329.00 |
| 100 | 506(A)7200 | STRUCTURAL STEEL | 60 | LB | $12.00 | $22.00 | $12.00 | $100.00 | $98.90 | $60.00 |
| 110 | 509(B)0320 | CLASS A CONCRETE | 10 | CY | $2,500.00 | $490.00 | $2,500.00 | $2,000.00 | $3,300.00 | $2,155.00 |
| 120 | 511(A)2210 | REINFORCING STEEL | 1,170 | LB | $5.00 | $3.05 | $5.00 | $3.00 | $13.00 | $6.00 |
| 130 | 601(A)1110 | TYPE I PLAIN RIPRAP | 110 | TON | $180.00 | $95.00 | $150.00 | $175.00 | $137.00 | $222.00 |
| 140 | 601(C)1310 | TYPE I-A FILTER BLANKET | 28 | TON | $150.00 | $70.00 | $100.00 | $150.00 | $114.00 | $178.00 |
| 150 | 202(D)2510 | UNCLASSIFIED BORROW | 70 | CY | $250.00 | $82.50 | $100.00 | $30.00 | $16.50 | $329.00 |
| 160 | 506(A)7200 | STRUCTURAL STEEL | 120 | LB | $12.00 | $23.50 | $12.00 | $100.00 | $98.90 | $60.00 |
| 170 | 509(B)0320 | CLASS A CONCRETE | 6 | CY | $2,500.00 | $990.00 | $5,000.00 | $2,000.00 | $4,327.00 | $2,155.00 |
| 180 | 511(A)2210 | REINFORCING STEEL | 800 | LB | $5.00 | $3.63 | $5.00 | $3.00 | $9.85 | $6.00 |
| 190 | 601(A)1110 | TYPE I PLAIN RIPRAP | 70 | TON | $190.00 | $105.00 | $175.00 | $175.00 | $137.00 | $222.00 |
| 200 | 601(C)1310 | TYPE I-A FILTER BLANKET | 16 | TON | $160.00 | $83.00 | $125.00 | $150.00 | $114.00 | $178.00 |
| 210 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $12,000.00 | $15,000.00 | $15,000.00 | $20,000.00 | $13,975.00 | $14,900.00 |
| 220 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 90 | CY | $200.00 | $33.00 | $25.00 | $30.00 | $11.00 | $186.00 |
| 230 | 506(A)7200 | STRUCTURAL STEEL | 120 | LB | $12.00 | $23.50 | $12.00 | $100.00 | $98.90 | $60.00 |
| 240 | 509(B)0320 | CLASS A CONCRETE | 6 | CY | $2,500.00 | $990.00 | $1,750.00 | $2,000.00 | $2,504.00 | $2,155.00 |
| 250 | 509(D)0510 | CLASS C CONCRETE | 4 | CY | $1,200.00 | $1,035.00 | $1,500.00 | $1,000.00 | $3,393.00 | $2,527.00 |
| 260 | 511(A)2210 | REINFORCING STEEL | 760 | LB | $5.00 | $3.82 | $5.00 | $3.00 | $10.30 | $6.00 |
| 270 | 601(A)1110 | TYPE I PLAIN RIPRAP | 290 | TON | $180.00 | $85.00 | $125.00 | $175.00 | $126.00 | $222.00 |
| 280 | 880(J)7110 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $25,000.00 | $15,000.00 | $31,000.00 | $4,000.00 | $20,319.25 | $21,000.00 |
| 290 | 641 2100 | MOBILIZATION | 1 | LSUM | $35,000.00 | $28,000.00 | $38,000.00 | $50,000.00 | $45,000.00 | $59,500.00 |