Bridge Repair
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $105,733 | ||
| 1 | PBX Corporation Low bidder | $211,221 | +99.8% | |
| 2 | Built Right Construction, LLC | $232,855 | +120.2% | +10.2% |
| 3 | K & R BUILDERS, INC. | $246,269 | +132.9% | +16.6% |
| 4 | LOGOS CONSTRUCTION CO., LLC | $313,254 | +196.3% | +48.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 PBX Corporation | #2 Built Right Con… | #3 K & R BUILDERS,… | #4 LOGOS CONSTRUCT… |
|---|---|---|---|---|---|---|---|---|---|
| 10 | 201 1100 | (PL)REMOVE DRIFT AND SILT | 1 | LSUM | $2,000.00 | $2,500.00 | $35,000.00 | $8,750.00 | $9,610.00 |
| 20 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 145 | CY | $24.57 | $50.00 | $35.00 | $38.25 | $192.00 |
| 30 | 502(B)3310 | FALSEWORK AND JACKING | 1 | LSUM | $2,500.00 | $1,800.00 | $11,500.00 | $9,750.00 | $11,530.00 |
| 40 | 509(B)0320 | CLASS A CONCRETE | 9 | CY | $1,797.31 | $2,600.00 | $1,500.00 | $2,590.00 | $2,225.00 |
| 50 | 511(B)2310 | EPOXY COATED REINFORCING STEEL | 800 | LB | $3.21 | $3.00 | $4.50 | $6.83 | $6.10 |
| 60 | 601(C)1310 | TYPE I-A FILTER BLANKET | 44 | TON | $56.30 | $110.00 | $100.00 | $89.00 | $184.00 |
| 70 | 601(F)1600 | TYPE IV GROUTED RIPRAP | 203 | SY | $150.00 | $375.00 | $225.00 | $358.00 | $555.00 |
| 80 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 3 | CY | $38.26 | $300.00 | $35.00 | $367.50 | $192.00 |
| 90 | 502(B)3310 | FALSEWORK AND JACKING | 1 | LSUM | $7,500.00 | $4,000.00 | $11,500.00 | $7,500.00 | $11,530.00 |
| 100 | 509(B)0320 | CLASS A CONCRETE | 10 | CY | $1,757.30 | $2,700.00 | $1,500.00 | $2,790.00 | $2,225.00 |
| 110 | 511(B)2310 | EPOXY COATED REINFORCING STEEL | 900 | LB | $3.16 | $3.00 | $4.50 | $7.32 | $6.10 |
| 120 | 601(C)1310 | TYPE I-A FILTER BLANKET | 2 | TON | $66.60 | $900.00 | $100.00 | $510.00 | $491.00 |
| 130 | 601(F)1600 | TYPE IV GROUTED RIPRAP | 7 | SY | $150.00 | $850.00 | $225.00 | $1,061.00 | $555.00 |
| 140 | 201 1100 | (PL)REMOVE DRIFT AND SILT | 1 | LSUM | $2,500.00 | $3,000.00 | $35,000.00 | $10,100.00 | $9,610.00 |
| 150 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 10 | CY | $38.26 | $150.00 | $35.00 | $152.50 | $192.00 |
| 160 | 501(G)1800 | CLSM BACKFILL | 1 | CY | $455.65 | $2,600.00 | $1,000.00 | $2,970.00 | $1,302.00 |
| 170 | 502(B)3310 | FALSEWORK AND JACKING | 1 | LSUM | $5,000.00 | $900.00 | $11,500.00 | $5,500.00 | $11,530.00 |
| 180 | 601(C)1310 | TYPE I-A FILTER BLANKET | 3 | TON | $66.60 | $650.00 | $150.00 | $335.50 | $363.00 |
| 190 | 601(F)1600 | TYPE IV GROUTED RIPRAP | 15 | SY | $150.00 | $650.00 | $225.00 | $648.00 | $555.00 |
| 200 | 880(J)7110 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $3,000.00 | $9,500.00 | $5,000.00 | $10,500.00 | $13,000.00 |
| 210 | 641 2100 | MOBILIZATION | 1 | LSUM | $3,000.00 | $21,356.23 | $25,000.00 | $24,000.00 | $27,119.00 |