Bridge Repair
- Let date
- Thursday, October 9, 2025
- Contract
- 250293 · job page
- J/P numbers
- 38474(04)
- District
- Division 8
- County
- Nowata, Washington
- Highway
- COUNTY ROADS
- Limits
- COUNTY ROADS: OVER FISH CREEK, COON CREEK, AND UNNAMED CREEK, AT MULTIPLE LOCATIONS IN DISTRICT VIII.
- Classification
- Bridge Repair
- Project number
- BRO-274F(045)CB
- Working days
- 150
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $796,975 | ||
| 1 | LOGOS CONSTRUCTION CO., LLC Low bidder | $403,793 | -49.3% | |
| 2 | PBX Corporation | $489,609 | -38.6% | +21.3% |
| 3 | Built Right Construction, LLC | $880,875 | +10.5% | +118.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 LOGOS CONSTRUCT… | #2 PBX Corporation | #3 Built Right Con… |
|---|---|---|---|---|---|---|---|---|
| 10 | 201 1100 | (PL)REMOVE DRIFT AND SILT | 1 | LSUM | $5,000.00 | $10,000.00 | $6,000.00 | $75,000.00 |
| 20 | 501(G)1800 | CLSM BACKFILL | 7 | CY | $800.00 | $1,000.00 | $1,300.00 | $600.00 |
| 30 | 501(G)1800 | CLSM BACKFILL | 6 | CY | $800.00 | $1,000.00 | $1,000.00 | $600.00 |
| 40 | 510(C)1500 | SOIL NAIL BANK STABILIZATION | 1 | LSUM | $250,000.00 | $74,402.00 | $105,000.00 | $275,000.00 |
| 50 | 510(C)1500 | SOIL NAIL BANK STABILIZATION | 1 | LSUM | $400,000.00 | $150,062.00 | $200,000.00 | $325,000.00 |
| 60 | 501(G)1800 | CLSM BACKFILL | 12 | CY | $800.00 | $1,000.00 | $875.00 | $600.00 |
| 70 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 445 | TON | $60.00 | $200.00 | $120.00 | $200.00 |
| 80 | 601(C)1310 | TYPE I-A FILTER BLANKET | 55 | TON | $50.00 | $90.00 | $95.00 | $125.00 |
| 90 | 880(J)7110 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $20,000.00 | $10,000.00 | $12,000.00 | $10,000.00 |
| 100 | 641 2110 | MOBILIZATION | 1 | LSUM | $72,525.00 | $40,379.33 | $82,383.93 | $85,000.00 |