Bridge Repair
- Let date
- Thursday, August 14, 2025
- Contract
- 250212 · job page
- J/P numbers
- 38133(04)
- District
- Division 5
- County
- Greer, Kiowa
- Highway
- COUNTY ROADS
- Limits
- COUNTY ROADS: OVER UNNAMED CREEKS
- Classification
- Bridge Repair
- Project number
- BRO-238F(102)CB
- Working days
- 45
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $237,600 | ||
| 1 | Haskell Lemon Group, LLC Low bidder | $147,612 | -37.9% | |
| 2 | B & B CONSTRUCTION SERVICE J.T., INC. | $160,260 | -32.6% | +8.6% |
| 3 | K & R BUILDERS, INC. | $184,737 | -22.2% | +25.2% |
| 4 | SEWELL BROS., INC. | $188,300 | -20.7% | +27.6% |
| 5 | PBX Corporation | $193,619 | -18.5% | +31.2% |
| 6 | LOGOS CONSTRUCTION CO., LLC | $205,055 | -13.7% | +38.9% |
| 7 | Built Right Construction, LLC | $242,300 | +2.0% | +64.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Haskell Lemon G… | #2 B & B CONSTRUCT… | #3 K & R BUILDERS,… | #4 SEWELL BROS., I… | #5 PBX Corporation | #6 LOGOS CONSTRUCT… | #7 Built Right Con… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 10 | 501(G)1800 | CLSM BACKFILL | 10 | CY | $1,500.00 | $629.50 | $1,200.00 | $1,102.00 | $900.00 | $1,000.00 | $485.00 | $1,500.00 |
| 20 | 601(A)1110 | TYPE I PLAIN RIPRAP | 60 | TON | $200.00 | $121.00 | $126.00 | $116.50 | $135.00 | $285.00 | $320.00 | $300.00 |
| 30 | 613(Z)8400 | DEWATERING | 8 | DAY | $1,000.00 | $330.00 | $330.00 | $505.00 | $2,000.00 | $400.00 | $700.00 | $500.00 |
| 40 | 619(A)6200 | REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM | $3,000.00 | $10,408.65 | $4,000.00 | $4,250.00 | $5,000.00 | $3,500.00 | $17,000.00 | $5,000.00 |
| 50 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $12,000.00 | $10,628.65 | $1,500.00 | $7,250.00 | $10,000.00 | $3,500.00 | $9,500.00 | $10,000.00 |
| 60 | 202(D)2510 | UNCLASSIFIED BORROW | 60 | CY | $400.00 | $16.50 | $19.00 | $76.00 | $200.00 | $105.00 | $105.00 | $30.00 |
| 70 | 501(G)1800 | CLSM BACKFILL | 8 | CY | $1,200.00 | $724.50 | $1,200.00 | $1,153.00 | $950.00 | $1,000.00 | $485.00 | $1,500.00 |
| 80 | 601(A)1110 | TYPE I PLAIN RIPRAP | 30 | TON | $200.00 | $137.50 | $150.00 | $154.00 | $150.00 | $285.00 | $320.00 | $300.00 |
| 90 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $8,000.00 | $11,728.65 | $5,500.00 | $8,000.00 | $10,000.00 | $3,500.00 | $9,500.00 | $10,000.00 |
| 100 | 501(G)1800 | CLSM BACKFILL | 10 | CY | $1,200.00 | $629.50 | $1,000.00 | $1,058.00 | $900.00 | $1,000.00 | $485.00 | $1,500.00 |
| 110 | 601(A)1110 | TYPE I PLAIN RIPRAP | 50 | TON | $200.00 | $137.50 | $205.00 | $133.50 | $150.00 | $285.00 | $320.00 | $300.00 |
| 120 | 613(Z)8400 | DEWATERING | 8 | DAY | $1,000.00 | $330.00 | $330.00 | $655.50 | $1,200.00 | $400.00 | $700.00 | $500.00 |
| 130 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $8,000.00 | $11,178.65 | $5,900.00 | $8,400.00 | $10,000.00 | $7,000.00 | $9,500.00 | $10,000.00 |
| 140 | 501(G)1800 | CLSM BACKFILL | 10 | CY | $1,200.00 | $629.50 | $1,000.00 | $1,049.00 | $900.00 | $1,100.00 | $485.00 | $1,500.00 |
| 150 | 601(A)1110 | TYPE I PLAIN RIPRAP | 70 | TON | $200.00 | $137.50 | $207.00 | $120.00 | $150.00 | $285.00 | $320.00 | $300.00 |
| 160 | 613(Z)8400 | DEWATERING | 8 | DAY | $1,000.00 | $330.00 | $330.00 | $655.50 | $2,000.00 | $400.00 | $700.00 | $500.00 |
| 170 | 501(G)1800 | CLSM BACKFILL | 5 | CY | $1,200.00 | $871.50 | $1,800.00 | $1,594.00 | $950.00 | $1,100.00 | $485.00 | $1,500.00 |
| 180 | 601(A)1110 | TYPE I PLAIN RIPRAP | 20 | TON | $200.00 | $137.50 | $150.00 | $188.00 | $175.00 | $350.00 | $320.00 | $300.00 |
| 190 | 501(G)1800 | CLSM BACKFILL | 10 | CY | $1,200.00 | $560.00 | $1,000.00 | $1,046.00 | $900.00 | $925.00 | $485.00 | $1,500.00 |
| 200 | 601(A)1110 | TYPE I PLAIN RIPRAP | 30 | TON | $200.00 | $137.50 | $150.00 | $152.00 | $175.00 | $350.00 | $320.00 | $300.00 |
| 210 | 880(J)7110 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $10,000.00 | $10,858.65 | $2,000.00 | $23,000.00 | $2,000.00 | $8,500.00 | $7,750.00 | $10,000.00 |
| 220 | 641 2100 | MOBILIZATION | 1 | LSUM | $30,000.00 | $14,500.00 | $27,400.00 | $20,000.00 | $10,000.00 | $20,619.32 | $19,800.00 | $26,000.00 |