Bridge Repair
- Let date
- Thursday, August 14, 2025
- Contract
- 250210 · job page
- J/P numbers
- 38221(04)
- District
- Division 7
- County
- Caddo, Grady, Mcclain
- Highway
- COUNTY ROADS
- Limits
- COUNTY ROADS: OVER RED BLANKET CREEK AND UNNAMED CREEKS
- Classification
- Bridge Repair
- Project number
- BRO-226F(135)CB
- Working days
- 180
Bidders 8
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | SAC Services, Inc. Low bidder | $427,170 | ||
| 2 | K & R BUILDERS, INC. | $462,485 | +8.3% | |
| 3 | B & B CONSTRUCTION SERVICE J.T., INC. | $535,884 | +25.4% | |
| 4 | Redlands Contracting, LLC | $542,960 | +27.1% | |
| 5 | PBX Corporation | $563,269 | +31.9% | |
| 6 | Built Right Construction, LLC | $579,875 | +35.7% | |
| 7 | LOGOS CONSTRUCTION CO., LLC | $657,572 | +53.9% | |
| 8 | Haskell Lemon Group, LLC | $694,286 | +62.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 SAC Services, I… | #2 K & R BUILDERS,… | #3 B & B CONSTRUCT… | #4 Redlands Contra… | #5 PBX Corporation | #6 Built Right Con… | #7 LOGOS CONSTRUCT… | #8 Haskell Lemon G… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 10 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 30 | CY | $250.00 | $50.00 | $61.50 | $100.00 | $55.00 | $70.00 | $50.00 | $220.00 | $16.20 |
| 20 | 202(D)2510 | UNCLASSIFIED BORROW | 353 | CY | $60.00 | $45.00 | $37.50 | $25.00 | $60.00 | $68.00 | $25.00 | $60.00 | $16.20 |
| 30 | 501(G)1800 | CLSM BACKFILL | 3 | CY | $1,200.00 | $685.00 | $1,850.00 | $1,500.00 | $650.00 | $2,500.00 | $500.00 | $560.00 | $899.50 |
| 40 | 506(A)7200 | STRUCTURAL STEEL | 50 | LB | $12.00 | $85.00 | $29.25 | $45.00 | $150.00 | $40.00 | $50.00 | $24.00 | $51.20 |
| 50 | 509(B)0320 | CLASS A CONCRETE | 16 | CY | $2,500.00 | $1,150.00 | $1,490.00 | $2,600.00 | $1,650.00 | $2,800.00 | $2,500.00 | $2,500.00 | $2,327.00 |
| 60 | 511(A)2210 | REINFORCING STEEL | 1,600 | LB | $5.00 | $3.00 | $1.96 | $4.10 | $5.00 | $2.25 | $3.00 | $2.40 | $5.15 |
| 70 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 341 | TON | $185.00 | $110.00 | $89.00 | $140.00 | $130.00 | $175.00 | $150.00 | $195.00 | $124.00 |
| 80 | 601(C)1310 | TYPE I-A FILTER BLANKET | 69 | TON | $130.00 | $95.00 | $70.20 | $100.00 | $125.00 | $155.00 | $100.00 | $175.00 | $108.00 |
| 90 | 619(A)6200 | REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM | $15,000.00 | $6,950.00 | $9,750.00 | $2,250.00 | $15,000.00 | $3,000.00 | $5,000.00 | $14,000.00 | $10,350.00 |
| 100 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $10,000.00 | $7,100.00 | $6,000.00 | $3,000.00 | $15,000.00 | $6,000.00 | $10,000.00 | $10,000.00 | $21,970.00 |
| 110 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 15 | CY | $250.00 | $50.00 | $88.00 | $100.00 | $55.00 | $75.00 | $50.00 | $220.00 | $429.00 |
| 120 | 501(G)1800 | CLSM BACKFILL | 4 | CY | $1,200.00 | $685.00 | $1,350.00 | $1,000.00 | $650.00 | $1,200.00 | $500.00 | $560.00 | $1,242.00 |
| 130 | 509(B)0320 | CLASS A CONCRETE | 11 | CY | $2,500.00 | $1,150.00 | $1,675.00 | $2,385.74 | $1,650.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,315.00 |
| 140 | 511(A)2210 | REINFORCING STEEL | 1,500 | LB | $5.00 | $3.00 | $1.96 | $4.10 | $5.00 | $2.25 | $3.00 | $2.40 | $5.10 |
| 150 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 20 | CY | $250.00 | $50.00 | $88.00 | $100.00 | $55.00 | $85.00 | $50.00 | $220.00 | $16.20 |
| 160 | 509(B)0320 | CLASS A CONCRETE | 25 | CY | $2,500.00 | $1,150.00 | $1,366.00 | $1,800.00 | $1,650.00 | $2,000.00 | $2,500.00 | $2,500.00 | $1,706.00 |
| 170 | 511(A)2210 | REINFORCING STEEL | 3,300 | LB | $5.00 | $3.00 | $1.80 | $3.50 | $5.00 | $2.25 | $3.00 | $2.40 | $2.85 |
| 180 | 601(A)1110 | TYPE I PLAIN RIPRAP | 35 | TON | $200.00 | $110.00 | $125.15 | $150.00 | $130.00 | $250.00 | $150.00 | $195.00 | $135.00 |
| 190 | 619(A)6200 | REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM | $15,000.00 | $7,100.00 | $6,250.00 | $2,750.00 | $10,000.00 | $3,000.00 | $5,000.00 | $15,000.00 | $15,260.00 |
| 200 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 20 | CY | $250.00 | $50.00 | $103.50 | $200.00 | $55.00 | $75.00 | $50.00 | $220.00 | $1,296.00 |
| 210 | 501(G)1800 | CLSM BACKFILL | 15 | CY | $1,000.00 | $685.00 | $650.00 | $500.00 | $650.00 | $1,200.00 | $500.00 | $560.00 | $488.00 |
| 220 | 502(B)3320 | (PL)FALSEWORK JACKING | 1 | LSUM | $25,000.00 | $12,950.00 | $91,000.00 | $39,000.00 | $13,500.00 | $18,000.00 | $35,000.00 | $33,243.00 | $110,540.00 |
| 230 | 509(B)0320 | CLASS A CONCRETE | 50 | CY | $2,500.00 | $1,150.00 | $750.00 | $1,677.12 | $1,650.00 | $2,000.00 | $2,500.00 | $2,500.00 | $1,058.00 |
| 240 | 511(A)2210 | REINFORCING STEEL | 14,000 | LB | $5.00 | $3.00 | $1.70 | $4.00 | $4.75 | $2.25 | $3.00 | $2.40 | $2.30 |
| 250 | 613(Z)8400 | DEWATERING | 20 | DAY | $1,000.00 | $685.00 | $200.00 | $5.00 | $250.00 | $300.00 | $350.00 | $800.00 | $4,113.00 |
| 260 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $12,000.00 | $7,100.00 | $12,000.00 | $2,500.00 | $15,000.00 | $5,500.00 | $5,000.00 | $8,631.00 | $21,970.00 |
| 270 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 10 | CY | $300.00 | $50.00 | $95.50 | $150.00 | $55.00 | $75.00 | $50.00 | $220.00 | $111.50 |
| 280 | 509(B)0320 | CLASS A CONCRETE | 13 | CY | $2,500.00 | $1,150.00 | $1,615.00 | $2,646.89 | $1,650.00 | $2,800.00 | $2,500.00 | $2,500.00 | $2,005.00 |
| 290 | 511(A)2210 | REINFORCING STEEL | 1,600 | LB | $5.00 | $3.00 | $1.96 | $4.00 | $5.00 | $2.25 | $3.00 | $2.40 | $2.90 |
| 300 | 613(Z)8400 | DEWATERING | 10 | DAY | $1,000.00 | $685.00 | $530.00 | $5.00 | $250.00 | $300.00 | $350.00 | $800.00 | $1,132.00 |
| 310 | 880(J)7110 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $25,000.00 | $16,800.00 | $36,400.00 | $6,500.00 | $15,000.00 | $9,500.00 | $7,500.00 | $15,573.01 | $12,995.00 |
| 320 | 641 2100 | MOBILIZATION | 1 | LSUM | $30,000.00 | $62,500.00 | $35,000.00 | $63,000.00 | $50,000.00 | $58,470.18 | $58,000.00 | $55,829.61 | $49,167.45 |