Bridge Repair
- Let date
- Thursday, August 14, 2025
- Contract
- 250209 · job page
- J/P numbers
- 38163(04)
- District
- Division 7
- County
- Caddo, Comanche, Jefferson
- Highway
- COUNTY ROADS
- Limits
- COUNTY ROADS: OVER SPRING CREEK
- Classification
- Bridge Repair
- Project number
- BRO-216F(128)CB
- Working days
- 120
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | B & B CONSTRUCTION SERVICE J.T., INC. Low bidder | $219,395 | ||
| 2 | Haskell Lemon Group, LLC | $249,032 | +13.5% | |
| 3 | K & R BUILDERS, INC. | $264,194 | +20.4% | |
| 4 | LOGOS CONSTRUCTION CO., LLC | $299,210 | +36.4% | |
| 5 | PBX Corporation | $336,223 | +53.3% | |
| 6 | Built Right Construction, LLC | $378,500 | +72.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 B & B CONSTRUCT… | #2 Haskell Lemon G… | #3 K & R BUILDERS,… | #4 LOGOS CONSTRUCT… | #5 PBX Corporation | #6 Built Right Con… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 10 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $15,000.00 | $5,000.00 | $11,585.00 | $16,500.00 | $13,700.00 | $15,000.00 | $15,000.00 |
| 20 | 501(G)1800 | CLSM BACKFILL | 10 | CY | $1,200.00 | $1,250.00 | $425.00 | $1,075.00 | $450.00 | $1,600.00 | $1,000.00 |
| 30 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $8,000.00 | $1,500.00 | $8,349.00 | $3,125.00 | $5,000.00 | $5,000.00 | $15,000.00 |
| 40 | 601(A)1110 | TYPE I PLAIN RIPRAP | 15 | TON | $170.00 | $150.00 | $102.00 | $127.00 | $215.00 | $350.00 | $250.00 |
| 50 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $8,000.00 | $2,500.00 | $12,610.00 | $16,000.00 | $6,500.00 | $17,000.00 | $15,000.00 |
| 60 | 601(A)1110 | TYPE I PLAIN RIPRAP | 90 | TON | $180.00 | $135.00 | $83.60 | $103.00 | $215.00 | $350.00 | $250.00 |
| 70 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 3 | CY | $300.00 | $50.00 | $176.00 | $700.00 | $200.00 | $190.00 | $50.00 |
| 80 | 501(G)1800 | CLSM BACKFILL | 6 | CY | $1,200.00 | $1,500.00 | $1,037.00 | $1,575.00 | $500.00 | $1,000.00 | $1,000.00 |
| 90 | 601(A)1110 | TYPE I PLAIN RIPRAP | 40 | TON | $200.00 | $140.00 | $151.50 | $165.00 | $215.00 | $250.00 | $250.00 |
| 100 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $6,000.00 | $2,500.00 | $8,608.00 | $3,112.50 | $6,500.00 | $4,000.00 | $15,000.00 |
| 110 | 601(A)1110 | TYPE I PLAIN RIPRAP | 10 | TON | $200.00 | $200.00 | $120.50 | $321.00 | $215.00 | $300.00 | $250.00 |
| 120 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $10,000.00 | $3,000.00 | $12,100.00 | $4,025.00 | $8,100.00 | $3,000.00 | $15,000.00 |
| 130 | 601(A)1110 | TYPE I PLAIN RIPRAP | 50 | TON | $200.00 | $140.00 | $103.50 | $144.50 | $215.00 | $250.00 | $250.00 |
| 140 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $10,000.00 | $2,500.00 | $8,095.00 | $5,325.00 | $8,000.00 | $4,000.00 | $15,000.00 |
| 150 | 601(A)1110 | TYPE I PLAIN RIPRAP | 12 | TON | $200.00 | $200.00 | $118.50 | $438.50 | $215.00 | $300.00 | $250.00 |
| 160 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 70 | CY | $300.00 | $35.00 | $122.50 | $80.00 | $170.00 | $80.00 | $50.00 |
| 170 | 601(A)1110 | TYPE I PLAIN RIPRAP | 90 | TON | $200.00 | $207.00 | $131.00 | $150.50 | $215.00 | $225.00 | $250.00 |
| 180 | 613(Z)8400 | DEWATERING | 14 | DAY | $1,000.00 | $5.00 | $765.00 | $257.50 | $540.00 | $300.00 | $350.00 |
| 190 | 501(G)1800 | CLSM BACKFILL | 4 | CY | $1,200.00 | $1,500.00 | $536.50 | $1,851.00 | $500.00 | $1,400.00 | $1,000.00 |
| 200 | 601(A)1110 | TYPE I PLAIN RIPRAP | 30 | TON | $190.00 | $175.00 | $146.50 | $170.00 | $215.00 | $285.00 | $250.00 |
| 210 | 501(G)1800 | CLSM BACKFILL | 5 | CY | $1,200.00 | $1,500.00 | $567.50 | $2,050.00 | $1,000.00 | $1,400.00 | $1,000.00 |
| 220 | 601(A)1110 | TYPE I PLAIN RIPRAP | 140 | TON | $185.00 | $145.00 | $105.00 | $113.00 | $215.00 | $250.00 | $250.00 |
| 230 | 613(Z)8400 | DEWATERING | 7 | DAY | $1,000.00 | $5.00 | $1,025.00 | $562.50 | $540.00 | $495.00 | $350.00 |
| 240 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $12,000.00 | $2,250.00 | $11,105.00 | $6,100.00 | $6,500.00 | $6,000.00 | $15,000.00 |
| 250 | 501(G)1800 | CLSM BACKFILL | 5 | CY | $1,200.00 | $1,500.00 | $387.00 | $1,425.00 | $450.00 | $1,200.00 | $1,000.00 |
| 260 | 601(A)1110 | TYPE I PLAIN RIPRAP | 51 | TON | $190.00 | $140.00 | $81.50 | $132.50 | $215.00 | $255.00 | $250.00 |
| 270 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $10,000.00 | $3,900.00 | $9,096.00 | $7,650.00 | $3,300.00 | $4,500.00 | $15,000.00 |
| 280 | 501(G)1800 | CLSM BACKFILL | 15 | CY | $1,200.00 | $1,000.00 | $335.00 | $775.00 | $500.00 | $800.00 | $1,000.00 |
| 290 | 601(A)1110 | TYPE I PLAIN RIPRAP | 90 | TON | $190.00 | $138.00 | $89.90 | $123.50 | $215.00 | $235.00 | $250.00 |
| 300 | 880(J)7110 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $45,000.00 | $3,500.00 | $27,531.85 | $20,700.00 | $29,250.00 | $12,500.00 | $10,000.00 |
| 310 | 641 2100 | MOBILIZATION | 1 | LSUM | $65,000.00 | $37,400.00 | $24,500.00 | $24,000.00 | $31,400.00 | $34,983.05 | $38,000.00 |