Bridge Repair
- Let date
- Thursday, August 14, 2025
- Contract
- 250206 · job page
- J/P numbers
- 38180(04)
- District
- Division 7
- County
- Caddo, Comanche, Cotton
- Highway
- COUNTY ROADS
- Limits
- COUNTY ROADS: OVER WASHITA RIVER AND UNNAMED CREEKS
- Classification
- Bridge Repair
- Project number
- BRO-208F(139)CB
- Working days
- 80
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $753,100 | ||
| 1 | Haskell Lemon Group, LLC Low bidder | $496,719 | -34.0% | |
| 2 | K & R BUILDERS, INC. | $530,280 | -29.6% | +6.8% |
| 3 | Built Right Construction, LLC | $867,475 | +15.2% | +74.6% |
| 4 | LOGOS CONSTRUCTION CO., LLC | $867,475 | +15.2% | +74.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Haskell Lemon G… | #2 K & R BUILDERS,… | #3 Built Right Con… | #4 LOGOS CONSTRUCT… |
|---|---|---|---|---|---|---|---|---|---|
| 10 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 25 | CY | $300.00 | $31.60 | $68.50 | $225.00 | $150.00 |
| 20 | 501(G)1800 | CLSM BACKFILL | 30 | CY | $1,000.00 | $338.50 | $435.00 | $300.00 | $450.00 |
| 30 | 514(H)5900 | SHEET PILING, FURNISHED | 15 | SY | $300.00 | $1,091.00 | $720.00 | $500.00 | $1,320.00 |
| 40 | 514(I)6000 | SHEET PILING, DRIVEN | 15 | SY | $100.00 | $127.50 | $80.00 | $650.00 | $146.00 |
| 50 | 601(A)1110 | TYPE I PLAIN RIPRAP | 70 | TON | $180.00 | $85.00 | $117.00 | $150.00 | $191.00 |
| 60 | 501(G)1800 | CLSM BACKFILL | 15 | CY | $1,200.00 | $452.50 | $950.00 | $300.00 | $450.00 |
| 70 | 514(H)5900 | SHEET PILING, FURNISHED | 50 | SY | $250.00 | $552.50 | $495.00 | $500.00 | $765.00 |
| 80 | 514(I)6000 | SHEET PILING, DRIVEN | 50 | SY | $80.00 | $134.50 | $55.00 | $650.00 | $85.00 |
| 90 | 601(A)1110 | TYPE I PLAIN RIPRAP | 160 | TON | $190.00 | $79.40 | $114.00 | $140.00 | $191.00 |
| 100 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 128 | CY | $150.00 | $37.00 | $40.50 | $225.00 | $150.00 |
| 110 | 202(D)2510 | UNCLASSIFIED BORROW | 128 | CY | $250.00 | $60.40 | $59.50 | $50.00 | $50.00 |
| 120 | 506(A)7200 | STRUCTURAL STEEL | 1,600 | LB | $10.00 | $9.80 | $11.00 | $20.00 | $36.00 |
| 130 | 514(H)5900 | SHEET PILING, FURNISHED | 180 | SY | $225.00 | $222.00 | $258.75 | $250.00 | $333.75 |
| 140 | 514(I)6000 | SHEET PILING, DRIVEN | 180 | SY | $75.00 | $49.70 | $28.75 | $250.00 | $37.00 |
| 150 | 619(B)6304 | REMOVAL OF BRIDGE ITEMS | 1 | LSUM | $10,000.00 | $12,210.00 | $12,500.00 | $10,000.00 | $12,700.00 |
| 160 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $25,000.00 | $26,190.00 | $20,000.00 | $5,000.00 | $26,427.00 |
| 170 | 202(D)2510 | UNCLASSIFIED BORROW | 2,850 | CY | $60.00 | $39.60 | $27.75 | $50.00 | $50.00 |
| 180 | 514(H)5900 | SHEET PILING, FURNISHED | 170 | SY | $200.00 | $384.00 | $450.00 | $500.00 | $556.00 |
| 190 | 514(I)6000 | SHEET PILING, DRIVEN | 170 | SY | $70.00 | $45.00 | $50.00 | $650.00 | $61.75 |
| 200 | 601(A)1110 | TYPE I PLAIN RIPRAP | 1,200 | TON | $170.00 | $55.80 | $93.00 | $140.00 | $181.00 |
| 210 | 880(J)7110 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $20,000.00 | $11,110.00 | $5,000.00 | $7,500.00 | $12,900.00 |
| 220 | 641 2100 | MOBILIZATION | 1 | LSUM | $35,000.00 | $28,392.05 | $40,000.00 | $55,000.00 | $68,375.60 |