Bridge Repair
- Let date
- Thursday, August 14, 2025
- Contract
- 250205 · job page
- J/P numbers
- 38150(04)
- District
- Division 5
- County
- Blaine, Caddo
- Highway
- COUNTY ROADS
- Limits
- COUNTY ROADS: OVER SUGAR CREEK
- Classification
- Bridge Repair
- Project number
- BRO-208F(137)CB
- Working days
- 90
Bidders 8
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | B & B CONSTRUCTION SERVICE J.T., INC. Low bidder | $280,270 | ||
| 2 | Haskell Lemon Group, LLC | $299,180 | +6.7% | |
| 3 | SAC Services, Inc. | $358,885 | +28.0% | |
| 4 | K & R BUILDERS, INC. | $360,046 | +28.5% | |
| 5 | SEWELL BROS., INC. | $458,395 | +63.6% | |
| 6 | LOGOS CONSTRUCTION CO., LLC | $487,998 | +74.1% | |
| 7 | Redlands Contracting, LLC | $591,610 | +111.1% | |
| 8 | Built Right Construction, LLC | $689,750 | +146.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 B & B CONSTRUCT… | #2 Haskell Lemon G… | #3 SAC Services, I… | #4 K & R BUILDERS,… | #5 SEWELL BROS., I… | #6 LOGOS CONSTRUCT… | #7 Redlands Contra… | #8 Built Right Con… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 10 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $9,000.00 | $2,250.00 | $6,361.00 | $7,200.00 | $11,100.00 | $10,000.00 | $10,000.00 | $20,000.00 | $35,000.00 |
| 20 | 501(G)1800 | CLSM BACKFILL | 15 | CY | $900.00 | $975.00 | $460.00 | $650.00 | $1,075.00 | $950.00 | $420.00 | $750.00 | $1,000.00 |
| 30 | 601(A)1110 | TYPE I PLAIN RIPRAP | 90 | TON | $175.00 | $135.00 | $121.00 | $110.00 | $112.50 | $135.00 | $182.00 | $250.00 | $300.00 |
| 40 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $8,000.00 | $4,500.00 | $8,561.00 | $6,700.00 | $11,000.00 | $10,000.00 | $12,300.00 | $25,000.00 | $35,000.00 |
| 50 | 501(G)1800 | CLSM BACKFILL | 5 | CY | $1,200.00 | $1,250.00 | $879.50 | $650.00 | $1,650.00 | $950.00 | $420.00 | $750.00 | $1,000.00 |
| 60 | 601(A)1110 | TYPE I PLAIN RIPRAP | 10 | TON | $200.00 | $155.00 | $137.50 | $125.00 | $246.50 | $175.00 | $182.00 | $250.00 | $300.00 |
| 70 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 70 | CY | $50.00 | $25.00 | $16.50 | $55.00 | $38.50 | $200.00 | $130.00 | $45.00 | $50.00 |
| 80 | 501(G)1800 | CLSM BACKFILL | 6 | CY | $1,200.00 | $1,200.00 | $774.50 | $710.00 | $1,460.00 | $950.00 | $420.00 | $750.00 | $1,000.00 |
| 90 | 601(A)1110 | TYPE I PLAIN RIPRAP | 185 | TON | $180.00 | $130.00 | $121.00 | $110.00 | $102.50 | $125.00 | $182.00 | $250.00 | $300.00 |
| 100 | 501(G)1800 | CLSM BACKFILL | 6 | CY | $1,200.00 | $1,200.00 | $774.50 | $650.00 | $1,460.00 | $950.00 | $420.00 | $750.00 | $1,000.00 |
| 110 | 601(A)1110 | TYPE I PLAIN RIPRAP | 80 | TON | $180.00 | $140.00 | $126.50 | $110.00 | $130.00 | $135.00 | $182.00 | $250.00 | $300.00 |
| 120 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $12,000.00 | $4,500.00 | $8,561.00 | $10,100.00 | $9,850.00 | $12,000.00 | $10,000.00 | $20,000.00 | $35,000.00 |
| 130 | 202(D)2510 | UNCLASSIFIED BORROW | 1,510 | CY | $250.00 | $16.00 | $13.20 | $45.00 | $26.85 | $75.00 | $72.50 | $45.00 | $30.00 |
| 140 | 601(A)1110 | TYPE I PLAIN RIPRAP | 340 | TON | $170.00 | $130.00 | $121.00 | $110.00 | $97.50 | $135.00 | $182.00 | $250.00 | $300.00 |
| 150 | 601(C)1310 | TYPE I-A FILTER BLANKET | 86 | TON | $145.00 | $100.00 | $110.00 | $95.00 | $83.00 | $120.00 | $145.00 | $235.00 | $150.00 |
| 160 | 619(B)6304 | REMOVAL OF BRIDGE ITEMS | 1 | LSUM | $10,000.00 | $2,250.00 | $6,361.00 | $5,500.00 | $7,000.00 | $10,000.00 | $14,050.00 | $18,500.00 | $30,000.00 |
| 170 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $10,000.00 | $2,250.00 | $6,361.00 | $7,000.00 | $9,350.00 | $10,000.00 | $12,300.00 | $25,000.00 | $35,000.00 |
| 180 | 501(G)1800 | CLSM BACKFILL | 10 | CY | $1,000.00 | $1,100.00 | $565.00 | $750.00 | $1,100.00 | $900.00 | $420.00 | $750.00 | $1,000.00 |
| 190 | 601(A)1110 | TYPE I PLAIN RIPRAP | 15 | TON | $200.00 | $150.00 | $137.50 | $110.00 | $248.65 | $300.00 | $182.00 | $250.00 | $300.00 |
| 200 | 601(F)1600 | TYPE IV GROUTED RIPRAP | 120 | SY | $325.00 | $318.00 | $440.00 | $165.00 | $455.00 | $335.00 | $381.00 | $410.00 | $400.00 |
| 210 | 202(D)2510 | UNCLASSIFIED BORROW | 185 | CY | $250.00 | $20.00 | $13.20 | $45.00 | $37.50 | $200.00 | $72.50 | $60.00 | $30.00 |
| 220 | 601(A)1110 | TYPE I PLAIN RIPRAP | 85 | TON | $190.00 | $135.00 | $121.00 | $110.00 | $113.00 | $150.00 | $182.00 | $250.00 | $300.00 |
| 230 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $10,000.00 | $700.00 | $5,261.00 | $7,000.00 | $8,750.00 | $10,000.00 | $14,750.00 | $30,000.00 | $35,000.00 |
| 240 | 501(G)1800 | CLSM BACKFILL | 5 | CY | $1,500.00 | $1,200.00 | $1,364.00 | $750.00 | $1,650.00 | $950.00 | $420.00 | $750.00 | $1,000.00 |
| 250 | 880(J)7110 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $35,000.00 | $3,500.00 | $11,106.10 | $10,180.00 | $11,500.00 | $4,000.00 | $13,750.00 | $15,000.00 | $12,000.00 |
| 260 | 641 2100 | MOBILIZATION | 1 | LSUM | $50,000.00 | $24,800.00 | $29,500.00 | $76,000.00 | $30,000.00 | $22,500.00 | $44,420.00 | $50,000.00 | $69,000.00 |