Bridge Repair
- Let date
- Thursday, August 7, 2025
- Contract
- 250194 · job page
- J/P numbers
- 38144(04)
- District
- Division 7
- County
- Caddo, Grady
- Highway
- COUNTY ROADS
- Limits
- COUNTY ROADS: OVER WINTER CREEK
- Classification
- Bridge Repair ·
- Project number
- BRO-226F(134)CB
- Working days
- 130
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,181,780 | ||
| 1 | Haskell Lemon Group, LLC Low bidder | $791,731 | -33.0% | |
| 2 | K & R BUILDERS, INC. | $946,119 | -19.9% | +19.5% |
| 3 | SEWELL BROS., INC. | $1,307,770 | +10.7% | +65.2% |
| 4 | LOGOS CONSTRUCTION CO., LLC | $1,309,468 | +10.8% | +65.4% |
| 5 | Built Right Construction, LLC | $1,312,300 | +11.0% | +65.8% |
| 6 | BRIDGECO CONTRACTORS, INC. | $1,315,862 | +11.3% | +66.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Haskell Lemon G… | #2 K & R BUILDERS,… | #3 SEWELL BROS., I… | #4 LOGOS CONSTRUCT… | #5 Built Right Con… | #6 BRIDGECO CONTRA… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 10 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 10 | CY | $250.00 | $15.80 | $120.00 | $500.00 | $188.00 | $50.00 | $150.00 |
| 20 | 202(D)2510 | UNCLASSIFIED BORROW | 200 | CY | $60.00 | $15.80 | $47.50 | $150.00 | $92.00 | $25.00 | $55.00 |
| 30 | 509(B)0320 | CLASS A CONCRETE | 10 | CY | $2,500.00 | $601.50 | $1,800.00 | $2,000.00 | $2,550.00 | $4,000.00 | $2,610.00 |
| 40 | 511(A)2210 | REINFORCING STEEL | 2,500 | LB | $5.00 | $1.15 | $1.70 | $5.00 | $4.50 | $5.00 | $3.76 |
| 50 | 514(H)5900 | SHEET PILING, FURNISHED | 100 | SY | $250.00 | $334.00 | $486.00 | $260.00 | $486.00 | $350.00 | $426.09 |
| 60 | 514(I)6000 | SHEET PILING, DRIVEN | 100 | SY | $80.00 | $51.90 | $54.00 | $100.00 | $54.00 | $100.00 | $275.00 |
| 70 | 601(A)1110 | TYPE I PLAIN RIPRAP | 55 | TON | $230.00 | $110.50 | $97.00 | $190.00 | $224.28 | $150.00 | $151.65 |
| 80 | 613(Z)8400 | DEWATERING | 14 | DAY | $1,000.00 | $525.00 | $555.00 | $1,300.00 | $550.00 | $500.00 | $1,250.00 |
| 90 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $8,000.00 | $7,019.00 | $8,125.00 | $18,000.00 | $12,250.00 | $15,000.00 | $12,500.00 |
| 100 | 501(G)1800 | CLSM BACKFILL | 4 | CY | $1,500.00 | $599.50 | $1,511.00 | $2,000.00 | $540.00 | $500.00 | $1,087.50 |
| 110 | 506(A)7200 | STRUCTURAL STEEL | 500 | LB | $12.00 | $14.60 | $11.00 | $10.00 | $25.50 | $25.00 | $55.00 |
| 120 | 509(B)0320 | CLASS A CONCRETE | 15 | CY | $2,500.00 | $1,139.00 | $1,615.00 | $2,000.00 | $2,550.00 | $4,000.00 | $1,833.00 |
| 130 | 511(A)2210 | REINFORCING STEEL | 2,700 | LB | $5.00 | $2.20 | $1.77 | $5.00 | $4.50 | $5.00 | $3.70 |
| 140 | 514(A)5210 | PILES, FURNISHED (HP 10X42) | 120 | LF | $250.00 | $131.50 | $126.00 | $100.00 | $126.00 | $100.00 | $101.79 |
| 150 | 514(B)5310 | PILES, DRIVEN (HP 10X42) | 120 | LF | $125.00 | $43.20 | $14.00 | $100.00 | $14.00 | $65.00 | $154.17 |
| 160 | 514(H)5900 | SHEET PILING, FURNISHED | 50 | SY | $250.00 | $326.50 | $270.00 | $300.00 | $270.00 | $350.00 | $531.29 |
| 170 | 514(I)6000 | SHEET PILING, DRIVEN | 50 | SY | $80.00 | $103.50 | $30.00 | $150.00 | $30.00 | $100.00 | $380.00 |
| 180 | 601(A)1110 | TYPE I PLAIN RIPRAP | 55 | TON | $220.00 | $110.50 | $93.00 | $170.00 | $224.28 | $150.00 | $151.60 |
| 190 | 619(A)6200 | REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM | $12,000.00 | $8,069.00 | $10,000.00 | $15,000.00 | $12,500.00 | $7,500.00 | $8,000.00 |
| 200 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 20 | CY | $225.00 | $15.80 | $70.00 | $500.00 | $188.00 | $50.00 | $95.00 |
| 210 | 202(D)2510 | UNCLASSIFIED BORROW | 500 | CY | $60.00 | $12.60 | $30.50 | $125.00 | $92.00 | $25.00 | $47.00 |
| 220 | 506(A)7200 | STRUCTURAL STEEL | 100 | LB | $12.00 | $33.40 | $20.00 | $15.00 | $25.50 | $25.00 | $42.51 |
| 230 | 509(B)0320 | CLASS A CONCRETE | 5 | CY | $2,500.00 | $2,028.00 | $1,750.00 | $2,000.00 | $2,550.00 | $4,000.00 | $3,210.00 |
| 240 | 511(A)2210 | REINFORCING STEEL | 700 | LB | $5.00 | $3.45 | $2.45 | $5.00 | $4.50 | $5.00 | $4.60 |
| 250 | 514(H)5900 | SHEET PILING, FURNISHED | 1,000 | SY | $250.00 | $235.00 | $337.50 | $220.00 | $337.50 | $350.00 | $396.82 |
| 260 | 514(I)6000 | SHEET PILING, DRIVEN | 1,000 | SY | $80.00 | $20.70 | $37.50 | $220.00 | $37.50 | $100.00 | $95.50 |
| 270 | 601(A)1110 | TYPE I PLAIN RIPRAP | 750 | TON | $250.00 | $110.50 | $80.00 | $150.00 | $224.28 | $150.00 | $86.49 |
| 280 | 601(C)1310 | TYPE I-A FILTER BLANKET | 160 | TON | $120.00 | $89.30 | $58.50 | $100.00 | $177.00 | $100.00 | $79.00 |
| 290 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 20 | CY | $200.00 | $256.00 | $115.00 | $500.00 | $188.00 | $50.00 | $95.00 |
| 300 | 501(G)1800 | CLSM BACKFILL | 8 | CY | $900.00 | $599.50 | $875.00 | $2,000.00 | $540.00 | $500.00 | $2,297.00 |
| 310 | 506(A)7200 | STRUCTURAL STEEL | 1,600 | LB | $12.00 | $9.45 | $9.81 | $15.00 | $25.50 | $25.00 | $3.95 |
| 320 | 514(H)5900 | SHEET PILING, FURNISHED | 68 | SY | $250.00 | $268.00 | $270.00 | $220.00 | $270.00 | $350.00 | $462.31 |
| 330 | 514(I)6000 | SHEET PILING, DRIVEN | 68 | SY | $80.00 | $76.30 | $30.00 | $220.00 | $30.00 | $100.00 | $220.59 |
| 340 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $8,000.00 | $7,544.00 | $8,125.00 | $10,000.00 | $12,250.00 | $25,000.00 | $7,500.00 |
| 350 | 501(G)1800 | CLSM BACKFILL | 15 | CY | $1,500.00 | $409.50 | $800.00 | $1,500.00 | $540.00 | $500.00 | $1,850.00 |
| 360 | 514(H)5900 | SHEET PILING, FURNISHED | 45 | SY | $250.00 | $422.00 | $540.00 | $220.00 | $540.00 | $350.00 | $643.81 |
| 370 | 514(I)6000 | SHEET PILING, DRIVEN | 45 | SY | $80.00 | $98.80 | $60.00 | $220.00 | $60.00 | $100.00 | $225.59 |
| 380 | 520(A)1200 | PREPARATION OF CRACKS, ABOVE WATER | 50 | LF | $60.00 | $71.70 | $61.00 | $100.00 | $45.00 | $35.00 | $29.00 |
| 390 | 520(C)1400 | EPOXY RESIN, ABOVE WATER | 2 | GAL | $250.00 | $556.50 | $265.00 | $300.00 | $50.00 | $150.00 | $425.00 |
| 400 | 601(A)1110 | TYPE I PLAIN RIPRAP | 350 | TON | $180.00 | $110.50 | $82.50 | $150.00 | $224.28 | $150.00 | $85.58 |
| 410 | 613(Z)8400 | DEWATERING | 4 | DAY | $1,000.00 | $525.00 | $475.00 | $1,500.00 | $550.00 | $500.00 | $1,250.00 |
| 420 | 506(A)7200 | STRUCTURAL STEEL | 500 | LB | $12.00 | $14.60 | $18.50 | $15.00 | $25.50 | $25.00 | $6.30 |
| 430 | 509(B)0320 | CLASS A CONCRETE | 13 | CY | $2,500.00 | $936.50 | $1,700.00 | $2,000.00 | $2,550.00 | $4,000.00 | $1,975.00 |
| 440 | 511(A)2210 | REINFORCING STEEL | 1,650 | LB | $5.00 | $1.95 | $1.73 | $5.00 | $4.50 | $5.00 | $4.30 |
| 450 | 514(A)5210 | PILES, FURNISHED (HP 10X42) | 106 | LF | $250.00 | $138.50 | $126.00 | $100.00 | $126.00 | $75.00 | $106.79 |
| 460 | 514(B)5310 | PILES, DRIVEN (HP 10X42) | 106 | LF | $125.00 | $36.70 | $14.00 | $100.00 | $14.00 | $50.00 | $164.00 |
| 470 | 514(H)5900 | SHEET PILING, FURNISHED | 18 | SY | $250.00 | $543.50 | $414.00 | $500.00 | $414.00 | $350.00 | $1,121.00 |
| 480 | 514(I)6000 | SHEET PILING, DRIVEN | 18 | SY | $80.00 | $144.00 | $46.00 | $500.00 | $46.00 | $100.00 | $575.00 |
| 490 | 613(Z)8400 | DEWATERING | 8 | DAY | $1,000.00 | $526.00 | $475.00 | $1,500.00 | $550.00 | $500.00 | $1,250.00 |
| 500 | 619(B)6304 | REMOVAL OF BRIDGE ITEMS | 1 | LSUM | $8,000.00 | $14,745.00 | $9,000.00 | $13,000.00 | $12,500.00 | $10,000.00 | $6,000.00 |
| 510 | 880(J)7110 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $18,000.00 | $8,804.00 | $12,000.00 | $12,000.00 | $21,000.00 | $12,000.00 | $10,900.00 |
| 520 | 641 2100 | MOBILIZATION | 1 | LSUM | $30,000.00 | $43,339.53 | $68,000.00 | $60,000.00 | $90,444.66 | $110,000.00 | $72,000.00 |