Bid tab 250143

Let May 8, 2025 · Division 8 · Tulsa

‹ May 2025 results

Bridge Rehabilitation

Let date
Thursday, May 8, 2025
Contract
250143 · job page
J/P numbers
31084(04)
District
Division 8
County
Tulsa
Highway
US-75
Limits
US-75: OVER BIRD CREEK OVERFLOW, 3.4 MILES NORTH OF THE SH-11 INTERSECTION NEAR TULSA.
Classification
Bridge Rehabilitation ·
Project number
NHPP-014N(134)PM
Working days
210
DBE goal
19%

Bidders 8

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 BECCO CONTRACTORS, INC. Low bidder $4,197,000
2 Haskell Lemon Group, LLC $5,197,867 +23.8%
3 BRIDGECO CONTRACTORS, INC. $5,200,982 +23.9%
4 K & R BUILDERS, INC. $5,297,943 +26.2%
5 SHERWOOD CONSTRUCTION CO., INC. $5,458,501 +30.1%
6 C3 Construction, Inc. $5,713,942 +36.1%
7 Frontier Bridge, Inc. $5,966,615 +42.2%
8 Built Right Construction, LLC $6,048,215 +44.1%

Bid tab: unit prices 99 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 BECCO CONTRACTO…#2 Haskell Lemon G…#3 BRIDGECO CONTRA…#4 K & R BUILDERS,…#5 SHERWOOD CONSTR…#6 C3 Construction…#7 Frontier Bridge…#8 Built Right Con…
10201(A)1200 CLEARING AND GRUBBING1LSUM $50,000.00 $45,000.00 $115,000.00 $15,600.00 $120,000.00 $99,661.74 $23,895.76 $66,000.00 $10,000.00
20202(A)2200 UNCLASSIFIED EXCAVATION1,000CY $17.50 $7.00 $35.20 $18.00 $11.25 $12.98 $31.05 $35.20 $25.00
30202(D)2500 UNCLASSIFIED BORROW2,500CY $20.00 $10.00 $28.60 $20.50 $20.50 $17.81 $37.69 $28.60 $25.00
40221(B)2300 TEMPORARY SILT FENCE1,500LF $5.00 $3.00 $5.10 $3.95 $4.65 $5.05 $5.68 $8.36 $5.50
50221(E)2600 TEMPORARY SILT DIKE150LF $20.00 $25.00 $25.30 $27.50 $23.00 $30.10 $22.97 $52.25 $25.00
60230(A)7200 SOLID SLAB SODDING5,000SY $6.00 $6.00 $4.95 $6.70 $5.40 $7.31 $4.92 $11.50 $5.00
70307(K)4200 STABILIZED SUBGRADE2,140SY $13.00 $9.00 $11.00 $45.37 $24.75 $16.68 $12.01 $40.70 $45.00
80402(E)2600 TRAFFIC BOUND SURFACE COURSE TYPE E733TON $50.00 $25.00 $34.10 $40.50 $34.10 $30.25 $27.54 $34.10 $65.00
90407(B)7300 TACK COAT642GAL $6.00 $3.00 $3.30 $1.10 $3.00 $8.07 $3.52 $1.10 $2.00
100408 8100 PRIME COAT1,068GAL $7.00 $3.00 $6.60 $8.80 $6.00 $0.6100 $17.41 $8.80 $10.00
110411(B)1300 SUPERPAVE, TYPE S3(PG 76-28 OK)299TON $170.00 $110.00 $153.00 $212.00 $152.90 $119.63 $153.65 $176.00 $200.00
120411(B)1330 SUPERPAVE, TYPE S3(PG 64-22 OK)1,068TON $190.00 $105.00 $125.50 $201.60 $125.40 $106.57 $136.53 $132.00 $180.00
130411(C)1400 SUPERPAVE, TYPE S4(PG 76-28 OK)174TON $200.00 $165.00 $164.00 $256.00 $163.90 $206.87 $197.16 $258.50 $265.00
140411(C)1430 SUPERPAVE, TYPE S4(PG 64-22 OK)541TON $200.00 $115.00 $150.50 $217.00 $150.70 $119.96 $173.28 $220.00 $235.00
150412 3100 COLD MILLING PAVEMENT2,892SY $7.00 $5.00 $27.40 $23.00 $17.50 $4.72 $12.01 $25.11 $26.00
160414(B)5300 DOWEL JOINTED P.C.C.PAVT.(PLACEMENT)80SY $75.00 $130.00 $57.20 $97.00 $93.50 $290.88 $116.14 $110.22 $50.00
170414(G)5800 P.C. CONCRETE FOR PAVEMENT20CY $300.00 $200.00 $247.50 $275.00 $275.00 $306.24 $252.43 $504.51 $325.00
180509(A)0200 CLASS AA CONCRETE370CY $1,000.00 $150.00 $187.00 $325.00 $187.00 $170.97 $214.59 $550.00 $1,200.00
190613(B)5500 12" CORR. GALV. STEEL PIPE300LF $53.00 $70.00 $49.50 $46.17 $48.00 $85.59 $39.11 $49.50 $75.00
200619(B)6364 REMOVAL OF ASPHALT PAVEMENT2,970SY $11.00 $8.00 $27.10 $10.19 $17.50 $6.22 $13.80 $16.50 $20.00
210619(B)6396 REMOVAL OF GUARDRAIL972LF $8.00 $6.00 $7.70 $7.20 $9.00 $8.60 $8.84 $7.70 $10.00
220619(C)6600 SAWING PAVEMENT206LF $10.00 $7.00 $27.50 $14.00 $27.50 $6.47 $4.86 $27.50 $10.00
230623(A)1200 BEAM GUARDRAIL W-BEAM SINGLE850LF $35.00 $30.00 $26.00 $26.00 $26.00 $29.05 $29.84 $26.00 $30.00
240623(G)1820 GUARDRAIL END TREATMENT (31")3EA $4,500.00 $3,500.00 $5,868.00 $6,900.00 $5,867.40 $6,553.09 $6,733.19 $5,867.40 $3,500.00
250623(I)2050 GUARDRAIL BRIDGE CONN-THRIE BEAM (31")3EA $4,000.00 $3,500.00 $5,862.00 $6,908.00 $5,861.90 $6,546.95 $6,726.88 $5,861.90 $2,500.00
260501(G)1800 CLSM BACKFILL140CY $300.00 $115.00 $225.00 $307.71 $304.75 $281.92 $251.12 $492.90 $400.00
270502(B)3320 (PL)FALSEWORK JACKING1LSUM $350,000.00 $35,000.00 $85,000.00 $185,000.00 $257,000.00 $167,639.26 $181,394.62 $135,570.56 $75,000.00
280504(A)5200 APPROACH SLAB387.4SY $300.00 $200.00 $245.00 $306.50 $344.00 $290.25 $295.88 $283.33 $325.00
290504(B)5300 SAW-CUT GROOVING2,811SY $6.00 $5.00 $5.30 $5.35 $5.28 $5.89 $6.06 $5.28 $10.00
300504(E)5520 42" F-SHAPED PARAPET925LF $160.00 $160.00 $140.00 $152.98 $140.00 $105.70 $107.06 $210.28 $135.00
310507(A)8210 WEATHERING STEEL FIXED BEARING ASSEMBLY60EA $2,400.00 $1,500.00 $2,090.00 $3,094.00 $1,950.00 $1,282.55 $2,017.08 $2,777.96 $2,000.00
320507(B)8310 WEATHERING STL EXP. BEARING ASSEMBLY36EA $2,400.00 $1,500.00 $2,109.00 $3,094.00 $1,950.00 $1,282.55 $2,017.08 $2,725.76 $2,000.00
330509(A)0210 CLASS AA CONCRETE636.6CY $950.00 $1,100.00 $874.50 $855.50 $1,250.00 $1,191.51 $899.69 $1,447.14 $1,200.00
340509(D)0510 CLASS C CONCRETE8CY $850.00 $800.00 $533.50 $625.00 $843.00 $1,070.54 $639.31 $1,445.47 $750.00
350511(B)2310 EPOXY COATED REINFORCING STEEL210,720LB $1.80 $1.25 $1.60 $1.42 $1.67 $1.54 $1.46 $1.51 $2.50
360515(A)7200 WATER REPELLENT (VISUALLY INSPECTED)2,132SY $6.00 $6.00 $6.15 $6.15 $6.16 $6.88 $7.07 $6.16 $5.00
370517 9110 ELASTOMERIC COATING2,386SF $25.00 $20.00 $22.00 $22.65 $22.00 $24.57 $25.25 $24.54 $30.00
380518(B)0300 SEALED EXPANSION JOINTS343.5LF $450.00 $300.00 $310.50 $294.38 $390.00 $351.21 $385.95 $389.58 $300.00
390520(A)1200 PREPARATION OF CRACKS, ABOVE WATER60LF $50.00 $50.00 $50.60 $53.00 $50.60 $58.97 $58.07 $66.00 $35.00
400520(C)1400 EPOXY RESIN, ABOVE WATER1GAL $150.00 $125.00 $137.50 $156.00 $137.50 $153.57 $157.79 $165.00 $150.00
410521(A)2200 PNEUMATICALLY PLACED MORTAR25SY $1,000.00 $850.00 $935.00 $920.50 $935.00 $1,044.27 $1,072.97 $990.00 $900.00
420523(A)3200 SEALER CRACK PREPARATION58LF $6.50 $7.00 $6.60 $7.00 $6.60 $7.37 $7.57 $6.60 $5.00
430523(B)3300 SEALER RESIN1GAL $130.00 $220.00 $203.50 $225.00 $203.50 $227.28 $233.53 $203.50 $125.00
440524(A)4200 (SP) CARBON FIBER-REINFORCED POLYMER250SF $100.00 $50.00 $55.00 $59.00 $55.00 $61.43 $63.12 $49.50 $100.00
450535 7100 CORROSION INHIBITOR(SURFACE APPLIED)40SY $55.00 $50.00 $50.60 $55.00 $50.60 $58.97 $58.07 $55.00 $60.00
460540 8104 (PL)REPAIR BRIDGE ITEMS5EA $5,000.00 $3,500.00 $3,080.00 $5,920.00 $3,960.00 $3,931.37 $4,544.33 $1,540.00 $3,500.00
470619(B)6304 REMOVAL OF BRIDGE ITEMS1LSUM $250,000.00 $485,000.00 $600,000.00 $205,000.00 $312,500.00 $571,732.09 $600,000.00 $486,419.93 $75,000.00
480501(G)1800 CLSM BACKFILL100CY $320.00 $115.00 $248.00 $337.00 $304.75 $368.56 $250.04 $573.09 $400.00
490502(B)3320 (PL)FALSEWORK JACKING1LSUM $350,000.00 $34,384.80 $90,000.00 $195,000.00 $180,000.00 $178,140.03 $194,457.05 $62,700.00 $75,000.00
500504(A)5200 APPROACH SLAB275.6SY $320.00 $200.00 $396.50 $331.00 $344.00 $399.28 $316.07 $509.59 $325.00
510504(B)5300 SAW-CUT GROOVING398SY $6.00 $5.00 $5.30 $5.80 $5.28 $5.89 $6.06 $5.28 $10.00
520504(E)5500 CONCRETE PARAPET188LF $200.00 $150.00 $237.50 $176.00 $190.00 $245.71 $151.75 $265.94 $135.00
530507(A)8210 WEATHERING STEEL FIXED BEARING ASSEMBLY52EA $2,400.00 $1,500.00 $2,090.00 $3,094.00 $2,025.00 $2,887.09 $2,113.31 $2,225.89 $2,000.00
540507(B)8310 WEATHERING STL EXP. BEARING ASSEMBLY12EA $2,400.00 $1,500.00 $2,109.00 $3,094.00 $2,025.00 $2,887.09 $2,113.31 $2,252.57 $2,000.00
550509(A)0210 CLASS AA CONCRETE55.6CY $1,600.00 $1,500.00 $2,846.00 $1,680.39 $2,060.00 $3,071.38 $765.64 $3,123.16 $1,200.00
560511(B)2310 EPOXY COATED REINFORCING STEEL15,280LB $2.30 $2.00 $2.55 $1.78 $1.87 $2.76 $1.46 $2.69 $2.50
570513(B)4300 CLASS B BRIDGE DECK REPAIR100SY $380.00 $300.00 $110.00 $475.00 $350.00 $500.44 $207.10 $110.00 $400.00
580515(A)7200 WATER REPELLENT (VISUALLY INSPECTED)1,977SY $6.00 $6.00 $6.15 $6.10 $6.16 $6.88 $7.07 $6.16 $5.00
590517 9110 ELASTOMERIC COATING1,715SF $27.00 $20.00 $22.00 $23.00 $22.00 $24.57 $25.25 $24.54 $30.00
600518(B)0300 SEALED EXPANSION JOINTS121.5LF $500.00 $300.00 $395.00 $420.62 $432.50 $552.85 $393.95 $410.31 $300.00
610520(A)1200 PREPARATION OF CRACKS, ABOVE WATER60LF $50.00 $50.00 $50.60 $53.00 $50.60 $58.97 $58.07 $66.00 $35.00
620520(C)1400 EPOXY RESIN, ABOVE WATER1GAL $150.00 $125.00 $137.50 $200.00 $203.50 $153.57 $157.79 $165.00 $150.00
630521(A)2200 PNEUMATICALLY PLACED MORTAR30SY $1,000.00 $850.00 $935.00 $942.00 $935.00 $1,044.27 $1,072.97 $990.00 $900.00
640523(C)3400 DECK AREA SEALED (FLOODCOATS)1,748SY $20.00 $20.00 $20.00 $21.50 $20.02 $22.36 $22.97 $35.16 $20.00
650524(A)4200 (SP) CARBON FIBER-REINFORCED POLYMER250SF $100.00 $50.00 $55.00 $58.00 $55.00 $61.43 $63.12 $49.50 $100.00
660535 7100 CORROSION INHIBITOR(SURFACE APPLIED)15SY $55.00 $50.00 $50.60 $53.00 $50.60 $58.97 $58.07 $88.00 $60.00
670540 8104 (PL)REPAIR BRIDGE ITEMS5EA $5,000.00 $3,500.00 $3,080.00 $5,100.00 $3,960.00 $3,931.37 $4,544.33 $1,540.00 $3,500.00
680619(B)6304 REMOVAL OF BRIDGE ITEMS1LSUM $75,000.00 $145,000.00 $161,000.00 $75,000.00 $79,000.00 $122,855.19 $370,000.00 $140,587.70 $50,000.00
690857(C)9405 REMOVABLE PAVEMENT MARKING TAPE(6" WIDE)65,300LF $1.60 $0.3500 $2.50 $2.98 $2.48 $2.76 $2.84 $2.48 $2.00
700857(F)9700 PAVEMENT MRKNG.REMOVAL(TRAF.STRP)25,530LF $0.5000 $0.1500 $0.5800 $0.5900 $0.5900 $0.6500 $0.6700 $0.5800 $0.5500
710858(A)0224 PAVE.MARKERS CLASS A TYPE 2-C960EA $9.00 $5.00 $8.65 $8.50 $8.64 $9.65 $9.91 $8.64 $10.00
720858(A)0228 PAVE.MARKERS CLASS A TYPE 2-D960EA $9.00 $5.00 $8.65 $8.50 $8.64 $9.65 $9.91 $8.64 $10.00
730871(B)2300 CONST.ZONE IMPACT ATTEN.1,380SD $20.00 $2.00 $33.00 $38.00 $33.00 $36.86 $37.87 $13.20 $23.00
740876(A)3210 (PL)TRUCK MOUNTED ATTENUATOR30SD $50.00 $100.00 $13.20 $13.10 $13.20 $14.74 $15.15 $13.20 $75.00
750877(B)4300 DELIVER PORTABLE LONGITUDINAL BARRIER3,170LF $30.00 $18.00 $20.70 $20.56 $23.00 $23.09 $23.73 $20.68 $32.00
760877(C)4400 RELOCATION OF PORT. LONGITUDINAL BARRIER1,800LF $6.00 $9.00 $2.20 $22.80 $4.00 $2.46 $2.52 $2.20 $6.00
770880(A)6220 ARROW DISPLAY(TYPE C)720SD $9.00 $25.00 $3.30 $3.27 $3.30 $3.69 $3.79 $3.30 $9.00
780880(B)6300 CONSTRUCTION SIGNS 0 TO 6.25 SF138,060SD $0.3000 $0.0500 $0.0200 $0.0300 $0.0300 $0.0200 $0.0300 $0.0200 $0.5000
790880(B)6310 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF25,110SD $0.8000 $0.0500 $0.3300 $0.3300 $0.3300 $0.3700 $0.3800 $0.3300 $0.4000
800880(B)6320 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF29,130SD $1.50 $0.0500 $0.0200 $0.0300 $0.0300 $0.0200 $0.0300 $0.0200 $2.10
810880(C)6410 CONSTRUCTION BARRICADES(TYPE III)16,950SD $1.40 $0.2500 $0.0200 $0.0400 $0.0300 $0.0200 $0.0300 $0.0200 $1.75
820880(E)6607 WARNING LIGHTS(TYPE B)55,740SD $0.4300 $0.0200 $1.10 $1.08 $1.10 $1.23 $1.26 $1.10 $0.5000
830880(E)6616 WARNING LIGHTS(TYPE D)48,720SD $0.2300 $0.0200 $0.0200 $0.0300 $0.0300 $0.0200 $0.0300 $0.0200 $0.6000
840880(F)6700 DRUMS48,720SD $0.3900 $1.00 $0.0200 $0.0300 $0.0300 $0.0200 $0.0300 $0.0200 $0.3000
850880(G)6800 TUBE CHANNELIZERS345,600SD $0.5700 $0.0500 $0.0200 $0.0300 $0.0300 $0.0200 $0.0300 $0.0200 $0.4000
860882(A)8210 PORT.CHANGEABLE MESSAGE SIGN1,440SD $20.00 $55.00 $27.50 $28.00 $27.50 $30.72 $31.56 $27.50 $18.00
870413(B)4310 RUMBLE STRIP-METHOD HMA-CYC800LF $3.00 $5.00 $5.25 $5.08 $5.25 $5.83 $6.00 $5.23 $20.00
880805(A)3248 (PL)REMOVAL OF EXISTING SIGNS1LSUM $500.00 $1,000.00 $93.50 $115.00 $93.50 $104.42 $107.30 $93.50 $600.00
890850(A)1200 SHEET ALUMINUM SIGNS12SF $50.00 $40.00 $82.50 $84.00 $82.50 $92.14 $94.67 $82.50 $100.00
900851(C)2420 2 1/4" SQUARE TUBE POST48LF $20.00 $25.00 $7.70 $7.65 $7.70 $8.60 $8.84 $7.70 $20.00
910856(A)8207 (SP) TRAFFIC STRIPE(PLURAL-COMPONENT)(6" WIDE)9,060LF $0.9000 $2.50 $3.85 $3.88 $3.83 $4.27 $4.39 $3.83 $2.00
920619(B)6432 REMOVAL OF CABLE BARRIER4,010LF $10.00 $6.00 $5.45 $5.45 $5.50 $9.28 $6.49 $5.45 $17.00
930628(B)7300 HIGH-TENSION CABLE BARRIER(TL-4)3,490LF $20.00 $31.00 $33.00 $34.60 $33.00 $36.86 $37.87 $33.00 $35.00
940628(C)7400 END ANCHORS12EA $7,500.00 $5,700.00 $3,850.00 $3,850.00 $3,850.00 $4,299.93 $4,418.10 $3,850.00 $6,500.00
950628(F)7700 (PL)HIGH TENSION CABLE BARR. RE-TENSION2EA $1,100.00 $2,700.00 $1,320.00 $1,350.00 $1,320.00 $1,474.26 $1,514.78 $1,320.00 $3,000.00
960853 5170 GUARDRAIL DELINEATORS(TYPE 1, CODE 1)30EA $20.00 $20.00 $17.20 $17.10 $17.16 $19.17 $19.69 $17.16 $30.00
970871(A)2200 IMPACT ATTENUATOR1EA $36,500.00 $35,000.00 $35,180.00 $35,000.00 $35,179.00 $40,291.39 $40,367.57 $35,176.90 $15,000.00
980642(B)3300 CONSTRUCTION STAKING LEVEL II1LSUM $100,000.00 $21,400.00 $36,000.00 $24,500.00 $27,500.00 $21,716.80 $27,770.92 $24,200.00 $25,000.00
990641 2100 MOBILIZATION1LSUM $300,000.00 $230,000.00 $282,574.67 $265,000.00 $265,000.00 $245,655.49 $500,000.00 $289,621.20 $600,000.00