Bid tab 250033

Let Jan 9, 2025 · Division 8 · Nowata

‹ Jan 2025 results

Bridge Rehabilitation

Let date
Thursday, January 9, 2025
Contract
250033 · job page
J/P numbers
35137(04)
District
Division 8
County
Nowata
Highway
SH-28
Limits
SH-28: OVER PANTHER CREEK, 5.6 MILES SOUTH OF THE INTERSECTION OF US-60 NEAR NEW ALLUWE.
Classification
Bridge Rehabilitation ·
Project number
SBR-253C(069)SB
Working days
120

Bidders 8

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$1,078,591
1 BRIDGECO CONTRACTORS, INC. Low bidder $1,036,687 -3.9%
2 K & R BUILDERS, INC. $1,067,861 -1.0% +3.0%
3 C3 Construction, Inc. $1,117,647 +3.6% +7.8%
4 BRIGHT LIGHTING, INC. DBA BL TOWER CONSTRUCTION $1,205,250 +11.7% +16.3%
5 Frontier Bridge, Inc. $1,256,071 +16.5% +21.2%
6 BECCO CONTRACTORS, INC. $1,278,000 +18.5% +23.3%
7 Built Right Construction, LLC $1,283,463 +19.0% +23.8%
8 B & B CONSTRUCTION SERVICE J.T., INC. $1,308,210 +21.3% +26.2%

Bid tab: unit prices 51 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 BRIDGECO CONTRA…#2 K & R BUILDERS,…#3 C3 Construction…#4 BRIGHT LIGHTING…#5 Frontier Bridge…#6 BECCO CONTRACTO…#7 Built Right Con…#8 B & B CONSTRUCT…
10201(A)1200 CLEARING AND GRUBBING1LSUM $5,000.00 $8,500.00 $8,800.00 $4,920.88 $23,749.28 $11,555.88 $35,000.00 $20,000.00 $5,000.00
20221(B)2300 TEMPORARY SILT FENCE1,000LF $6.00 $5.95 $5.50 $6.28 $5.51 $5.35 $5.00 $6.00 $6.00
30230(A)7200 SOLID SLAB SODDING1,000SY $12.00 $8.25 $6.00 $8.82 $7.73 $7.51 $7.00 $8.00 $6.00
40233(A)0200 VEGETATIVE MULCHING0.5AC $6,000.00 $1,450.00 $200.00 $1,586.12 $1,391.10 $1,350.00 $1,250.00 $1,500.00 $3,000.00
50407(B)7300 TACK COAT168GAL $8.00 $6.00 $4.40 $7.09 $5.56 $4.32 $6.00 $7.00 $6.00
60411(C)1430 SUPERPAVE, TYPE S4(PG 64-22 OK)315TON $200.00 $188.79 $200.00 $150.91 $312.39 $187.92 $125.00 $225.00 $201.50
70412 3100 COLD MILLING PAVEMENT2,093SY $20.00 $15.23 $13.85 $9.05 $6.12 $8.49 $5.00 $10.00 $7.85
80619(B)6364 REMOVAL OF ASPHALT PAVEMENT93SY $20.00 $29.00 $18.00 $23.52 $109.44 $25.67 $30.00 $12.00 $15.00
90619(B)6396 REMOVAL OF GUARDRAIL565LF $10.00 $6.00 $6.00 $6.98 $6.12 $15.52 $5.00 $13.00 $5.50
100623(A)1200 BEAM GUARDRAIL W-BEAM SINGLE450LF $30.00 $31.00 $33.00 $35.53 $31.16 $27.00 $33.00 $30.00 $33.50
110623(G)1820 GUARDRAIL END TREATMENT (31")4EA $3,000.00 $3,950.00 $3,685.00 $4,568.05 $4,006.40 $4,428.00 $3,480.60 $4,000.00 $3,700.00
120623(I)2050 GUARDRAIL BRIDGE CONN-THRIE BEAM (31")4EA $2,500.00 $3,750.00 $3,135.00 $4,314.27 $3,783.82 $3,348.00 $3,000.00 $4,000.00 $3,190.00
130853 5175 GUARDRAIL DELINEATORS(TYPE 2, CODE 1)20EA $30.00 $29.00 $22.00 $31.72 $27.82 $16.20 $22.00 $20.00 $25.00
140202(A)2210 UNCLASSIFIED EXCAVATION30CY $25.00 $80.00 $25.50 $25.89 $452.37 $43.14 $100.00 $25.00 $50.00
150501(G)1800 CLSM BACKFILL90CY $250.00 $280.84 $220.00 $241.77 $513.86 $233.19 $200.00 $400.00 $330.00
160502(B)3310 FALSEWORK AND JACKING1LSUM $75,000.00 $29,000.00 $34,250.00 $38,921.92 $22,052.91 $57,996.59 $65,000.00 $120,000.00 $15,000.00
170504(A)5200 APPROACH SLAB217.8SY $325.00 $311.04 $334.11 $371.80 $269.12 $317.35 $280.00 $350.00 $340.88
180504(B)5300 SAW-CUT GROOVING650.3SY $6.00 $6.70 $6.60 $7.61 $6.68 $6.48 $7.00 $10.00 $7.35
190504(D)5420 CONCRETE RAIL (TR4)383.8LF $115.00 $108.00 $114.00 $113.28 $194.46 $132.88 $165.00 $175.00 $185.00
200506(A)7200 STRUCTURAL STEEL3,000LB $6.00 $9.70 $9.57 $10.15 $11.11 $11.33 $5.00 $5.00 $12.00
210507(A)8210 WEATHERING STEEL FIXED BEARING ASSEMBLY12EA $3,000.00 $1,990.00 $1,400.00 $1,216.50 $4,193.48 $1,485.80 $1,500.00 $2,500.00 $1,700.00
220507(B)8310 WEATHERING STL EXP. BEARING ASSEMBLY12EA $3,000.00 $1,990.00 $1,400.00 $1,258.79 $4,193.48 $1,485.80 $1,500.00 $2,500.00 $1,700.00
230509(A)0210 CLASS AA CONCRETE139.4CY $900.00 $900.00 $1,295.00 $1,166.11 $886.48 $1,663.71 $1,800.00 $1,000.00 $2,050.00
240509(B)0320 CLASS A CONCRETE7CY $1,000.00 $1,585.00 $2,100.00 $4,506.98 $6,950.78 $5,469.71 $4,500.00 $1,000.00 $2,329.32
250511(B)2310 EPOXY COATED REINFORCING STEEL40,320LB $1.75 $1.53 $1.56 $1.62 $1.88 $1.81 $2.00 $2.00 $2.03
260512(A)3200 PAINTING EXISTING STRUCTURES1LSUM $60,000.00 $79,520.00 $77,572.00 $88,823.20 $77,902.11 $75,600.00 $75,000.00 $100,000.00 $77,000.00
270512(B)3300 COLLECTION AND HANDLING OF WASTE1LSUM $5,000.00 $41,000.00 $11,852.50 $50,756.11 $44,515.49 $43,200.00 $5,000.00 $40,000.00 $44,000.00
280515(A)7200 WATER REPELLENT (VISUALLY INSPECTED)361.2SY $6.00 $6.20 $6.05 $6.98 $6.12 $5.94 $10.00 $6.00 $5.00
290517 9110 ELASTOMERIC COATING548SF $20.00 $26.00 $30.80 $27.92 $24.48 $23.76 $30.00 $30.00 $24.50
300518(B)0300 SEALED EXPANSION JOINTS66LF $325.00 $360.00 $377.50 $350.34 $485.17 $340.06 $300.00 $350.00 $371.34
310520(A)1200 PREPARATION OF CRACKS, ABOVE WATER126LF $40.00 $46.00 $38.50 $53.29 $46.74 $45.36 $35.00 $35.00 $46.50
320520(C)1400 EPOXY RESIN, ABOVE WATER2GAL $100.00 $120.00 $55.00 $158.62 $139.11 $135.00 $50.00 $150.00 $140.00
330521(A)2200 PNEUMATICALLY PLACED MORTAR44SY $850.00 $1,003.64 $1,100.00 $1,015.12 $1,016.77 $864.00 $1,000.00 $1,000.00 $825.00
340535 7100 CORROSION INHIBITOR(SURFACE APPLIED)82SY $50.00 $47.00 $66.00 $53.29 $46.74 $45.36 $65.00 $60.00 $47.00
350601(B)1230 TYPE I-A PLAIN RIPRAP46TON $60.00 $70.00 $75.00 $88.20 $260.22 $115.55 $100.00 $75.00 $110.00
360601(I)1700 FILTER FABRIC (RIPRAP)40SY $12.00 $31.25 $43.00 $34.17 $58.83 $139.37 $10.00 $55.00 $25.00
370619(B)6304 REMOVAL OF BRIDGE ITEMS1LSUM $100,000.00 $90,000.00 $95,000.00 $87,000.00 $76,675.11 $132,721.62 $182,000.00 $75,000.00 $110,000.00
380880(B)6300 CONSTRUCTION SIGNS 0 TO 6.25 SF17,520SD $0.8000 $0.6600 $0.6600 $0.7600 $0.6700 $0.6500 $0.6500 $0.2000 $0.6700
390880(B)6310 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF1,800SD $1.20 $0.5300 $0.5500 $0.6300 $0.5600 $0.5400 $0.5500 $0.0200 $0.5700
400880(B)6320 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF480SD $1.80 $2.15 $2.20 $2.54 $2.23 $2.16 $2.20 $0.0200 $2.25
410880(B)6330 CONSTRUCTION SIGNS 33.0 SF & OVER240SD $2.50 $4.30 $4.40 $5.08 $4.45 $4.32 $4.40 $0.0200 $4.50
420880(C)6410 CONSTRUCTION BARRICADES(TYPE III)960SD $3.00 $3.70 $3.85 $4.44 $3.90 $3.78 $4.00 $15.00 $4.00
430880(E)6607 WARNING LIGHTS(TYPE B)2,640SD $0.5000 $0.5400 $0.5500 $0.6300 $0.5600 $0.5400 $0.5500 $0.4000 $0.5600
440882(A)8210 PORT.CHANGEABLE MESSAGE SIGN268SD $0.5000 $11.00 $11.00 $12.69 $11.13 $10.80 $15.00 $12.00 $11.00
450413(B)4310 RUMBLE STRIP-METHOD HMA-CYC940LF $5.00 $4.90 $4.95 $5.71 $5.01 $4.86 $5.00 $2.20 $6.00
460805(A)3252 (PL)REMOVAL OF EXISTING SIGNS4EA $200.00 $108.00 $110.00 $126.89 $111.29 $108.00 $110.00 $350.00 $120.00
470850(A)1200 SHEET ALUMINUM SIGNS37.5SF $40.00 $54.00 $55.00 $63.45 $55.64 $54.00 $55.00 $150.00 $55.00
480851(C)2430 2 1/2" SQUARE TUBE POST72LF $30.00 $16.40 $16.50 $19.03 $16.69 $16.20 $20.00 $15.00 $17.00
490856(A)8206 (SP) TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE)2,656LF $0.7500 $2.38 $2.48 $2.86 $2.50 $2.43 $2.50 $3.50 $2.52
500642(B)3300 CONSTRUCTION STAKING LEVEL II1LSUM $10,000.00 $7,800.00 $7,500.00 $7,994.09 $8,736.17 $8,532.00 $15,000.00 $10,000.00 $7,000.00
510641 2100 MOBILIZATION1LSUM $100,000.00 $70,000.00 $73,500.00 $80,000.00 $31,864.89 $87,805.34 $89,000.00 $125,000.00 $134,827.20