| 10 | 201(A)1200 |
CLEARING AND GRUBBING | 1 | LSUM |
$30,000.00 |
$850,000.00 |
$205,447.98 |
$250,000.00 |
| 20 | 202(A)2200 |
UNCLASSIFIED EXCAVATION | 95,860 | CY |
$8.00 |
$6.50 |
$13.51 |
$11.61 |
| 30 | 202(D)2500 |
UNCLASSIFIED BORROW | 76,390 | CY |
$10.00 |
$3.15 |
$13.51 |
$11.61 |
| 40 | 203 5100 |
TEST ROLLING | 1 | LSUM |
$25,000.00 |
$10,000.00 |
$38,748.68 |
$24,936.50 |
| 50 | 205(A)6200 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$50,000.00 |
$79,000.00 |
$30,034.10 |
$45,897.48 |
| 60 | 221(B)2300 |
TEMPORARY SILT FENCE | 11,092 | LF |
$2.75 |
$1.80 |
$3.57 |
$5.28 |
| 70 | 221(C)2400 |
TEMPORARY SEDIMENT FILTER | 39 | EA |
$320.00 |
$212.00 |
$408.43 |
$194.92 |
| 80 | 221(E)2600 |
TEMPORARY SILT DIKE | 1,533 | LF |
$15.00 |
$8.50 |
$13.27 |
$14.24 |
| 90 | 221(F)2700 |
TEMPORARY ROCK FILTER DAM TYPE 1 | 14 | CY |
$220.00 |
$205.00 |
$149.26 |
$149.56 |
| 100 | 221(G)2800 |
TEMPORARY FIBER LOG | 1,504 | LF |
$7.50 |
$2.45 |
$5.11 |
$11.01 |
| 110 | 230(A)7200 |
SOLID SLAB SODDING | 95,591 | SY |
$3.00 |
$2.75 |
$3.57 |
$4.31 |
| 120 | 232(B)9300 |
SEEDING METHOD B | 20 | AC |
$750.00 |
$1,475.00 |
$1,225.28 |
$1,478.59 |
| 130 | 233(A)0200 |
VEGETATIVE MULCHING | 20 | AC |
$700.00 |
$1,210.00 |
$1,225.28 |
$1,478.59 |
| 140 | 241 3100 |
MOWING | 40 | AC |
$220.00 |
$550.00 |
$204.21 |
$246.43 |
| 150 | 303(A)1200 |
AGGREGATE BASE TYPE A | 11,738 | CY |
$65.00 |
$88.00 |
$73.96 |
$91.64 |
| 160 | 307(K)4200 |
STABILIZED SUBGRADE | 144,539 | SY |
$5.00 |
$5.50 |
$6.44 |
$5.47 |
| 170 | 317 7100 |
CEMENT TREATED BASE | 58,591 | SY |
$20.00 |
$23.00 |
$10.57 |
$19.74 |
| 180 | 325 0100 |
SEPARATOR FABRIC | 113,501 | SY |
$2.00 |
$3.10 |
$3.49 |
$2.93 |
| 190 | 402(E)2600 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 1,864 | TON |
$40.00 |
$82.00 |
$47.17 |
$45.57 |
| 200 | 405 5100 |
PERMEABLE FRICTION COURSE | 1,194 | TON |
$150.00 |
$170.00 |
$197.02 |
$203.31 |
| 210 | 407(B)7300 |
TACK COAT | 34,414 | GAL |
$3.50 |
$4.00 |
$4.82 |
$4.74 |
| 220 | 411(B)1320 |
SUPERPAVE, TYPE S3(PG 70-28 OK) | 4,512 | TON |
$105.00 |
$121.00 |
$138.37 |
$145.39 |
| 230 | 411(B)1330 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 20,477 | TON |
$105.00 |
$121.00 |
$121.41 |
$145.39 |
| 240 | 411(C)1400 |
SUPERPAVE, TYPE S4(PG 76-28 OK) | 1,003 | TON |
$140.00 |
$190.00 |
$166.29 |
$227.95 |
| 250 | 411(C)1430 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 4,505 | TON |
$130.00 |
$127.00 |
$133.76 |
$151.55 |
| 260 | 411(F)1700 |
STONE MATRIX ASPHALT | 3,366 | TON |
$140.00 |
$142.00 |
$188.40 |
$169.43 |
| 270 | 411(G)1800 |
RICH BOTTOM LAYER | 5,215 | TON |
$120.00 |
$135.00 |
$155.34 |
$161.41 |
| 280 | 414(A)5200 |
P.C.CONCRETE PAVEMENT(PLACEMENT) | 17,960 | SY |
$20.00 |
$13.00 |
$13.44 |
$19.25 |
| 290 | 414(B)5300 |
DOWEL JOINTED P.C.C.PAVT.(PLACEMENT) | 36,482 | SY |
$25.00 |
$19.00 |
$21.64 |
$30.33 |
| 300 | 414(G)5800 |
P.C. CONCRETE FOR PAVEMENT | 15,504 | CY |
$150.00 |
$171.00 |
$167.63 |
$192.68 |
| 310 | 504(E)5520 |
42" F-SHAPED PARAPET | 18,856 | LF |
$81.00 |
$195.00 |
$125.32 |
$225.66 |
| 315 | 509(A)0200 |
CLASS AA CONCRETE | 47 | CY |
$700.00 |
$205.00 |
$206.80 |
$338.84 |
| 320 | 509(B)0310 |
CLASS A CONCRETE(LONG. BAR. DES. 1-A) | 368 | CY |
$440.00 |
$540.00 |
$541.49 |
$501.18 |
| 330 | 509(D)0500 |
CLASS C CONCRETE | 217 | CY |
$450.00 |
$310.00 |
$916.29 |
$454.99 |
| 340 | 510(A)1240 |
TEMPORARY RETAINING WALL | 957 | SY |
$300.00 |
$1,000.00 |
$75.23 |
$45.01 |
| 350 | 510(C)1460 |
SLOPE WALL (6") | 4,723 | SY |
$200.00 |
$110.00 |
$118.62 |
$165.27 |
| 360 | 511(A)2200 |
REINFORCING STEEL | 50,456 | LB |
$1.50 |
$1.60 |
$2.33 |
$1.62 |
| 370 | 601(A)1100 |
TYPE I PLAIN RIPRAP | 30 | TON |
$85.00 |
$80.00 |
$105.12 |
$97.13 |
| 380 | 609(A)4220 |
CONC.CURB(4" MNTBLE-INTEGRAL) | 527 | LF |
$10.00 |
$3.50 |
$2.19 |
$1.27 |
| 390 | 609(A)4230 |
CONC.CURB(6" BARRIER-INTEGRAL) | 4,160 | LF |
$10.00 |
$5.00 |
$5.07 |
$1.67 |
| 400 | 609(B)4320 |
1'-8" COMB.CRB.& GUT.(4" MNTBLE) | 491 | LF |
$30.00 |
$54.00 |
$27.71 |
$54.66 |
| 410 | 609(B)4330 |
1'-8" COMB.CRB.& GUT.(6" BARRIER) | 101 | LF |
$30.00 |
$53.00 |
$24.05 |
$54.29 |
| 420 | 609(B)4360 |
2'-8" COMB.CRB.& GUT.(6" BARRIER) | 1,515 | LF |
$33.00 |
$52.00 |
$31.68 |
$22.61 |
| 430 | 610(C)5400 |
4" CONCRETE DIVIDING STRIP | 215 | SY |
$50.00 |
$60.00 |
$83.34 |
$55.49 |
| 440 | 611(A)7210 |
MANHOLE (4' DIA.) | 7 | EA |
$3,300.00 |
$5,000.00 |
$2,771.98 |
$3,145.27 |
| 450 | 611(A)7215 |
MANHOLE (5' DIA.) | 4 | EA |
$4,000.00 |
$5,000.00 |
$3,797.90 |
$4,592.89 |
| 460 | 611(A)7220 |
MANHOLE (6' DIA.) | 2 | EA |
$4,500.00 |
$10,000.00 |
$5,063.97 |
$9,121.27 |
| 470 | 611(B)7300 |
ADD'L.DEPTH IN MANHOLE (4' DIA.) | 24 | VF |
$275.00 |
$140.00 |
$360.52 |
$150.00 |
| 480 | 611(B)7305 |
ADD'L.DEPTH IN MANHOLE (5' DIA.) | 12 | VF |
$380.00 |
$260.00 |
$438.14 |
$200.00 |
| 490 | 611(B)7310 |
ADD'L.DEPTH IN MANHOLE (6' DIA.) | 15 | VF |
$375.00 |
$460.00 |
$598.57 |
$250.00 |
| 500 | 611(G)0362 |
INLET (SMD-TYPE 2B) | 1 | EA |
$4,000.00 |
$6,200.00 |
$2,219.90 |
$4,917.25 |
| 510 | 611(G)7700 |
SPECIAL INLET DRAIN | 24 | EA |
$4,065.00 |
$7,500.00 |
$6,885.44 |
$6,723.61 |
| 520 | 611(G)7754 |
INLET CI DES. 2 (STD) | 2 | EA |
$4,200.00 |
$9,500.00 |
$4,325.81 |
$6,287.54 |
| 530 | 611(G)7766 |
INLET CI DES. 2 (D) | 2 | EA |
$6,200.00 |
$6,500.00 |
$6,341.74 |
$10,254.07 |
| 540 | 611(G)7930 |
INLET GPI TYPE 1 (DES. 1) | 1 | EA |
$5,500.00 |
$6,000.00 |
$3,346.62 |
$4,329.81 |
| 550 | 611(G)7934 |
INLET GPI TYPE 1 (DES. 2) | 1 | EA |
$5,600.00 |
$6,000.00 |
$3,425.72 |
$4,262.19 |
| 560 | 611(G)7938 |
INLET GPI TYPE 1 (DES. 3) | 1 | EA |
$6,000.00 |
$4,500.00 |
$3,551.00 |
$5,973.06 |
| 570 | 611(G)7958 |
INLET GPI TYPE 2 (DES. 8) | 3 | EA |
$3,900.00 |
$6,500.00 |
$4,330.31 |
$5,636.71 |
| 580 | 611(G)7962 |
INLET GPI TYPE 2 (DES. 9) | 1 | EA |
$7,000.00 |
$6,600.00 |
$4,435.50 |
$6,366.06 |
| 590 | 611(G)7966 |
INLET GPI TYPE 2 (DES. 10) | 1 | EA |
$3,750.00 |
$7,000.00 |
$4,600.33 |
$6,181.03 |
| 600 | 611(H)0414 |
ADD'L DEPTH IN INLET CI DES. 2 | 8 | VF |
$420.00 |
$485.00 |
$367.36 |
$350.00 |
| 610 | 611(H)0470 |
ADD'L DEPTH IN INLET GPI TYPE 1 | 5 | VF |
$300.00 |
$450.00 |
$548.13 |
$400.00 |
| 620 | 611(H)0474 |
ADD'L DEPTH IN INLET GPI TYPE 2 | 6 | VF |
$400.00 |
$560.00 |
$587.32 |
$475.00 |
| 630 | 613(A)5208 |
18" R.C.PIPE CLASS III | 3,971 | LF |
$90.00 |
$73.00 |
$85.86 |
$140.40 |
| 640 | 613(A)5268 |
24" R.C.PIPE CLASS IV | 762 | LF |
$125.00 |
$128.00 |
$125.52 |
$111.52 |
| 650 | 613(A)5272 |
30" R.C.PIPE CLASS IV | 711 | LF |
$128.00 |
$165.00 |
$175.49 |
$198.47 |
| 660 | 613(A)5276 |
36" R.C.PIPE CLASS IV | 10 | LF |
$160.00 |
$355.00 |
$209.25 |
$229.45 |
| 670 | 613(J)6400 |
EDGE DRAIN CONDUIT-PERFORATED | 1,250 | LF |
$15.00 |
$12.50 |
$15.58 |
$12.01 |
| 680 | 613(K)6500 |
EDGE DRAIN OUTLET LATERAL-NONPERFORATED | 30 | LF |
$25.00 |
$16.00 |
$9.24 |
$8.79 |
| 690 | 613(L)6708 |
18" PREFAB. CULVERT END SEC., ROUND | 5 | EA |
$750.00 |
$1,750.00 |
$2,418.05 |
$1,070.53 |
| 700 | 613(L)6724 |
30" PREFAB. CULVERT END SEC., ROUND | 2 | EA |
$1,400.00 |
$1,100.00 |
$2,944.98 |
$1,913.77 |
| 710 | 613(Q)7500 |
OUTLET LATERAL HEADWALL | 1 | EA |
$600.00 |
$850.00 |
$1,044.45 |
$421.99 |
| 720 | 613(U)7910 |
BORE & JACK 24" STEEL CASING | 874 | LF |
$600.00 |
$840.00 |
$887.10 |
$1,054.15 |
| 730 | 619(A)6200 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$30,000.00 |
$35,000.00 |
$157,479.54 |
$94,077.87 |
| 740 | 619(B)6352 |
REMOVAL OF FENCE | 886 | LF |
$3.50 |
$2.25 |
$4.36 |
$2.52 |
| 750 | 619(B)6356 |
REMOVAL OF CURB AND GUTTER | 3,193 | LF |
$7.00 |
$4.30 |
$7.03 |
$7.91 |
| 760 | 619(B)6360 |
REMOVAL OF CONCRETE PAVEMENT | 38,486 | SY |
$10.00 |
$4.00 |
$12.71 |
$6.30 |
| 770 | 619(B)6364 |
REMOVAL OF ASPHALT PAVEMENT | 59,006 | SY |
$3.50 |
$7.50 |
$3.57 |
$4.31 |
| 780 | 619(B)6396 |
REMOVAL OF GUARDRAIL | 2,332 | LF |
$3.50 |
$4.00 |
$4.60 |
$4.73 |
| 790 | 619(B)6408 |
REMOVAL OF CONCRETE SLOPE PROTECTION | 879 | SY |
$15.00 |
$6.50 |
$10.28 |
$8.20 |
| 800 | 619(B)6416 |
REMOVAL OF CONCRETE MEDIAN BARRIER | 1,033 | LF |
$54.00 |
$16.50 |
$10.83 |
$12.03 |
| 810 | 619(B)6432 |
REMOVAL OF CABLE BARRIER | 3,228 | LF |
$21.00 |
$12.25 |
$11.37 |
$14.94 |
| 820 | 619(B)6436 |
REMOVAL OF CONCRETE DITCH LINER | 1,807 | LF |
$12.00 |
$5.50 |
$7.72 |
$8.35 |
| 830 | 619(B)6464 |
REMOVAL OF 6" CONCRETE DIVIDING STRIP | 347 | SY |
$11.00 |
$8.50 |
$10.82 |
$11.97 |
| 840 | 619(B)6476 |
REMOVAL OF EXISTING PARAPET | 3,897 | LF |
$140.00 |
$10.50 |
$12.54 |
$25.96 |
| 850 | 619(C)6600 |
SAWING PAVEMENT | 7,841 | LF |
$3.00 |
$2.25 |
$5.88 |
$2.42 |
| 852 | 623(A)1200 |
BEAM GUARDRAIL W-BEAM SINGLE | 25 | LF |
$35.00 |
$29.00 |
$28.95 |
$34.50 |
| 855 | 623(I)2050 |
GUARDRAIL BRIDGE CONN-THRIE BEAM (31") | 1 | EA |
$3,000.00 |
$4,900.00 |
$5,024.17 |
$5,987.08 |
| 860 | 624(C)3405 |
FENCE-STYLE SWF (5 BARBED WIRE) | 424 | LF |
$10.00 |
$21.00 |
$12.04 |
$12.20 |
| 870 | 627(A)6200 |
CONCRETE LONGITUDINAL BARRIER, DESIGN 1 | 1,338 | LF |
$93.00 |
$80.00 |
$71.41 |
$61.66 |
| 880 | 501(B)1300 |
SUBSTRUCTURE EXCAVATION COMMON | 1,674 | CY |
$16.00 |
$20.00 |
$35.36 |
$22.60 |
| 885 | 501(C)1400 |
SUBSTRUCTURE EXCAVATION ROCK | 236 | CY |
$50.00 |
$45.00 |
$35.36 |
$18.00 |
| 890 | 501(F)1700 |
GRANULAR BACKFILL | 710 | CY |
$70.00 |
$75.00 |
$56.43 |
$74.25 |
| 900 | 501(G)1800 |
CLSM BACKFILL | 1,590 | CY |
$150.00 |
$200.00 |
$147.93 |
$242.12 |
| 910 | 502(B)3320 |
(PL)FALSEWORK JACKING | 1 | LSUM |
$20,000.00 |
$8,000.00 |
$23,682.54 |
$19,081.78 |
| 920 | 503(A)4240 |
PRESTRESSED CONCRETE BEAMS (TYPE IV) | 520.11 | LF |
$300.00 |
$425.00 |
$392.63 |
$363.73 |
| 930 | 504(A)5200 |
APPROACH SLAB | 281 | SY |
$250.00 |
$300.00 |
$280.06 |
$269.12 |
| 940 | 504(B)5300 |
SAW-CUT GROOVING | 709.3 | SY |
$6.50 |
$5.00 |
$4.90 |
$5.91 |
| 950 | 504(E)5520 |
42" F-SHAPED PARAPET | 336 | LF |
$110.00 |
$125.00 |
$156.92 |
$165.98 |
| 960 | 506(A)7200 |
STRUCTURAL STEEL | 23,070 | LB |
$3.50 |
$3.30 |
$6.37 |
$11.66 |
| 970 | 507(A)8200 |
STAINLESS STEEL FIXED BEARING ASSEMBLY | 5 | EA |
$3,225.00 |
$4,000.00 |
$2,996.08 |
$4,013.99 |
| 980 | 507(B)8300 |
STAINLESS STEEL EXP. BEARING ASSEMBLY | 5 | EA |
$3,000.00 |
$4,000.00 |
$4,136.62 |
$4,013.99 |
| 990 | 509 0120 |
ELASTOMERIC COATING | 391 | SF |
$16.00 |
$18.00 |
$17.87 |
$21.56 |
| 1,000 | 509(A)0210 |
CLASS AA CONCRETE | 121.4 | CY |
$800.00 |
$1,250.00 |
$945.25 |
$983.43 |
| 1,010 | 509(B)0320 |
CLASS A CONCRETE | 1,029.8 | CY |
$800.00 |
$650.00 |
$808.73 |
$829.42 |
| 1,015 | 510(D)1500 |
GRAFFITI TREATMENT | 5,500 | SF |
$3.00 |
$2.80 |
$2.71 |
$3.82 |
| 1,020 | 511(B)2310 |
EPOXY COATED REINFORCING STEEL | 207,080 | LB |
$1.50 |
$1.80 |
$1.78 |
$1.80 |
| 1,030 | 515(A)7200 |
WATER REPELLENT (VISUALLY INSPECTED) | 611 | SY |
$5.00 |
$4.65 |
$4.59 |
$5.54 |
| 1,040 | 516(A)8250 |
DRILLED SHAFTS 72" DIAMETER | 120 | LF |
$2,000.00 |
$2,200.00 |
$1,595.45 |
$1,557.13 |
| 1,050 | 516(C)8400 |
CROSSHOLE SONIC LOGGING | 2 | EA |
$3,000.00 |
$1,600.00 |
$1,786.87 |
$1,848.24 |
| 1,060 | 518(B)0300 |
SEALED EXPANSION JOINTS | 40.82 | LF |
$330.00 |
$375.00 |
$428.44 |
$367.12 |
| 1,070 | 613(H)6205 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 78 | LF |
$32.00 |
$27.00 |
$24.36 |
$10.33 |
| 1,080 | 613(I)6310 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 140 | LF |
$26.00 |
$25.00 |
$16.01 |
$20.47 |
| 1,090 | 613(U)7950 |
PIPE UNDERDRAIN COVER MAT'L. | 400 | CY |
$60.00 |
$100.00 |
$71.29 |
$116.50 |
| 1,100 | 501(B)1300 |
SUBSTRUCTURE EXCAVATION COMMON | 2,691 | CY |
$16.00 |
$20.00 |
$35.36 |
$22.60 |
| 1,105 | 501(C)1400 |
SUBSTRUCTURE EXCAVATION ROCK | 344 | CY |
$50.00 |
$45.00 |
$35.36 |
$18.00 |
| 1,110 | 501(F)1700 |
GRANULAR BACKFILL | 1,080 | CY |
$70.00 |
$65.00 |
$56.43 |
$74.25 |
| 1,120 | 501(G)1800 |
CLSM BACKFILL | 2,880 | CY |
$150.00 |
$170.00 |
$147.93 |
$242.12 |
| 1,130 | 502(B)3320 |
(PL)FALSEWORK JACKING | 1 | LSUM |
$20,000.00 |
$14,700.00 |
$23,682.54 |
$19,081.78 |
| 1,140 | 503(A)4240 |
PRESTRESSED CONCRETE BEAMS (TYPE IV) | 703.21 | LF |
$300.00 |
$310.00 |
$340.28 |
$363.73 |
| 1,150 | 504(A)5200 |
APPROACH SLAB | 504.6 | SY |
$250.00 |
$245.00 |
$277.88 |
$269.12 |
| 1,160 | 504(B)5300 |
SAW-CUT GROOVING | 1,162.3 | SY |
$6.50 |
$5.00 |
$4.90 |
$5.91 |
| 1,170 | 504(E)5520 |
42" F-SHAPED PARAPET | 348.7 | LF |
$110.00 |
$95.00 |
$117.63 |
$165.98 |
| 1,180 | 506(A)7200 |
STRUCTURAL STEEL | 790 | LB |
$3.50 |
$3.50 |
$6.43 |
$4.39 |
| 1,190 | 507(A)8200 |
STAINLESS STEEL FIXED BEARING ASSEMBLY | 7 | EA |
$3,225.00 |
$3,500.00 |
$2,995.99 |
$4,013.99 |
| 1,200 | 507(B)8300 |
STAINLESS STEEL EXP. BEARING ASSEMBLY | 7 | EA |
$3,000.00 |
$3,500.00 |
$4,136.54 |
$4,013.99 |
| 1,210 | 509 0120 |
ELASTOMERIC COATING | 764 | SF |
$16.00 |
$18.00 |
$17.87 |
$21.56 |
| 1,220 | 509(A)0210 |
CLASS AA CONCRETE | 180.4 | CY |
$800.00 |
$750.00 |
$938.83 |
$983.43 |
| 1,230 | 509(B)0320 |
CLASS A CONCRETE | 1,171.9 | CY |
$800.00 |
$400.00 |
$835.51 |
$829.42 |
| 1,235 | 510(D)1500 |
GRAFFITI TREATMENT | 4,500 | SF |
$3.00 |
$2.80 |
$2.71 |
$3.82 |
| 1,240 | 511(B)2310 |
EPOXY COATED REINFORCING STEEL | 223,830 | LB |
$1.50 |
$1.60 |
$1.78 |
$1.80 |
| 1,250 | 515(A)7200 |
WATER REPELLENT (VISUALLY INSPECTED) | 499 | SY |
$5.00 |
$4.65 |
$4.59 |
$5.54 |
| 1,260 | 516(A)8250 |
DRILLED SHAFTS 72" DIAMETER | 168 | LF |
$2,000.00 |
$1,300.00 |
$1,595.31 |
$1,477.04 |
| 1,270 | 516(C)8400 |
CROSSHOLE SONIC LOGGING | 3 | EA |
$3,000.00 |
$1,600.00 |
$1,786.87 |
$1,848.24 |
| 1,280 | 518(B)0300 |
SEALED EXPANSION JOINTS | 61.4 | LF |
$330.00 |
$330.00 |
$428.32 |
$367.12 |
| 1,290 | 613(H)6205 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 134 | LF |
$32.00 |
$27.00 |
$24.36 |
$10.33 |
| 1,300 | 613(I)6310 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 6 | LF |
$26.00 |
$35.00 |
$15.89 |
$20.47 |
| 1,310 | 613(U)7950 |
PIPE UNDERDRAIN COVER MAT'L. | 700 | CY |
$60.00 |
$100.00 |
$71.29 |
$116.50 |
| 1,320 | 619(D)6700 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$50,000.00 |
$35,000.00 |
$119,261.24 |
$51,681.22 |
| 1,330 | 501(B)1300 |
SUBSTRUCTURE EXCAVATION COMMON | 2,916 | CY |
$16.00 |
$20.00 |
$35.36 |
$22.60 |
| 1,335 | 501(C)1400 |
SUBSTRUCTURE EXCAVATION ROCK | 344 | CY |
$50.00 |
$45.00 |
$35.36 |
$18.00 |
| 1,340 | 501(F)1700 |
GRANULAR BACKFILL | 980 | CY |
$70.00 |
$75.00 |
$56.43 |
$74.25 |
| 1,350 | 501(G)1800 |
CLSM BACKFILL | 2,635 | CY |
$150.00 |
$200.00 |
$147.93 |
$242.12 |
| 1,360 | 502(B)3320 |
(PL)FALSEWORK JACKING | 1 | LSUM |
$20,000.00 |
$19,400.00 |
$23,682.54 |
$19,081.78 |
| 1,370 | 503(A)4240 |
PRESTRESSED CONCRETE BEAMS (TYPE IV) | 703.65 | LF |
$300.00 |
$375.00 |
$340.86 |
$363.73 |
| 1,380 | 504(A)5200 |
APPROACH SLAB | 467.3 | SY |
$250.00 |
$315.00 |
$277.84 |
$269.12 |
| 1,390 | 504(B)5300 |
SAW-CUT GROOVING | 1,127.2 | SY |
$6.50 |
$5.00 |
$4.90 |
$5.91 |
| 1,400 | 504(E)5520 |
42" F-SHAPED PARAPET | 338.2 | LF |
$110.00 |
$125.00 |
$148.05 |
$165.98 |
| 1,410 | 506(A)7200 |
STRUCTURAL STEEL | 22,650 | LB |
$3.50 |
$3.30 |
$6.42 |
$11.80 |
| 1,420 | 507(A)8200 |
STAINLESS STEEL FIXED BEARING ASSEMBLY | 7 | EA |
$3,225.00 |
$4,000.00 |
$2,995.99 |
$4,013.99 |
| 1,430 | 507(B)8300 |
STAINLESS STEEL EXP. BEARING ASSEMBLY | 7 | EA |
$3,000.00 |
$4,000.00 |
$4,136.54 |
$4,013.99 |
| 1,440 | 509 0120 |
ELASTOMERIC COATING | 764 | SF |
$16.00 |
$18.00 |
$17.87 |
$21.56 |
| 1,450 | 509(A)0210 |
CLASS AA CONCRETE | 180.5 | CY |
$800.00 |
$1,250.00 |
$941.83 |
$983.43 |
| 1,460 | 509(B)0320 |
CLASS A CONCRETE | 1,461.4 | CY |
$800.00 |
$550.00 |
$800.81 |
$829.42 |
| 1,465 | 510(D)1500 |
GRAFFITI TREATMENT | 5,460 | SF |
$3.00 |
$2.80 |
$2.71 |
$3.82 |
| 1,470 | 511(B)2310 |
EPOXY COATED REINFORCING STEEL | 300,970 | LB |
$1.50 |
$1.80 |
$1.78 |
$1.80 |
| 1,480 | 513(B)4300 |
CLASS B BRIDGE DECK REPAIR | 30 | SY |
$380.00 |
$300.00 |
$459.48 |
$316.09 |
| 1,490 | 513(C)4400 |
CLASS C BRIDGE DECK REPAIR | 30 | SY |
$620.00 |
$350.00 |
$663.69 |
$286.42 |
| 1,500 | 515(A)7200 |
WATER REPELLENT (VISUALLY INSPECTED) | 606 | SY |
$5.00 |
$4.65 |
$4.59 |
$5.54 |
| 1,510 | 516(A)8250 |
DRILLED SHAFTS 72" DIAMETER | 168 | LF |
$2,000.00 |
$1,750.00 |
$1,595.31 |
$1,483.97 |
| 1,520 | 516(C)8400 |
CROSSHOLE SONIC LOGGING | 3 | EA |
$3,000.00 |
$1,600.00 |
$1,786.87 |
$1,848.24 |
| 1,530 | 518(B)0300 |
SEALED EXPANSION JOINTS | 61.5 | LF |
$330.00 |
$375.00 |
$428.28 |
$367.12 |
| 1,540 | 613(H)6205 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 120 | LF |
$32.00 |
$34.00 |
$24.37 |
$10.33 |
| 1,550 | 613(I)6310 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 350 | LF |
$26.00 |
$25.00 |
$16.02 |
$20.47 |
| 1,560 | 613(U)7950 |
PIPE UNDERDRAIN COVER MAT'L. | 630 | CY |
$60.00 |
$100.00 |
$71.29 |
$116.50 |
| 1,570 | 619(D)6700 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$50,000.00 |
$40,000.00 |
$142,740.17 |
$63,874.48 |
| 1,580 | 501(B)1300 |
SUBSTRUCTURE EXCAVATION COMMON | 350 | CY |
$16.00 |
$120.00 |
$35.36 |
$22.60 |
| 1,590 | 501(G)1800 |
CLSM BACKFILL | 289.8 | CY |
$150.00 |
$250.00 |
$147.93 |
$242.12 |
| 1,600 | 503(A)4240 |
PRESTRESSED CONCRETE BEAMS (TYPE IV) | 2,691.67 | LF |
$300.00 |
$390.00 |
$341.49 |
$350.47 |
| 1,610 | 504(A)5200 |
APPROACH SLAB | 274 | SY |
$250.00 |
$315.00 |
$280.71 |
$272.63 |
| 1,620 | 504(B)5300 |
SAW-CUT GROOVING | 8,511 | SY |
$6.50 |
$5.00 |
$4.75 |
$5.73 |
| 1,630 | 504(E)5520 |
42" F-SHAPED PARAPET | 3,760 | LF |
$110.00 |
$82.00 |
$120.95 |
$149.27 |
| 1,640 | 506(A)7200 |
STRUCTURAL STEEL | 2,552,229 | LB |
$3.50 |
$3.14 |
$2.66 |
$2.72 |
| 1,650 | 507(A)8200 |
STAINLESS STEEL FIXED BEARING ASSEMBLY | 45 | EA |
$3,225.00 |
$4,250.00 |
$2,993.37 |
$4,328.55 |
| 1,660 | 507(B)8300 |
STAINLESS STEEL EXP. BEARING ASSEMBLY | 75 | EA |
$3,000.00 |
$4,100.00 |
$4,136.41 |
$4,328.55 |
| 1,670 | 509 0120 |
ELASTOMERIC COATING | 4,685 | SF |
$16.00 |
$18.00 |
$17.87 |
$21.56 |
| 1,680 | 509(A)0210 |
CLASS AA CONCRETE | 1,996.4 | CY |
$800.00 |
$750.00 |
$1,091.29 |
$1,054.36 |
| 1,690 | 509(B)0320 |
CLASS A CONCRETE | 2,405.2 | CY |
$800.00 |
$685.00 |
$775.90 |
$984.91 |
| 1,700 | 510(C)1450 |
SLOPE WALL (5") | 594.6 | SY |
$150.00 |
$145.00 |
$139.13 |
$165.27 |
| 1,710 | 510(D)1500 |
GRAFFITI TREATMENT | 14,540 | SF |
$3.00 |
$2.80 |
$2.71 |
$3.82 |
| 1,720 | 511(B)2310 |
EPOXY COATED REINFORCING STEEL | 1,086,450 | LB |
$1.50 |
$1.80 |
$1.78 |
$1.80 |
| 1,730 | 514(A)5210 |
PILES, FURNISHED (HP 10X42) | 83.51 | LF |
$45.00 |
$70.00 |
$75.25 |
$71.08 |
| 1,740 | 514(A)5220 |
PILES, FURNISHED (HP 12X53) | 358.4 | LF |
$48.00 |
$74.00 |
$68.05 |
$84.16 |
| 1,750 | 514(B)5310 |
PILES, DRIVEN (HP 10X42) | 83.51 | LF |
$16.00 |
$25.00 |
$61.07 |
$67.73 |
| 1,760 | 514(B)5320 |
PILES, DRIVEN (HP 12X53) | 358.4 | LF |
$16.00 |
$20.00 |
$32.39 |
$64.27 |
| 1,770 | 514(L)6300 |
PILE SPLICE, H-PILE (NON-BIDDABLE) | 1 | EA |
$500.00 |
$500.00 |
$500.00 |
$500.00 |
| 1,780 | 515(A)7200 |
WATER REPELLENT (VISUALLY INSPECTED) | 15,273 | SY |
$5.00 |
$4.65 |
$4.29 |
$5.17 |
| 1,790 | 516(A)8250 |
DRILLED SHAFTS 72" DIAMETER | 357 | LF |
$2,000.00 |
$1,850.00 |
$1,617.67 |
$1,761.43 |
| 1,800 | 516(A)8260 |
DRILLED SHAFTS 96" DIAMETER | 99 | LF |
$2,500.00 |
$2,000.00 |
$1,885.87 |
$2,523.25 |
| 1,810 | 516(C)8400 |
CROSSHOLE SONIC LOGGING | 24 | EA |
$3,000.00 |
$1,600.00 |
$1,786.87 |
$1,848.24 |
| 1,820 | 518(B)0300 |
SEALED EXPANSION JOINTS | 574 | LF |
$330.00 |
$375.00 |
$428.44 |
$367.12 |
| 1,830 | 523(A)3200 |
SEALER CRACK PREPARATION | 574 | LF |
$5.00 |
$5.20 |
$5.11 |
$6.16 |
| 1,840 | 523(B)3300 |
SEALER RESIN | 6.32 | GAL |
$110.00 |
$225.00 |
$224.63 |
$271.07 |
| 1,850 | 613(H)6205 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 166 | LF |
$32.00 |
$36.00 |
$29.49 |
$27.51 |
| 1,860 | 613(I)6310 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 92 | LF |
$26.00 |
$26.00 |
$21.28 |
$20.47 |
| 1,865 | 619(D)6700 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$80,000.00 |
$85,500.00 |
$211,355.32 |
$115,288.39 |
| 1,870 | 510(D)1510 |
MSE RETAINING WALL | 4,589.6 | SY |
$625.00 |
$700.00 |
$809.86 |
$777.65 |
| 1,880 | 857(A)9200 |
CONSTRUCTION TRAFFIC STR.(PAINT)(4" WIDE) | 145,000 | LF |
$0.1000 |
$0.2100 |
$0.2100 |
$0.2500 |
| 1,890 | 857(B)9300 |
CONSTRUCTION TRAFFIC STR.(PAINT)(ARROWS) | 27 | EA |
$110.00 |
$128.92 |
$131.05 |
$154.02 |
| 1,900 | 857(B)9310 |
CONSTRUCTION TRAFFIC STR.(PAINT)(WORDS) | 6 | EA |
$190.00 |
$180.49 |
$183.47 |
$215.63 |
| 1,910 | 857(B)9320 |
CONSTRUCTION TRAFFIC STR.(PAINT)(SYMBOL) | 6 | EA |
$100.00 |
$360.97 |
$366.94 |
$431.26 |
| 1,920 | 857(F)9700 |
PAVEMENT MRKNG.REMOVAL(TRAF.STRP) | 200,000 | LF |
$0.5000 |
$0.1600 |
$0.1600 |
$0.1800 |
| 1,930 | 857(F)9710 |
PAVEMENT MARKING REMOVAL(ARROWS) | 9 | EA |
$48.00 |
$62.00 |
$62.90 |
$73.93 |
| 1,940 | 857(F)9720 |
PAVEMENT MARKING REMOVAL(WORDS) | 3 | EA |
$68.00 |
$62.00 |
$62.91 |
$73.93 |
| 1,950 | 857(F)9730 |
PAVEMENT MARKING REMOVAL(SYMBOLS) | 3 | EA |
$100.00 |
$510.00 |
$524.20 |
$616.08 |
| 1,960 | 871(B)2300 |
CONST.ZONE IMPACT ATTEN. | 2,340 | SD |
$5.00 |
$36.00 |
$36.69 |
$43.12 |
| 1,970 | 876(A)3210 |
(PL)TRUCK MOUNTED ATTENUATOR | 250 | SD |
$18.00 |
$43.00 |
$44.03 |
$51.75 |
| 1,980 | 877(B)4300 |
DELIVER PORTABLE LONGITUDINAL BARRIER | 12,825 | LF |
$25.00 |
$25.00 |
$11.36 |
$18.37 |
| 1,990 | 877(C)4400 |
RELOCATION OF PORT. LONGITUDINAL BARRIER | 63,725 | LF |
$5.00 |
$2.60 |
$10.89 |
$4.85 |
| 2,000 | 880(A)6220 |
ARROW DISPLAY(TYPE C) | 4,515 | SD |
$3.00 |
$1.05 |
$1.05 |
$1.23 |
| 2,010 | 880(B)6300 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 34,550 | SD |
$0.0800 |
$0.0600 |
$0.0500 |
$0.0600 |
| 2,020 | 880(B)6310 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 34,260 | SD |
$0.1600 |
$0.1600 |
$0.1600 |
$0.1800 |
| 2,030 | 880(B)6320 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 34,770 | SD |
$0.5000 |
$0.3600 |
$0.3700 |
$0.4300 |
| 2,040 | 880(B)6330 |
CONSTRUCTION SIGNS 33.0 SF & OVER | 4,470 | SD |
$3.00 |
$0.5500 |
$0.5200 |
$0.6200 |
| 2,050 | 880(C)6410 |
CONSTRUCTION BARRICADES(TYPE III) | 17,305 | SD |
$0.3200 |
$6.25 |
$6.29 |
$7.39 |
| 2,060 | 880(C)6420 |
WING BARRICADES | 4,470 | SD |
$0.0900 |
$0.0300 |
$0.0200 |
$0.0200 |
| 2,070 | 880(E)6600 |
WARNING LIGHTS(TYPE A) | 55,405 | SD |
$0.1000 |
$0.7000 |
$0.6800 |
$0.8000 |
| 2,080 | 880(F)6700 |
DRUMS | 277,885 | SD |
$0.0500 |
$0.0600 |
$0.0500 |
$0.0600 |
| 2,090 | 880(K)7200 |
SURVEILLANCE TRAFFIC CONTROL | 745 | SD |
$100.00 |
$550.00 |
$910.54 |
$671.53 |
| 2,100 | 880(L)7310 |
(SP) TRAFFIC SURVEILLANCE, OHP (NON-BID) | 3,200 | HOUR |
$69.00 |
$69.00 |
$69.00 |
$69.00 |
| 2,105 | 882 8100 |
(SP)SMART WORK ZONE SYSTEM | 745 | SD |
$150.00 |
$42.00 |
$41.94 |
$49.28 |
| 2,110 | 882 8105 |
(SP)SMART WK. ZONE SYS.-PORT.CHNG.MSG.SN | 13,410 | SD |
$15.00 |
$20.50 |
$20.97 |
$24.64 |
| 2,120 | 882 8110 |
(SP)SMART WK. ZONE SYS.-PORT.TRAF.SENSOR | 8,940 | SD |
$20.00 |
$14.50 |
$14.68 |
$17.25 |
| 2,130 | 882 8115 |
(SP)SMART WK ZONE SYS-PAN-TILT-ZOOM CMRA | 745 | SD |
$50.00 |
$14.50 |
$14.68 |
$17.25 |
| 2,140 | 882 8120 |
(SP)SMART WK. ZONE SYS.-WEBSITE SYSTEM | 745 | SD |
$50.00 |
$36.00 |
$36.69 |
$43.12 |
| 2,150 | 882(A)8210 |
PORT.CHANGEABLE MESSAGE SIGN | 6,705 | SD |
$15.00 |
$7.25 |
$7.34 |
$8.62 |
| 2,152 | 413(A)4200 |
RUMBLE STRIP-METHOD HMA-CON | 4,280 | LF |
$0.4500 |
$0.3000 |
$0.3000 |
$0.3600 |
| 2,153 | 413(A)4210 |
RUMBLE STRIP-CENTERLINE HMA-CON | 5,430 | LF |
$0.4800 |
$0.4500 |
$0.4300 |
$0.5200 |
| 2,156 | 413(C)4400 |
RUMBLE STRIP-METHOD PCC-CON | 14,400 | LF |
$0.7500 |
$0.4000 |
$0.3600 |
$0.4300 |
| 2,157 | 413(C)4410 |
RUMBLE STRIP-CENTERLINE PCC-CON | 10,985 | LF |
$0.8500 |
$0.5000 |
$0.4900 |
$0.5800 |
| 2,160 | 516(A)8240 |
DRILLED SHAFTS 60" DIAMETER | 648 | LF |
$1,000.00 |
$830.00 |
$864.93 |
$1,016.53 |
| 2,163 | 628(B)7300 |
HIGH-TENSION CABLE BARRIER(TL-4) | 3,050 | LF |
$37.00 |
$15.00 |
$13.13 |
$15.65 |
| 2,165 | 628(C)7400 |
END ANCHORS | 4 | EA |
$10,000.00 |
$10,750.00 |
$10,627.36 |
$12,664.16 |
| 2,170 | 804(A)2200 |
STRUCTURAL CONCRETE | 22.1 | CY |
$990.00 |
$450.00 |
$445.57 |
$523.67 |
| 2,180 | 804(B)2300 |
REINFORCING STEEL | 3,950 | LB |
$2.50 |
$2.10 |
$2.10 |
$2.46 |
| 2,190 | 805(A)3240 |
(PL)REMOVAL OF OVHD.SIGN STR. & SIGNS | 1 | LSUM |
$800.00 |
$50,000.00 |
$50,401.88 |
$59,236.21 |
| 2,200 | 805(A)3244 |
(PL)REMOVAL OF GROUND MOUNTED SIGNS | 1 | LSUM |
$400.00 |
$15,000.00 |
$14,939.72 |
$17,558.31 |
| 2,210 | 805(D)3536 |
(PL)REMOVE & RESET GROUND MOUNTED SIGN | 10 | EA |
$630.00 |
$1,000.00 |
$995.98 |
$1,170.55 |
| 2,220 | 850(A)1200 |
SHEET ALUMINUM SIGNS | 682 | SF |
$22.50 |
$29.00 |
$29.36 |
$34.50 |
| 2,230 | 850(B)1310 |
EXTRUDED ALUMINUM PANEL SIGNS | 1,436 | SF |
$26.00 |
$33.00 |
$33.55 |
$39.43 |
| 2,240 | 850(B)1320 |
EXTR.ALUM.PAN.SGN.(OVRHD SIGNS) | 3,643 | SF |
$37.00 |
$33.00 |
$33.55 |
$39.43 |
| 2,250 | 851(A)2200 |
4"@13 GALV.STL.WD.FLANGE BM.POST | 365 | LF |
$30.00 |
$78.00 |
$78.63 |
$92.41 |
| 2,260 | 851(A)2205 |
6"@15 GALV.STL.WD.FLANGE BM.POST | 88 | LF |
$50.00 |
$72.00 |
$71.29 |
$83.79 |
| 2,270 | 851(A)2210 |
6"@20 GALV.STL.WD.FLANGE BM.POST | 63 | LF |
$32.00 |
$77.00 |
$77.58 |
$91.18 |
| 2,280 | 851(A)2220 |
8"@31 GALV.STL.WD.FLANGE BM.POST | 56 | LF |
$55.00 |
$90.00 |
$90.16 |
$105.97 |
| 2,290 | 851(B)2320 |
3 1/2"@9.11 GALV.STL.PIPE POST | 554 | LF |
$25.00 |
$27.00 |
$27.26 |
$32.03 |
| 2,300 | 851(C)2415 |
2" SQUARE TUBE POST | 438 | LF |
$9.50 |
$9.50 |
$9.44 |
$11.09 |
| 2,310 | 852(D)3512 |
OVHD.SN.STR., MONOTUBE TYPE B 70' | 1 | EA |
$150,000.00 |
$164,000.00 |
$167,482.07 |
$196,837.93 |
| 2,320 | 852(D)3528 |
OVHD.SN.STR., MONOTUBE TYPE B 90' | 3 | EA |
$200,000.00 |
$179,000.00 |
$186,353.29 |
$219,016.85 |
| 2,330 | 852(D)3536 |
OVHD.SN.STR., MONOTUBE TYPE B 100' | 3 | EA |
$225,000.00 |
$182,000.00 |
$188,712.19 |
$221,789.22 |
| 2,340 | 852(E)3600 |
OVHD.SN.STR., MONOTUBE TYPE C | 4 | EA |
$75,000.00 |
$72,000.00 |
$73,388.08 |
$86,251.37 |
| 2,350 | 853 5130 |
DELINEATORS(TYPE 1, CODE 1, FLEXIBLE) | 48 | EA |
$21.00 |
$68.00 |
$68.15 |
$80.09 |
| 2,360 | 853 5135 |
DELINEATORS(TYPE 1, CODE 2, FLEXIBLE) | 60 | EA |
$62.00 |
$68.00 |
$68.15 |
$80.09 |
| 2,370 | 853 5145 |
DELINEATORS(TYPE 2, CODE 1, FLEXIBLE) | 16 | EA |
$65.00 |
$70.00 |
$71.29 |
$83.79 |
| 2,380 | 853 5150 |
DELINEATORS(TYPE 2, CODE 2, FLEXIBLE) | 6 | EA |
$65.00 |
$70.00 |
$71.29 |
$83.79 |
| 2,390 | 853 5155 |
DELINEATORS(TYPE 2, CODE 3, FLEXIBLE) | 52 | EA |
$70.00 |
$72.00 |
$73.39 |
$86.25 |
| 2,400 | 853 5160 |
BARRIER DELINEATORS(TYPE 1, CODE 1) | 436 | EA |
$18.00 |
$23.00 |
$23.06 |
$27.11 |
| 2,410 | 853 5165 |
BARRIER DELINEATORS(TYPE 2, CODE 1) | 182 | EA |
$30.00 |
$26.00 |
$26.21 |
$30.80 |
| 2,420 | 856(A)8200 |
TRAFFIC STRIPE(MULTI-POLY.)(4" WIDE) | 8,535 | LF |
$1.10 |
$0.9000 |
$0.8900 |
$1.05 |
| 2,430 | 856(A)8204 |
TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE) | 81,960 | LF |
$0.6000 |
$1.05 |
$1.05 |
$1.23 |
| 2,440 | 856(A)8208 |
TRAFFIC STRIPE(MULTI-POLY.)(8" WIDE) | 9,155 | LF |
$1.30 |
$2.50 |
$2.52 |
$2.96 |
| 2,450 | 856(A)8212 |
TRAFFIC STRIPE(MULTI-POLY)(12" WIDE) | 4,035 | LF |
$2.00 |
$3.75 |
$3.77 |
$4.44 |
| 2,460 | 856(B)8304 |
TRAFFIC STRIPE(MULTI-POLY.)(ARROWS) | 46 | EA |
$155.00 |
$365.00 |
$366.94 |
$431.26 |
| 2,470 | 856(B)8308 |
TRAFFIC STRIPE(MULTI-POLY.)(SYMBOLS) | 28 | EA |
$260.00 |
$4,000.00 |
$4,062.55 |
$4,774.63 |
| 2,480 | 856(B)8312 |
TRAFFIC STRIPE(MULTI-POLY.)(WORDS) | 12 | EA |
$290.00 |
$414.00 |
$419.36 |
$492.86 |
| 2,490 | 857(F)9700 |
PAVEMENT MRKNG.REMOVAL(TRAF.STRP) | 40,000 | LF |
$0.3000 |
$0.3800 |
$0.3800 |
$0.4400 |
| 2,500 | 870(A)1100 |
SAND FILLED IMPACT ATTEN.MODULE | 195 | EA |
$450.00 |
$440.00 |
$445.57 |
$523.67 |
| 2,510 | 871(A)2210 |
(PL) IMPACT ATTENUATOR | 7 | EA |
$25,000.00 |
$33,500.00 |
$36,636.12 |
$42,332.58 |
| 2,520 | 516(A)8230 |
DRILLED SHAFTS 48" DIAMETER | 160 | LF |
$1,000.00 |
$775.00 |
$1,547.07 |
$1,848.24 |
| 2,530 | 610(A)5200 |
4" CONCRETE SIDEWALK | 168 | SY |
$85.00 |
$155.00 |
$154.71 |
$184.83 |
| 2,540 | 802(A)0220 |
1 1/4" GALV.STEEL ELECT.COND. EXPOSED | 1,100 | LF |
$40.00 |
$42.00 |
$42.29 |
$50.51 |
| 2,550 | 802(B)0320 |
2" PVC SCH.40 PLASTIC CONDUIT BORED | 1,055 | LF |
$35.00 |
$42.00 |
$36.10 |
$43.12 |
| 2,560 | 802(B)0324 |
2" PVC SCH.40 PLASTIC CONDUIT TRENCHED | 2,668 | LF |
$15.00 |
$15.50 |
$19.08 |
$22.79 |
| 2,570 | 802(E)0600 |
JUNCTION BOX(6" X 6" X 4") | 13 | EA |
$1,000.00 |
$835.00 |
$1,392.36 |
$1,663.42 |
| 2,580 | 803(A)1210 |
PULL BOX(SIZE I) | 9 | EA |
$1,200.00 |
$1,250.00 |
$1,882.27 |
$2,248.70 |
| 2,590 | 804(A)2200 |
STRUCTURAL CONCRETE | 17.64 | CY |
$950.00 |
$975.00 |
$2,346.39 |
$2,803.17 |
| 2,600 | 804(B)2300 |
REINFORCING STEEL | 2,921 | LB |
$2.20 |
$2.55 |
$2.73 |
$3.26 |
| 2,610 | 805(A)3216 |
REMOVAL OF HIGH MAST TOWER | 5 | EA |
$5,000.00 |
$4,250.00 |
$10,313.80 |
$12,321.62 |
| 2,620 | 805(A)3228 |
(PL)REMOVAL OF LIGHT POLE | 8 | EA |
$500.00 |
$890.00 |
$1,031.38 |
$1,232.16 |
| 2,630 | 806(C)4516 |
40' MTG & 12' HLMA(G.STL.) | 2 | EA |
$45,000.00 |
$6,500.00 |
$5,775.73 |
$6,900.11 |
| 2,640 | 806(C)4524 |
40' MHP & TWIN H.L.MST.ARM(G.STL.) | 11 | EA |
$75,000.00 |
$6,800.00 |
$7,374.37 |
$8,809.96 |
| 2,650 | 807 5120 |
BREAKAWAY BASE (DES. B) | 2 | EA |
$830.00 |
$1,200.00 |
$1,443.94 |
$1,725.02 |
| 2,660 | 809(A)7200 |
ROADWAY LUMINAIRE | 22 | EA |
$1,800.00 |
$1,800.00 |
$1,493.44 |
$1,784.17 |
| 2,670 | 809(B)7300 |
UNDERPASS LUMINAIRE | 23 | EA |
$1,850.00 |
$1,180.00 |
$1,145.86 |
$1,368.93 |
| 2,680 | 809(E)7600 |
HIGH MAST LUMINAIRE | 68 | EA |
$2,800.00 |
$3,300.00 |
$2,498.00 |
$2,984.29 |
| 2,690 | 810(A)8200 |
SERVICE POLE | 2 | EA |
$5,000.00 |
$4,700.00 |
$1,031.38 |
$1,232.16 |
| 2,700 | 811 9105 |
1/C NO.1 ELECT.COND. | 9,729 | LF |
$2.50 |
$5.25 |
$5.16 |
$6.16 |
| 2,710 | 811 9130 |
1/C NO.10 ELECT.COND. | 1,400 | LF |
$3.00 |
$3.15 |
$2.58 |
$3.08 |
| 2,720 | 811 9135 |
1/C NO.12 ELECT.COND. | 2,420 | LF |
$3.20 |
$2.60 |
$1.65 |
$1.97 |
| 2,730 | 812 0150 |
150' HIGH MAST POLE(G.STL.) | 8 | EA |
$85,000.00 |
$69,000.00 |
$76,837.79 |
$91,796.09 |
| 2,740 | 813 1100 |
HIGH MAST LOWERING DEV.TYP.I | 9 | EA |
$15,000.00 |
$21,000.00 |
$33,519.84 |
$40,045.28 |
| 2,750 | 642(B)3300 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$190,000.00 |
$368,000.00 |
$484,991.03 |
$220,680.27 |
| 2,760 | 220 1100 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$50,000.00 |
$2,025.44 |
$38,084.80 |
$5,000.00 |
| 2,770 | 641 2100 |
MOBILIZATION | 1 | LSUM |
$2,210,000.00 |
|
|
|