Bid tab 220133

Let Apr 14, 2022 · Division 4 · Noble Sign up free

‹ Apr 2022 results

BRIDGE AND APPROACHES COUNTY ROAD (EW-36): OVER BUNCH CREEK, 3.6 MILES WEST OF I -35 NEAR BILLINGS. PROJECT LENGTH = 0.237 MILE

Let date
Thursday, April 14, 2022
Contract
220133
J/P numbers
31949(04)
District
Division 4
County
Noble
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (EW-36): OVER BUNCH CREEK, 3.6 MILES WEST OF I -35 NEAR BILLINGS. PROJECT LENGTH = 0.237 MILE
Project number
STP-252D(094)CI

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$935,308
1 K & R BUILDERS, INC. Low bidder $979,341 +4.7%
2 RRY SERVICES LLC $1,014,593 +8.5% +3.6%
3 BRIDGECO CONTRACTORS, INC. $1,091,647 +16.7% +11.5%

Bid tab: unit prices 45 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 K & R BUILDERS,…#2 RRY SERVICES LLC#3 BRIDGECO CONTRA…
10201(A)1200 CLEARING AND GRUBBING1LSUM $7,500.00 $10,500.00 $15,000.00 $37,000.00
20202(A)2200 UNCLASSIFIED EXCAVATION1,601CY $10.00 $8.50 $7.00 $10.00
30202(D)2500 UNCLASSIFIED BORROW4,962CY $11.00 $9.60 $11.00 $13.00
40205(A)6200 TYPE A-SALVAGED TOPSOIL1LSUM $7,000.00 $8,250.00 $13,000.00 $8,100.00
50221(B)2300 TEMPORARY SILT FENCE1,950LF $3.00 $2.50 $2.24 $4.40
60221(E)2600 TEMPORARY SILT DIKE336LF $12.50 $12.50 $12.50 $13.00
70230(A)7200 SOLID SLAB SODDING9,938SY $3.20 $3.45 $2.95 $4.95
80233(A)0200 VEGETATIVE MULCHING2.05AC $800.00 $500.00 $800.00 $1,100.00
90402(E)2600 TRAFFIC BOUND SURFACE COURSE TYPE E803TON $50.00 $48.98 $60.00 $63.82
100509(D)0500 CLASS C CONCRETE10CY $350.00 $375.00 $330.00 $375.00
110613(EE)5976 (SP) 30" CORRUGATED POLYPROPYLENE PIPE64LF $93.00 $150.00 $165.00 $141.41
120613(M)6908 TYPE C3 CULVERT END TREATMENT2EA $1,575.00 $1,625.00 $2,050.00 $3,500.00
130619(A)6200 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $3,500.00 $4,000.00 $2,600.00 $6,000.00
140623(F)1704 GUARDRAIL ANCHOR UNIT (TYPE A)4EA $3,200.00 $2,750.00 $2,500.00 $2,750.00
150623(F)1724 GUARDRAIL ANCHOR UNIT (TYPE D-BF)4EA $3,500.00 $2,475.00 $2,250.00 $2,600.00
160624(C)3410 FENCE-STYLE SWF (6 BARBED WIRE)1,164LF $7.75 $15.40 $12.80 $20.00
170501(B)1300 SUBSTRUCTURE EXCAVATION COMMON180CY $15.00 $12.00 $13.00 $18.00
180501(F)1700 GRANULAR BACKFILL66CY $79.50 $90.00 $107.00 $154.55
190503(A)4220 PRESTRESSED CONCRETE BEAMS (TYPE II)507LF $250.00 $256.00 $260.00 $267.20
200504(D)5410 CONCRETE RAIL (TR3)396LF $83.50 $82.50 $110.00 $86.00
210506(A)7200 STRUCTURAL STEEL1,060LB $4.00 $5.00 $5.00 $5.60
220507(A)8210 WEATHERING STEEL FIXED BEARING ASSEMBLY9EA $1,200.00 $1,280.00 $1,600.00 $1,223.60
230507(B)8310 WEATHERING STL EXP. BEARING ASSEMBLY9EA $1,200.00 $1,280.00 $1,600.00 $1,223.60
240509(A)0210 CLASS AA CONCRETE131.5CY $675.00 $690.00 $725.00 $760.00
250509(B)0320 CLASS A CONCRETE90.6CY $675.00 $720.00 $725.00 $760.00
260511(A)2210 REINFORCING STEEL45,020LB $1.40 $1.39 $1.37 $1.41
270514(A)5210 PILES, FURNISHED (HP 10X42)156LF $55.00 $49.00 $65.00 $44.10
280514(A)5220 PILES, FURNISHED (HP 12X53)360LF $65.00 $58.80 $78.00 $54.30
290514(B)5310 PILES, DRIVEN (HP 10X42)156LF $16.00 $21.00 $10.00 $20.00
300514(B)5320 PILES, DRIVEN (HP 12X53)360LF $15.55 $25.20 $10.00 $20.00
310514(L)6300 PILE SPLICE, H-PILE (NON-BIDDABLE)1EA $400.00 $400.00 $400.00 $400.00
320516(A)8230 DRILLED SHAFTS 48" DIAMETER154LF $810.00 $773.00 $825.00 $787.00
330518(B)0300 SEALED EXPANSION JOINTS58.34LF $340.00 $370.00 $370.00 $359.00
340601(B)1230 TYPE I-A PLAIN RIPRAP533TON $60.00 $63.65 $64.00 $54.00
350601(C)1310 TYPE I-A FILTER BLANKET178TON $51.00 $48.98 $50.00 $53.00
360613(H)6205 6" PERFORATED PIPE UNDERDRAIN ROUND52LF $33.40 $43.00 $45.00 $60.00
370613(I)6310 6" NON-PERF.PIPE UNDERDRAIN RND.60LF $28.75 $37.00 $45.00 $60.00
380619(D)6700 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $8,000.00 $20,000.00 $5,000.00 $33,000.00
390880(B)6310 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF3,000SD $0.3200 $0.5500 $0.1000 $0.1500
400880(B)6320 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF300SD $0.3500 $10.00 $6.00 $5.50
410880(C)6410 CONSTRUCTION BARRICADES(TYPE III)2,400SD $0.2700 $1.10 $0.1000 $0.1500
420880(E)6600 WARNING LIGHTS(TYPE A)6,000SD $0.0200 $0.8300 $0.1500 $0.1200
430642(B)3300 CONSTRUCTION STAKING LEVEL II1LSUM $6,400.00 $6,900.00 $8,000.00 $10,100.00
440220 1100 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $2,300.00 $1,800.00 $1,350.00 $4,200.00
450641 2100 MOBILIZATION1LSUM $60,000.00 $68,500.00 $79,000.00 $62,000.00