Bid tab 200169

Let Apr 16, 2020 · Division 8 · Rogers Sign up free

‹ Apr 2020 results

RESURFACE (ASPHALT ) US-169: FROM 7.36 MILES NORTHEAST OF THE TULSA COUNTY LINE , EXTEND NORTH NEAR OOLOGAH . PROJECT LENGTH = 5.010 MILES

Let date
Thursday, April 16, 2020
Contract
200169
J/P numbers
32718(04)
District
Division 8
County
Rogers
Highway
Limits
RESURFACE (ASPHALT ) US-169: FROM 7.36 MILES NORTHEAST OF THE TULSA COUNTY LINE , EXTEND NORTH NEAR OOLOGAH . PROJECT LENGTH = 5.010 MILES
Project number
NHPP-030N(078)3P

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 BECCO CONTRACTORS, INC. Low bidder $1,793,000
2 APAC-CENTRAL, INC. $1,865,000 +4.0%
3 Rosscon, LLC $2,015,378 +12.4%
4 SHERWOOD CONSTRUCTION CO., INC. $2,057,537 +14.8%

Bid tab: unit prices 15 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 BECCO CONTRACTO…#2 APAC-CENTRAL, I…#3 Rosscon, LLC#4 SHERWOOD CONSTR…
1303(A) 2100 AGGREGATE BASE TYPE A667CY $45.00 $20.00 $50.00 $45.00 $61.00
2402(A) 0217 TRAFFIC BOUND SURFACE COURSE TYPE A59TON $25.00 $18.00 $50.00 $30.00 $48.57
3407(B) 0250 TACK COAT11,738GAL $2.00 $2.00 $2.00 $2.50 $1.93
4411(C) 5955 SUPERPAVE, TYPE S4(PG 70-28 OK)16,755TON $85.00 $70.00 $79.00 $83.50 $82.09
5411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)723TON $68.00 $75.00 $79.00 $60.00 $84.73
6411(H) 6210 SUPERPAVE, TYPE S3(PATCH)(PG64-22OK)1,344TON $100.00 $40.00 $79.00 $100.00 $72.00
7411(I) 6310 SUPERPAVE, TYPE S4(PATCH)(PG64-22OK)336TON $100.00 $60.00 $79.00 $95.00 $100.00
8412 5267 COLD MILLING PAVEMENT156,498SY $1.50 $1.50 $1.00 $1.50 $1.51
9413(A) 4870 RUMBLE STRIP-CENTERLINE HMA-CON4,921LF $0.4500 $0.7000 $0.7500 $0.5500 $0.5200
10856(A) 8535 TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE)122,100LF $0.7500 $0.5000 $0.5000 $0.5000 $0.4900
11856(A) 8548 TRAFFIC STRIPE(MULTI-POLY)(12" WIDE)180LF $1.10 $5.00 $3.00 $3.50 $3.12
12856(B) 8860 TRAFFIC STRIPE(MULTI-POLY.)(ARROWS)30EA $100.00 $125.00 $120.00 $120.00 $120.49
13857(F) 8820 PAVEMENT MARKING REMOVAL (HYDROBLASTING)1,386LF $2.50 $2.00 $1.00 $2.00 $1.04
14880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $15,000.00 $34,463.30 $17,500.00 $10,000.00 $37,666.58
15641 1552 MOBILIZATION1LSUM $20,000.00 $113,000.00 $47,477.25 $30,000.00 $82,300.35