RESURFACE (ASPHALT ) US-62: FROM 6.3 MILES EAST OF THE SH -9 JUNCTION, EXTEND EAST THEN NORTH IN ANADARKO . PROJECT LENGTH = 1.620 MILES
- Let date
- Thursday, April 16, 2020
- Contract
- 200142
- J/P numbers
- 33883(04)
- District
- Division 7
- County
- Caddo
- Highway
- Limits
- RESURFACE (ASPHALT ) US-62: FROM 6.3 MILES EAST OF THE SH -9 JUNCTION, EXTEND EAST THEN NORTH IN ANADARKO . PROJECT LENGTH = 1.620 MILES
- Project number
- STP-208B(072)3P
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $843,750 | ||
| 1 | T & G CONSTRUCTION, INC. Low bidder | $735,101 | -12.9% | |
| 2 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) | $893,970 | +6.0% | +21.6% |
| 3 | HASKELL LEMON CONSTRUCTION CO. | $963,033 | +14.1% | +31.0% |
| 4 | Silver Star Construction Company, Inc. | $992,700 | +17.7% | +35.0% |
| 5 | THE CUMMINS CONSTRUCTION CO., INC. | $1,211,656 | +43.6% | +64.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 T & G CONSTRUCT… | #2 ALLEN CONTRACTI… | #3 HASKELL LEMON C… | #4 Silver Star Con… | #5 THE CUMMINS CON… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 411(C) 5955 | SUPERPAVE, TYPE S4(PG 70-28 OK) | 5,700 | TON | $95.00 | $88.80 | $99.00 | $124.00 | $103.90 | $129.80 |
| 2 | 411(H) 6210 | SUPERPAVE, TYPE S3(PATCH)(PG64-22OK) | 632 | TON | $200.00 | $150.00 | $190.00 | $115.00 | $148.00 | $291.00 |
| 3 | 412 5267 | COLD MILLING PAVEMENT | 50,750 | SY | $2.00 | $1.26 | $3.00 | $2.85 | $4.60 | $4.35 |
| 4 | 855(A) 8825 | TRAFFIC STRIPE(PLASTIC)(24" WIDE) | 260 | LF | $9.00 | $11.86 | $3.50 | $3.45 | $11.00 | $13.15 |
| 5 | 855(A) 8840 | TRAFFIC STRIPE(PLASTIC)(THIN LINE)(4" WIDE) | 49,775 | LF | $0.4000 | $0.6100 | $0.4000 | $0.5000 | $0.6000 | $0.7000 |
| 6 | 855(B) 8818 | TRAFFIC STRIPE(PLASTIC)(ARROWS) | 12 | EA | $100.00 | $142.73 | $110.00 | $115.00 | $140.00 | $160.00 |
| 7 | 855(B) 8821 | TRAFFIC STRIPE(PLASTIC)(WORDS) | 6 | EA | $150.00 | $234.30 | $200.00 | $201.50 | $250.00 | $265.00 |
| 8 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $50,000.00 | $33,631.14 | $34,000.00 | $10,541.50 | $37,579.00 | $25,350.00 |