RIGHT-OF-WAY CLEARANCE SH-20 REALIGNMENT: FROM 0.7 MILES EAST OF THE SH -66 JUNCTION, EXTEND NORTHWEST IN CLAREMORE . PROJECT LENGTH = 1.723 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTED .

Let date
Thursday, April 16, 2020
Contract
200122
J/P numbers
26242(10)
District
Division 8
County
Rogers
Highway
Limits
RIGHT-OF-WAY CLEARANCE SH-20 REALIGNMENT: FROM 0.7 MILES EAST OF THE SH -66 JUNCTION, EXTEND NORTHWEST IN CLAREMORE . PROJECT LENGTH = 1.723 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTED .
Project number
SSP-266N(083)RW

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Robin Hausner Demolition, LLC Low bidder $58,338
2 D T SPECIALIZED SERVICES, INC. $64,500 +10.6%
3 WEAVER EXCAVATING, INC. $71,000 +21.7%
4 GROUND LEVEL, LLC $78,000 +33.7%

Bid tab: unit prices 4 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Robin Hausner D…#2 D T SPECIALIZED…#3 WEAVER EXCAVATI…#4 GROUND LEVEL, L…
1233(A) 2817 VEGETATIVE MULCHING1AC $5,000.00 $100.00 $1,500.00 $2,000.00 $12,500.00
2619(G) 0094 RIGHT-OF-WAY CLEARANCE1LSUM $111,878.00 $56,238.00 $55,800.00 $59,000.00 $58,000.00
3880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $5,000.00 $500.00 $0.00 $1,000.00 $2,500.00
4641 1552 MOBILIZATION1LSUM $5,000.00 $1,500.00 $7,200.00 $9,000.00 $5,000.00