Bid tab 190175

Let May 16, 2019 · Division 3 · Garvin Sign up free

‹ May 2019 results

RESURFACE (ASPHALT ) I-35 (SB LANES): FROM THE SH -29 JUNCTION, EXTEND SOUTH NEAR WYNNEWOOD. PROJECT LENGTH = 6.59 MILES

Let date
Thursday, May 16, 2019
Contract
190175
J/P numbers
31840(04)
District
Division 3
County
Garvin
Highway
Limits
RESURFACE (ASPHALT ) I-35 (SB LANES): FROM THE SH -29 JUNCTION, EXTEND SOUTH NEAR WYNNEWOOD. PROJECT LENGTH = 6.59 MILES
Project number
NHPPI-3500-(051)SS

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$2,390,372
1 THE CUMMINS CONSTRUCTION CO., INC. Low bidder $2,796,665 +17.0%
2 Silver Star Construction Company, Inc. $3,002,000 +25.6% +7.3%
3 HASKELL LEMON CONSTRUCTION CO. $3,114,400 +30.3% +11.4%

Bid tab: unit prices 11 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 THE CUMMINS CON…#2 Silver Star Con…#3 HASKELL LEMON C…
1407(B) 0250 TACK COAT24,937GAL $2.70 $3.00 $2.50 $3.35
2411(D) 5965 SUPERPAVE, TYPE S5(PG 76-28 OK)13,000TON $85.00 $89.70 $87.40 $103.00
3411(J) 6410 (SP) RICH INTERMEDIATE LAYER10,900TON $88.00 $116.20 $112.00 $107.50
4412 5267 COLD MILLING PAVEMENT92,787SY $0.8500 $1.80 $4.20 $2.75
5413(A) 4861 RUMBLE STRIP-METHOD HMA-CON69,590LF $0.2200 $0.1500 $0.2000 $0.1500
6855(A) 8813 TRAFFIC STRIPE(PLASTIC)(6" WIDE)78,290LF $0.5500 $0.5500 $0.6000 $0.8500
7857(D) 8870 NONREMOVABLE PAVEMENT MARKING TAPE(6" WIDE)6,326LF $14.00 $6.50 $6.95 $16.90
8880(A) 8812 ARROW DISPLAY(TYPE C)80SD $5.00 $10.00 $10.65 $1.40
9880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $20,000.00 $14,500.00 $74,922.40 $68,788.40
10880(L) 8920 (SP) TRAFFIC SURVEILLANCE, OHP (NON-BIDDABLE)160HOUR $69.00 $69.00 $69.00 $69.00
11882(A) 8306 PORT.CHANGEABLE MESSAGE SIGN80SD $20.00 $15.00 $16.00 $13.90