RESURFACE (ASPHALT ) US-75 (SB LANES): FROM THE SH -16 JUNCTION, EXTEND NORTH NEAR WINCHESTER. PROJECT LENGTH = 8.00 MILES
- Let date
- Thursday, March 14, 2019
- Contract
- 190126
- J/P numbers
- 34045(04)
- District
- Division 1
- County
- Okmulgee
- Highway
- Limits
- RESURFACE (ASPHALT ) US-75 (SB LANES): FROM THE SH -16 JUNCTION, EXTEND NORTH NEAR WINCHESTER. PROJECT LENGTH = 8.00 MILES
- Project number
- MC-256N(053)
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,312,100 | ||
| 1 | APAC-CENTRAL, INC. Low bidder | $1,250,044 | -4.7% | |
| 2 | Rosscon, LLC | $1,275,945 | -2.8% | +2.1% |
| 3 | BECCO CONTRACTORS, INC. | $1,293,000 | -1.5% | +3.4% |
| 4 | Paragon Contractors, LLC | $1,316,316 | +0.3% | +5.3% |
| 5 | SHERWOOD CONSTRUCTION CO., INC. | $1,411,520 | +7.6% | +12.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 APAC-CENTRAL, I… | #2 Rosscon, LLC | #3 BECCO CONTRACTO… | #4 Paragon Contrac… | #5 SHERWOOD CONSTR… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 407(B) 0250 | TACK COAT | 8,800 | GAL | $2.25 | $1.50 | $2.00 | $1.00 | $3.50 | $7.07 |
| 2 | 411(C) 5950 | SUPERPAVE, TYPE S4(PG 76-28 OK) | 12,750 | TON | $76.00 | $84.00 | $84.00 | $75.00 | $81.25 | $90.25 |
| 3 | 411(I) 6310 | SUPERPAVE, TYPE S4(PATCH)(PG64-22OK) | 25 | TON | $225.00 | $84.00 | $100.00 | $75.00 | $282.00 | $220.80 |
| 4 | 412 5267 | COLD MILLING PAVEMENT | 113,500 | SY | $2.00 | $1.00 | $1.10 | $1.25 | $1.05 | $1.31 |
| 5 | 856(A) 8530 | TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 91,700 | LF | $0.7500 | $0.3200 | $0.3500 | $0.3500 | $0.3500 | $0.3500 |
| 6 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $15,000.00 | $14,000.00 | $21,000.00 | $145,205.00 | $84,358.50 | $5,416.84 |
| 7 | 880(L) 8920 | (SP) TRAFFIC SURVEILLANCE, OHP (NON-BIDDABLE) | 100 | HOUR | $69.00 | $69.00 | $69.00 | $69.00 | $69.00 | $69.00 |