| 1 | 201(B) 0181 |
SELECTIVE CLEARING | 1 | LSUM |
$3,000.00 |
$849.59 |
$3,000.00 |
$7,250.00 |
$4,200.00 |
$14,650.00 |
| 2 | 414(E) 0225 |
FULL DEPTH P.C. CONCRETE PATCHING(PLACEMENT ONLY) | 10 | SY |
$115.00 |
$120.36 |
$325.00 |
$630.00 |
$220.00 |
$364.00 |
| 3 | 414(G) 5275 |
P.C. CONCRETE FOR PAVEMENT | 3 | CY |
$150.00 |
$177.00 |
$300.00 |
$200.00 |
$180.00 |
$398.50 |
| 4 | 501(G) 6309 |
CLSM BACKFILL | 47.7 | CY |
$150.00 |
$198.73 |
$280.00 |
$308.00 |
$250.00 |
$317.50 |
| 5 | 501(H) 6360 |
(PL) CELLULAR CONCRETE BACKFILL | 9.4 | CY |
$175.00 |
$601.94 |
$550.00 |
$100.00 |
$400.00 |
$150.00 |
| 6 | 504(A) 1304 |
APPROACH SLAB | 169.3 | SY |
$200.00 |
$68.30 |
$300.00 |
$467.50 |
$425.00 |
$435.50 |
| 7 | 504(B) 1305 |
SAW-CUT GROOVING | 495.6 | SY |
$4.50 |
$7.65 |
$8.00 |
$5.94 |
$5.60 |
$6.80 |
| 8 | 505(A) 6065 |
BRIDGE DECK CONCRETE OVERLAY | 415.9 | SY |
$150.00 |
$225.77 |
$175.00 |
$196.75 |
$181.90 |
$291.50 |
| 9 | 505(E) 1000 |
HYDRODEMOLITION | 415.9 | SY |
$110.00 |
$116.11 |
$180.00 |
$148.00 |
$169.00 |
$174.50 |
| 10 | 509 6152 |
SPECIAL CONCRETE FINISH | 230 | SY |
$30.00 |
$124.61 |
$35.00 |
$96.80 |
$85.00 |
$114.50 |
| 11 | 513(B) 6019 |
CLASS B BRIDGE DECK REPAIR | 21 | SY |
$350.00 |
$318.60 |
$205.00 |
$250.00 |
$660.00 |
$150.00 |
| 12 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 274 | SY |
$4.00 |
$7.08 |
$7.00 |
$5.50 |
$4.00 |
$6.30 |
| 13 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 150 | LF |
$30.00 |
$56.64 |
$20.00 |
$44.00 |
$36.00 |
$52.00 |
| 14 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 2.1 | GAL |
$75.00 |
$113.28 |
$80.00 |
$88.00 |
$80.00 |
$104.00 |
| 15 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 3.5 | SY |
$900.00 |
$1,168.19 |
$750.00 |
$907.50 |
$1,700.00 |
$1,072.00 |
| 16 | 523(A) 6550 |
SEALER CRACK PREPARATION | 99 | LF |
$5.00 |
$7.08 |
$5.00 |
$5.50 |
$4.00 |
$6.30 |
| 17 | 523(B) 6560 |
SEALER RESIN | 0.2 | GAL |
$175.00 |
$424.80 |
$50.00 |
$330.00 |
$80.00 |
$378.50 |
| 18 | 535 6130 |
(SP)CORROSION INHIBITOR(SURFACE APPLIED) | 20 | SY |
$60.00 |
$42.48 |
$50.00 |
$33.00 |
$30.00 |
$39.00 |
| 19 | 540 4505 |
(PL)REPAIR BRIDGE ITEMS | 1 | EA |
$300.00 |
$424.80 |
$3,000.00 |
$3,100.00 |
$4,000.00 |
$3,972.00 |
| 20 | 542 4605 |
(PL)INSTALLATION OF BRIDGE ITEMS | 2 | EA |
$50.00 |
$70.80 |
$600.00 |
$1,500.00 |
$1,000.00 |
$200.00 |
| 21 | 619(B) 2500 |
REMOVAL OF BRIDGE ITEMS | 1 | LSUM |
$10,000.00 |
$11,327.93 |
$15,000.00 |
$13,970.00 |
$36,000.00 |
$18,000.00 |
| 22 | 501(G) 6309 |
CLSM BACKFILL | 47.7 | CY |
$150.00 |
$241.21 |
$280.00 |
$308.00 |
$250.00 |
$302.50 |
| 23 | 501(H) 6360 |
(PL) CELLULAR CONCRETE BACKFILL | 12.4 | CY |
$175.00 |
$601.94 |
$550.00 |
$100.00 |
$400.00 |
$150.00 |
| 24 | 504(A) 1304 |
APPROACH SLAB | 169.3 | SY |
$200.00 |
$68.30 |
$300.00 |
$467.50 |
$425.00 |
$401.00 |
| 25 | 504(B) 1305 |
SAW-CUT GROOVING | 495.6 | SY |
$4.50 |
$7.65 |
$8.00 |
$5.94 |
$5.60 |
$6.80 |
| 26 | 505(A) 6065 |
BRIDGE DECK CONCRETE OVERLAY | 415.9 | SY |
$150.00 |
$225.77 |
$175.00 |
$196.75 |
$181.90 |
$291.50 |
| 27 | 505(E) 1000 |
HYDRODEMOLITION | 415.9 | SY |
$110.00 |
$116.11 |
$180.00 |
$148.00 |
$169.00 |
$174.50 |
| 28 | 509 6152 |
SPECIAL CONCRETE FINISH | 230 | SY |
$30.00 |
$124.61 |
$35.00 |
$96.80 |
$85.00 |
$114.50 |
| 29 | 513(B) 6019 |
CLASS B BRIDGE DECK REPAIR | 21 | SY |
$350.00 |
$318.60 |
$205.00 |
$250.00 |
$660.00 |
$150.00 |
| 30 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 274 | SY |
$4.00 |
$7.08 |
$7.00 |
$5.50 |
$4.00 |
$6.30 |
| 31 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 100 | LF |
$30.00 |
$56.64 |
$20.00 |
$44.00 |
$36.00 |
$52.00 |
| 32 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 1.5 | GAL |
$75.00 |
$113.28 |
$80.00 |
$88.00 |
$80.00 |
$104.00 |
| 33 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 4 | SY |
$900.00 |
$1,168.19 |
$750.00 |
$907.50 |
$1,700.00 |
$1,072.00 |
| 34 | 523(A) 6550 |
SEALER CRACK PREPARATION | 99 | LF |
$5.00 |
$7.08 |
$5.00 |
$5.50 |
$4.00 |
$6.30 |
| 35 | 523(B) 6560 |
SEALER RESIN | 0.2 | GAL |
$175.00 |
$424.80 |
$50.00 |
$330.00 |
$80.00 |
$378.50 |
| 36 | 535 6130 |
(SP)CORROSION INHIBITOR(SURFACE APPLIED) | 20 | SY |
$60.00 |
$42.48 |
$50.00 |
$33.00 |
$30.00 |
$39.00 |
| 37 | 619(B) 2500 |
REMOVAL OF BRIDGE ITEMS | 1 | LSUM |
$10,000.00 |
$11,327.93 |
$15,000.00 |
$13,970.00 |
$36,000.00 |
$18,000.00 |
| 38 | 856(A) 8535 |
TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE) | 10,740 | LF |
$1.00 |
$0.8500 |
$0.6000 |
$0.6600 |
$0.6300 |
$0.8600 |
| 39 | 857(E) 8887 |
(PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 | 2,508 | EA |
$0.6500 |
$1.06 |
$0.7500 |
$0.8300 |
$0.7900 |
$0.8200 |
| 40 | 857(F) 8820 |
PAVEMENT MARKING REMOVAL (HYDROBLASTING) | 12,146 | LF |
$0.5000 |
$0.3500 |
$0.2500 |
$0.2800 |
$0.2600 |
$0.5400 |
| 41 | 871(B) 8705 |
(SP)CONST.ZONE IMPACT ATTEN. | 180 | SD |
$12.00 |
$7.08 |
$5.00 |
$5.50 |
$5.25 |
$22.70 |
| 42 | 877(B) 8484 |
DELIVER PORTABLE LONGITUDINAL BARRIER | 1,300 | LF |
$33.00 |
$22.66 |
$16.00 |
$17.60 |
$16.80 |
$16.40 |
| 43 | 877(C) 8486 |
RELOCATION OF PORTABLE LONGITUDINAL BARRIER | 1,300 | LF |
$3.50 |
$1.42 |
$1.00 |
$1.10 |
$1.05 |
$2.50 |
| 44 | 880(A) 8812 |
ARROW DISPLAY(TYPE C) | 180 | SD |
$475.00 |
$7.08 |
$5.00 |
$5.50 |
$5.25 |
$12.60 |
| 45 | 880(B) 8818 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 2,340 | SD |
$0.4000 |
$0.1400 |
$0.1000 |
$0.1100 |
$0.1100 |
$0.3200 |
| 46 | 880(B) 8821 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 2,520 | SD |
$0.7500 |
$0.1400 |
$0.1000 |
$0.1100 |
$0.1100 |
$0.8200 |
| 47 | 880(B) 8824 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 1,620 | SD |
$0.8500 |
$4.25 |
$3.00 |
$3.30 |
$3.15 |
$2.10 |
| 48 | 880(C) 8842 |
CONSTRUCTION BARRICADES(TYPE III) | 1,080 | SD |
$1.00 |
$2.83 |
$2.00 |
$2.20 |
$2.10 |
$0.6300 |
| 49 | 880(C) 8848 |
WING BARRICADES | 360 | SD |
$1.20 |
$7.08 |
$5.00 |
$5.50 |
$5.25 |
$0.6300 |
| 50 | 880(E) 8860 |
WARNING LIGHTS(TYPE A) | 2,520 | SD |
$0.3500 |
$1.42 |
$1.00 |
$1.10 |
$1.05 |
$0.4400 |
| 51 | 880(F) 8878 |
DRUMS | 6,480 | SD |
$0.2000 |
$0.1400 |
$0.1000 |
$0.1100 |
$0.1100 |
$0.8800 |
| 52 | 882(A) 8306 |
PORT.CHANGEABLE MESSAGE SIGN | 180 | SD |
$15.50 |
$14.16 |
$10.00 |
$11.00 |
$10.50 |
$20.20 |
| 53 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$10,000.00 |
$6,301.16 |
$3,000.00 |
$5,000.00 |
$6,000.00 |
$5,681.00 |
| 54 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$54,000.00 |
$57,347.66 |
$65,304.84 |
$74,000.00 |
$62,950.00 |
$74,000.00 |