RESURFACE (ASPHALT ) SH-76: FROM THE SH -19 JUNCTION, EXTEND SOUTH IN LINDSAY . PROJECT LENGTH = 2.76 MILES
- Let date
- Thursday, April 19, 2018
- Contract
- 180162
- J/P numbers
- 31829(04)
- District
- Division 3
- County
- Garvin
- Highway
- Limits
- RESURFACE (ASPHALT ) SH-76: FROM THE SH -19 JUNCTION, EXTEND SOUTH IN LINDSAY . PROJECT LENGTH = 2.76 MILES
- Project number
- ACSTP-225C(070)3P
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $509,831 | ||
| 1 | MARKWELL PAVING COMPANY, INC. Low bidder | $425,149 | -16.6% | |
| 2 | THE CUMMINS CONSTRUCTION CO., INC. | $481,722 | -5.5% | +13.3% |
| 3 | HASKELL LEMON CONSTRUCTION CO. | $519,952 | +2.0% | +22.3% |
| 4 | OVERLAND CORPORATION | $537,018 | +5.3% | +26.3% |
| 5 | Silver Star Construction Company, Inc. | $545,320 | +7.0% | +28.3% |
| 6 | Pavers, Inc. | $604,905 | +18.6% | +42.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 MARKWELL PAVING… | #2 THE CUMMINS CON… | #3 HASKELL LEMON C… | #4 OVERLAND CORPOR… | #5 Silver Star Con… | #6 Pavers, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 202(D) 0184 | UNCLASSIFIED BORROW | 234 | CY | $18.00 | $10.97 | $45.00 | $25.00 | $56.50 | $50.00 | $35.00 |
| 2 | 407(B) 0250 | TACK COAT | 5,000 | GAL | $2.75 | $2.00 | $2.40 | $3.50 | $0.0100 | $2.50 | $3.50 |
| 3 | 411(D) 5970 | SUPERPAVE, TYPE S5(PG 70-28 OK) | 5,101 | TON | $85.00 | $72.33 | $83.00 | $89.25 | $91.20 | $79.20 | $95.00 |
| 4 | 412 5267 | COLD MILLING PAVEMENT | 4,200 | SY | $6.00 | $1.98 | $2.10 | $4.50 | $2.50 | $11.70 | $5.00 |
| 5 | 828(B) 8136 | LOOP DETECTOR WIRE | 460 | LF | $14.00 | $8.59 | $9.55 | $10.50 | $6.00 | $10.90 | $20.00 |
| 6 | 855(A) 8825 | TRAFFIC STRIPE(PLASTIC)(24" WIDE) | 96 | LF | $7.00 | $4.00 | $4.00 | $4.25 | $9.85 | $4.35 | $20.00 |
| 7 | 855(A) 8840 | TRAFFIC STRIPE(PLASTIC)(THIN LINE)(4" WIDE) | 36,600 | LF | $0.4200 | $0.3200 | $0.3200 | $0.3500 | $0.3500 | $0.3500 | $1.00 |
| 8 | 855(B) 8818 | TRAFFIC STRIPE(PLASTIC)(ARROWS) | 4 | EA | $150.00 | $125.00 | $125.00 | $135.00 | $130.00 | $137.00 | $225.00 |
| 9 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $10,000.00 | $18,763.73 | $10,000.00 | $3,850.00 | $31,000.00 | $49,191.20 | $25,000.00 |