Bid tab 180145

Let Mar 15, 2018 · · Pottawatomie, Seminole Sign up free

‹ Mar 2018 results

PEDESTRIAN IMPROVEMENTS (TRAIL AND SIDEWALK ) PEDESTRIAN TRAIL : AT MAUD PUBLIC SCHOOL, BETWEEN HARRIS AVE AND TAYLOR AVE IN MAUD . PROJECT LENGTH = 0.410 MILE

Let date
Thursday, March 15, 2018
Contract
180145
J/P numbers
33006(04)
District
County
Pottawatomie, Seminole
Highway
Limits
PEDESTRIAN IMPROVEMENTS (TRAIL AND SIDEWALK ) PEDESTRIAN TRAIL : AT MAUD PUBLIC SCHOOL, BETWEEN HARRIS AVE AND TAYLOR AVE IN MAUD . PROJECT LENGTH = 0.410 MILE
Project number
TAP-263D(050)TP

Bidders 7

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$256,003
1 BISHOP CONSTRUCTION, LLC Low bidder $280,698 +9.6%
2 L & N BRIDGE, LLC $293,988 +14.8% +4.7%
3 SCHIRALLI CONSTRUCTION CORP. $310,964 +21.5% +10.8%
4 RUDY CONSTRUCTION CO. $340,710 +33.1% +21.4%
5 CP3 ENTERPRISES, INC. $349,518 +36.5% +24.5%
6 C3 Construction, Inc. $369,211 +44.2% +31.5%
7 Tri-City Seal Company, Inc. TCS General Contractors $490,004 +91.4% +74.6%

Bid tab: unit prices 20 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 BISHOP CONSTRUC…#2 L & N BRIDGE, L…#3 SCHIRALLI CONST…#4 RUDY CONSTRUCTI…#5 CP3 ENTERPRISES…#6 C3 Construction…#7 Tri-City Seal C…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $10,000.00 $3,000.00 $1,500.00 $5,756.93 $30,000.00 $38,995.29 $10,674.11 $4,702.00
2202(A) 0183 UNCLASSIFIED EXCAVATION23CY $10.00 $30.00 $25.00 $33.78 $15.00 $39.79 $16.68 $68.50
3202(D) 0184 UNCLASSIFIED BORROW83CY $13.00 $30.00 $40.00 $60.00 $35.00 $42.81 $16.68 $148.00
4205(A) 4230 TYPE A-SALVAGED TOPSOIL382CY $13.00 $15.00 $25.00 $26.61 $15.00 $24.36 $8.67 $36.60
5221(C) 2801 TEMPORARY SILT FENCE2,125LF $1.00 $2.00 $2.00 $3.15 $1.75 $2.84 $5.27 $7.30
6230(A) 2806 SOLID SLAB SODDING2,751SY $2.00 $3.00 $5.00 $5.08 $3.00 $5.07 $9.27 $10.20
7310(B) 0149 SUBGRADE, METHOD B2,230SY $3.00 $2.00 $1.50 $4.48 $3.00 $2.44 $5.34 $9.90
8407(B) 0250 TACK COAT237GAL $2.00 $3.00 $4.35 $5.78 $4.00 $18.27 $5.80 $5.40
9411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)265TON $120.00 $90.00 $114.65 $109.33 $110.00 $111.45 $293.34 $236.20
10610(A) 0602 4" CONCRETE SIDEWALK580SY $64.00 $57.00 $55.00 $59.27 $60.00 $53.29 $49.63 $55.00
11610(I) 4610 TACTILE WARNING DEVICE-NEW40SF $25.00 $37.00 $30.00 $21.96 $30.00 $32.89 $24.02 $35.00
12613(A) 0400 12" R.C.PIPE CLASS III30LF $35.00 $56.00 $50.00 $99.08 $80.00 $75.03 $33.46 $217.00
13613(L) 5722 12" PREFAB. CULVERT END SECTION, ROUND6EA $90.00 $1,200.00 $550.00 $984.43 $250.00 $707.66 $609.76 $854.00
14619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $2,000.00 $3,000.00 $1,000.00 $3,298.46 $15,000.00 $6,699.00 $2,001.40 $7,652.00
15632 0300 (PL) SITESCAPING1LSUM $10,000.00 $124,000.00 $128,000.00 $122,590.82 $105,000.00 $132,625.58 $108,271.53 $193,951.00
16809 8090 ENHANCEMENT LIGHTING (COMPLETE)84EA $900.00 $416.00 $320.00 $408.00 $480.00 $389.92 $533.71 $487.00
17880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $9,854.42 $2,200.00 $2,500.00 $2,136.00 $10,000.00 $3,045.00 $3,335.66 $2,577.00
18642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $10,322.69 $8,000.00 $4,000.00 $2,803.10 $6,000.00 $4,263.00 $6,537.89 $7,158.00
19220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $1,250.00 $3,200.00 $1,000.00 $2,246.87 $1,750.00 $3,520.00 $2,001.40 $3,500.00
20641 1552 MOBILIZATION1LSUM $44,399.50 $8,500.00 $25,000.00 $16,802.26 $35,000.00 $15,834.00 $24,350.32 $27,259.00