Bid tab 180014

Let Jan 18, 2018 · Division 2 · Mccurtain Sign up free

‹ Jan 2018 results

RESURFACE (ASPHALT ) SH-3: FROM THE US -259 JUNCTION, EXTEND EAST NEAR IDABEL . PROJECT LENGTH = 8.000 MILES

Let date
Thursday, January 18, 2018
Contract
180014
J/P numbers
31999(04)
District
Division 2
County
Mccurtain
Highway
Limits
RESURFACE (ASPHALT ) SH-3: FROM THE US -259 JUNCTION, EXTEND EAST NEAR IDABEL . PROJECT LENGTH = 8.000 MILES
Project number
SSR-245B(052)SR

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$2,192,180
1 OVERLAND CORPORATION Low bidder $1,683,573 -23.2%
2 THE CUMMINS CONSTRUCTION CO., INC. $1,877,434 -14.4% +11.5%
3 RK Hall Construction $2,288,517 +4.4% +35.9%

Bid tab: unit prices 6 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 OVERLAND CORPOR…#2 THE CUMMINS CON…#3 RK Hall Constru…
1407(B) 0250 TACK COAT9,200GAL $3.50 $0.0100 $3.50 $5.71
2411(C) 5950 SUPERPAVE, TYPE S4(PG 76-28 OK)17,100TON $85.00 $77.95 $82.45 $107.20
3412 5267 COLD MILLING PAVEMENT123,000SY $4.00 $1.30 $2.37 $1.82
4856(A) 8530 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE)168,960LF $0.5000 $0.3500 $0.2800 $0.3300
5880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $10,000.00 $8,600.00 $5,075.00 $8,822.00
6641 1552 MOBILIZATION1LSUM $120,000.00 $122,900.00 $91,445.00 $114,425.83