| 1 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 800 | CY |
$42.00 |
$65.50 |
$50.00 |
$65.50 |
$60.00 |
$34.20 |
$57.63 |
| 2 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 2,246 | TON |
$25.00 |
$28.39 |
$30.00 |
$26.91 |
$22.50 |
$32.00 |
$29.79 |
| 3 | 407(B) 0250 |
TACK COAT | 8,916 | GAL |
$2.60 |
$1.58 |
$2.00 |
$8.29 |
$2.00 |
$1.95 |
$1.66 |
| 4 | 411(C) 5955 |
SUPERPAVE, TYPE S4(PG 70-28 OK) | 10,704 | TON |
$78.00 |
$71.50 |
$70.00 |
$80.53 |
$71.75 |
$71.00 |
$75.04 |
| 5 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 2,663 | TON |
$75.00 |
$57.83 |
$55.00 |
$74.51 |
$57.50 |
$69.00 |
$60.69 |
| 6 | 411(H) 6210 |
SUPERPAVE, TYPE S3(PATCH)(PG64-22OK) | 1,215 | TON |
$120.00 |
$63.09 |
$80.00 |
$133.89 |
$90.00 |
$65.00 |
$66.21 |
| 7 | 412 5267 |
COLD MILLING PAVEMENT | 23,513 | SY |
$2.00 |
$2.10 |
$1.75 |
$1.90 |
$2.50 |
$2.60 |
$2.21 |
| 8 | 413(B) 4863 |
RUMBLE STRIP-METHOD HMA-CYC | 68,316 | LF |
$0.1500 |
$0.1600 |
$0.2500 |
$0.1500 |
$0.2000 |
$0.1500 |
$0.1500 |
| 9 | 414(E) 0225 |
FULL DEPTH P.C. CONCRETE PATCHING(PLACEMENT ONLY) | 5,220 | SY |
$55.00 |
$55.00 |
$60.00 |
$55.00 |
$65.81 |
$80.65 |
$94.00 |
| 10 | 414(G) 5275 |
P.C. CONCRETE FOR PAVEMENT | 1,305 | CY |
$110.00 |
$178.40 |
$182.00 |
$178.40 |
$219.40 |
$206.00 |
$170.00 |
| 11 | 415 6300 |
CONCRETE JOINT SEALING | 36,764.6 | LF |
$5.00 |
$1.95 |
$2.15 |
$1.95 |
$1.88 |
$2.15 |
$2.25 |
| 12 | 416 0100 |
DOWEL BAR RETROFIT | 9,799 | EA |
$30.00 |
$34.40 |
$37.00 |
$34.40 |
$35.75 |
$36.63 |
$32.00 |
| 13 | 425 5195 |
DIAMOND GRINDING CONCRETE PAVEMENT | 36,700 | SY |
$4.00 |
$3.50 |
$4.00 |
$3.30 |
$3.69 |
$3.07 |
$4.80 |
| 14 | 856(A) 8535 |
TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE) | 95,900 | LF |
$0.9000 |
$0.4800 |
$0.5000 |
$0.6000 |
$0.4600 |
$0.7000 |
$0.5600 |
| 15 | 856(A) 8548 |
TRAFFIC STRIPE(MULTI-POLY)(12" WIDE) | 256 | LF |
$6.65 |
$5.26 |
$5.50 |
$6.50 |
$5.00 |
$6.00 |
$2.21 |
| 16 | 856(A) 8555 |
TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE) | 214 | LF |
$9.80 |
$10.51 |
$11.00 |
$13.01 |
$10.00 |
$11.00 |
$11.03 |
| 17 | 856(B) 8860 |
TRAFFIC STRIPE(MULTI-POLY.)(ARROWS) | 28 | EA |
$110.00 |
$105.15 |
$110.00 |
$130.09 |
$100.00 |
$200.00 |
$248.28 |
| 18 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$40,000.00 |
$84,490.00 |
$60,367.36 |
$11,707.65 |
$47,500.00 |
$110,000.00 |
$225,000.00 |
| 19 | 882(A) 8306 |
PORT.CHANGEABLE MESSAGE SIGN | 90 | SD |
$25.00 |
$26.29 |
$26.00 |
$32.52 |
$25.00 |
$35.00 |
$22.07 |
| 20 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$50,000.00 |
$120,000.00 |
$151,000.00 |
$108,119.81 |
$200,000.00 |
$175,000.00 |
$175,000.00 |