RESURFACE (ASPHALT ) US-281: FROM 11.25 MILES WEST OF SH -45, EXTEND EAST. PROJECT LENGTH = 8.00 MILES
- Let date
- Thursday, February 19, 2015
- Contract
- 150082
- J/P numbers
- 29484(04)
- District
- Division 6
- County
- Woods
- Highway
- Limits
- RESURFACE (ASPHALT ) US-281: FROM 11.25 MILES WEST OF SH -45, EXTEND EAST. PROJECT LENGTH = 8.00 MILES
- Project number
- STP-276B(010)3P
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,812,447 | ||
| 1 | J & R SAND COMPANY, INC. Low bidder | $1,600,867 | -11.7% | |
| 2 | THE CUMMINS CONSTRUCTION CO., INC. | $2,105,540 | +16.2% | +31.5% |
| 3 | APAC-KANSAS, INC. | $2,174,622 | +20.0% | +35.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 J & R SAND COMP… | #2 THE CUMMINS CON… | #3 APAC-KANSAS, IN… |
|---|---|---|---|---|---|---|---|---|
| 1 | 202(D) 0184 | UNCLASSIFIED BORROW | 1,825 | CY | $5.00 | $5.00 | $17.15 | $8.92 |
| 2 | 202(H) 0185 | EARTHWORK | 1 | LSUM | $8,000.00 | $30,000.00 | $28,500.00 | $26,506.07 |
| 3 | 230(A) 2806 | SOLID SLAB SODDING | 32,900 | SY | $2.50 | $1.10 | $3.25 | $1.15 |
| 4 | 407(B) 0250 | TACK COAT | 8,500 | GAL | $3.00 | $2.50 | $5.00 | $3.18 |
| 5 | 411(C) 5960 | SUPERPAVE, TYPE S4(PG 64-22 OK) | 15,900 | TON | $94.00 | $85.50 | $103.45 | $113.04 |
| 6 | 411(I) 6310 | SUPERPAVE, TYPE S4(PATCH)(PG64-22OK) | 250 | TON | $125.00 | $145.00 | $230.00 | $193.90 |
| 7 | 413(A) 4861 | RUMBLE STRIP-METHOD HMA-CON | 84,480 | LF | $0.1300 | $0.0400 | $0.1000 | $0.2100 |
| 8 | 856(A) 8530 | TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 144,350 | LF | $0.4000 | $0.3500 | $0.3100 | $0.2900 |
| 9 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $8,000.00 | $4,700.00 | $18,765.00 | $32,108.00 |
| 10 | 641 1552 | MOBILIZATION | 1 | LSUM | $85,000.00 | $50,000.00 | $122,000.00 | $129,450.62 |