RESURFACE (ASPHALT ) US-62: FROM THE HARMON COUNTY LINE , EXTEND EAST. PROJECT LENGTH = 5.97 MILES
- Let date
- Thursday, February 19, 2015
- Contract
- 150060
- J/P numbers
- 29647(04)
- District
- Division 5
- County
- Jackson
- Highway
- Limits
- RESURFACE (ASPHALT ) US-62: FROM THE HARMON COUNTY LINE , EXTEND EAST. PROJECT LENGTH = 5.97 MILES
- Project number
- NHPP-233N(019)3P
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,470,822 | ||
| 1 | CASWELL CONSTRUCTION, INC. Low bidder | $1,599,742 | +8.8% | |
| 2 | CORNELL CONSTRUCTION COMPANY, INC. | $1,651,022 | +12.3% | +3.2% |
| 3 | OVERLAND CORPORATION | $1,673,800 | +13.8% | +4.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 CASWELL CONSTRU… | #2 CORNELL CONSTRU… | #3 OVERLAND CORPOR… |
|---|---|---|---|---|---|---|---|---|
| 1 | 407(C) 0301 | (SP) POLYMER MODIFIED CATIONIC RAPID SET - 1S | 24,279 | GAL | $3.25 | $2.49 | $2.34 | $2.30 |
| 2 | 411(C) 5950 | SUPERPAVE, TYPE S4(PG 76-28 OK) | 14,683 | TON | $85.00 | $98.81 | $102.82 | $99.85 |
| 3 | 412 5267 | COLD MILLING PAVEMENT | 14,406 | SY | $6.00 | $2.48 | $2.63 | $2.85 |
| 4 | 856(A) 8530 | TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 98,500 | LF | $0.5000 | $0.3400 | $0.3800 | $0.3200 |
| 5 | 856(A) 8548 | TRAFFIC STRIPE(MULTI-POLY)(12" WIDE) | 1,500 | LF | $1.70 | $2.95 | $2.00 | $2.75 |
| 6 | 856(A) 8555 | TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE) | 56 | LF | $4.00 | $28.33 | $10.00 | $26.40 |
| 7 | 856(B) 8860 | TRAFFIC STRIPE(MULTI-POLY.)(ARROWS) | 6 | EA | $150.00 | $566.68 | $150.00 | $530.00 |
| 8 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $4,500.00 | $9,831.82 | $4,725.00 | $70,500.00 |