RESURFACE (ASPHALT ) SH-7: FROM 0.10 MILES EAST OF SH -76, EXTEND EAST. PROJECT LENGTH = 4.250 MILES
- Let date
- Thursday, February 19, 2015
- Contract
- 150046
- J/P numbers
- 29184(04)
- District
- Division 7
- County
- Carter
- Highway
- Limits
- RESURFACE (ASPHALT ) SH-7: FROM 0.10 MILES EAST OF SH -76, EXTEND EAST. PROJECT LENGTH = 4.250 MILES
- Project number
- NHPP-021N(056)3P
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,577,380 | ||
| 1 | OVERLAND CORPORATION Low bidder | $1,448,706 | -8.2% | |
| 2 | THE CUMMINS CONSTRUCTION CO., INC. | $1,473,786 | -6.6% | +1.7% |
| 3 | Pavers, Inc. | $1,594,728 | +1.1% | +10.1% |
| 4 | Silver Star Construction Company, Inc. | $1,626,810 | +3.1% | +12.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 OVERLAND CORPOR… | #2 THE CUMMINS CON… | #3 Pavers, Inc. | #4 Silver Star Con… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 409(A) 4242 | FABRIC REINFORCEMENT | 63,220 | SY | $1.00 | $0.7500 | $0.9000 | $1.58 | $1.05 |
| 2 | 409(B) 4268 | BITUMINOUS BINDER | 15,810 | GAL | $3.25 | $2.60 | $4.00 | $3.33 | $3.90 |
| 3 | 411(C) 5955 | SUPERPAVE, TYPE S4(PG 70-28 OK) | 10,780 | TON | $90.00 | $83.25 | $86.50 | $85.33 | $88.40 |
| 4 | 411(C) 5960 | SUPERPAVE, TYPE S4(PG 64-22 OK) | 4,150 | TON | $90.00 | $74.35 | $75.00 | $78.33 | $80.65 |
| 5 | 412 5267 | COLD MILLING PAVEMENT | 63,220 | SY | $1.00 | $1.05 | $0.8000 | $1.58 | $2.40 |
| 6 | 413(B) 4863 | RUMBLE STRIP-METHOD HMA-CYC | 30,100 | LF | $0.2500 | $0.1700 | $0.2000 | $0.8000 | $0.2000 |
| 7 | 855(A) 8840 | TRAFFIC STRIPE(PLASTIC)(THIN LINE)(4" WIDE) | 83,331 | LF | $0.4000 | $0.3300 | $0.4000 | $0.4800 | $0.3500 |
| 8 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $15,000.00 | $55,200.00 | $20,000.00 | $33,300.00 | $24,206.65 |