RESURFACE (ASPHALT ) SH-86: FROM SH-51 EXTEND NORTH 3.01 MILES TO THE NOBLE COUNTY LINE. PROJECT LENGTH = 2.91 MILES
- Let date
- Thursday, January 23, 2014
- Contract
- 140066
- J/P numbers
- 29616(04)
- District
- Division 4
- County
- Payne
- Highway
- Limits
- RESURFACE (ASPHALT ) SH-86: FROM SH-51 EXTEND NORTH 3.01 MILES TO THE NOBLE COUNTY LINE. PROJECT LENGTH = 2.91 MILES
- Project number
- STPY-260C(011)3P
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $430,136 | ||
| 1 | THE QUAPAW COMPANY Low bidder | $436,240 | +1.4% | |
| 2 | HASKELL LEMON CONSTRUCTION CO. | $504,725 | +17.3% | +15.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 THE QUAPAW COMP… | #2 HASKELL LEMON C… |
|---|---|---|---|---|---|---|---|
| 1 | 202(D) 4781 | UNCLASSIFIED BORROW (TOPSOIL) | 1,500 | CY | $13.00 | $6.00 | $25.00 |
| 2 | 202(E) 0186 | SELECT BORROW | 200 | CY | $18.00 | $32.50 | $35.00 |
| 3 | 202(H) 0185 | EARTHWORK | 1 | LSUM | $10,000.00 | $22,500.00 | $30,000.00 |
| 4 | 230(A) 2806 | SOLID SLAB SODDING | 500 | SY | $3.00 | $5.50 | $4.00 |
| 5 | 411(B) 5945 | SUPERPAVE, TYPE S3(PG 64-22 OK) | 300 | TON | $100.00 | $98.25 | $110.00 |
| 6 | 411(C) 5960 | SUPERPAVE, TYPE S4(PG 64-22 OK) | 3,900 | TON | $90.00 | $88.25 | $94.50 |
| 7 | 412 5267 | COLD MILLING PAVEMENT | 3,000 | SY | $3.00 | $4.50 | $5.00 |
| 8 | 619(B) 4726 | REMOVAL OF CURB AND GUTTER | 67 | LF | $8.00 | $20.00 | $25.00 |
| 9 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $5,000.00 | $7,000.00 | $10,000.00 |