ENHANCEMENT (SIDEWALK IMPROVEMENT ) SH-56: FROM 14TH STREET NORTH TO 1ST STREET IN WEWOKA. PROJECT LENGTH = 0.9 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTABLE .
- Let date
- Thursday, February 21, 2013
- Contract
- 130115
- J/P numbers
- 30045(04)
- District
- Division 3
- County
- Seminole
- Highway
- Limits
- ENHANCEMENT (SIDEWALK IMPROVEMENT ) SH-56: FROM 14TH STREET NORTH TO 1ST STREET IN WEWOKA. PROJECT LENGTH = 0.9 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTABLE .
- Project number
- STPY-267E(014)SG
Bidders 8
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $242,282 | ||
| 1 | Redlands Contracting, LLC Low bidder | $205,287 | -15.3% | |
| 2 | GLOVER & ASSOCIATES, INC. | $209,176 | -13.7% | +1.9% |
| 3 | T. McDonald Construction, Inc. | $217,425 | -10.3% | +5.9% |
| 4 | AUSTIN PAVING LLC | $224,116 | -7.5% | +9.2% |
| 5 | JLT Contracting, LLC | $252,548 | +4.2% | +23.0% |
| 6 | RUDY CONSTRUCTION CO. | $269,426 | +11.2% | +31.2% |
| 7 | STRICKLIN CONSTRUCTION, INC. | $277,232 | +14.4% | +35.0% |
| 8 | TI-ZACK CONCRETE, LLC | $398,330 | +64.4% | +94.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Redlands Contra… | #2 GLOVER & ASSOCI… | #3 T. McDonald Con… | #4 AUSTIN PAVING L… | #5 JLT Contracting… | #6 RUDY CONSTRUCTI… | #7 STRICKLIN CONST… | #8 TI-ZACK CONCRET… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 610(A) 0605 | 6" CONCRETE SIDEWALK | 2,710 | SY | $60.00 | $47.23 | $47.00 | $44.10 | $42.00 | $52.05 | $60.00 | $55.00 | $100.00 |
| 2 | 610(B) 0604 | 6" CONCRETE DRIVEWAY | 590 | SY | $60.00 | $50.20 | $37.00 | $44.10 | $46.00 | $53.25 | $65.00 | $60.00 | $100.00 |
| 3 | 610(I) 4610 | TACTILE WARNING DEVICE-NEW | 448 | SF | $32.00 | $22.00 | $27.00 | $23.00 | $52.00 | $29.60 | $24.00 | $30.00 | $35.00 |
| 4 | 610(I) 4615 | TACTILE WARNING DEVICE-RETROFIT | 56 | SF | $76.00 | $35.00 | $35.00 | $23.00 | $105.00 | $41.40 | $24.00 | $32.00 | $35.00 |
| 5 | 619(B) 4766 | REMOVAL OF CONCRETE DRIVEWAY | 590 | SY | $7.50 | $5.55 | $15.00 | $18.37 | $14.00 | $8.90 | $9.00 | $20.00 | $18.00 |
| 6 | 619(B) 4792 | REMOVAL OF SIDEWALK | 2,230 | SY | $5.50 | $3.85 | $9.00 | $18.37 | $14.00 | $6.00 | $9.00 | $25.00 | $9.00 |
| 7 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $5,000.00 | $16,000.00 | $5,000.00 | $6,000.00 | $9,500.00 | $39,945.00 | $25,000.00 | $5,000.00 | $15,000.00 |
| 8 | 642(B) 0096 | CONSTRUCTION STAKING LEVEL II | 1 | LSUM | $4,000.00 | $8,000.00 | $12,000.00 | $2,500.00 | $5,000.00 | $5,920.00 | $6,000.00 | $5,000.00 | $5,000.00 |